Planning
Planning
Installation 0%
hoist
Bolt tightening control 0%
fasteners preparation 0%
installation 0%
Structure
Hoist unit Bolt tightening control 0%
Touch-up painting 0%
wire Change 0% waiting for delivery
Oil change 0%
Gearbox
Shrink disk bolt tightening 0%
feeding head to dismantle after alignment & install 0% greasing nipples & spiral locking
after screw erection pins to deliver by FLS
Vertical screw
sections alignment to be checked 0% checking in the 4 positions Induproj/FLS
Installation 0%
hoist
Bolt tightening control 0%
fasteners preparation 0%
installation 0%
Structure
Hoist unit Bolt tightening control 0%
Touch-up painting 0%
wire Change 0% waiting for delivery
Welding 0%
additional stiffeners CMS
Touch-up painting 0%
torque limiter Changing the old ones 0%
Slewing tower
access Bolt tightening control 0%
slewing gear Bolt tightening control 0% After all CW installation
C.W boom sleeve keeprs installation 0% polyethylene sheet
lubrication routing
bogies
installing new routing 0% voith
lubrication routing changing the old lubrication pump
Gantry area 0%
box
complete the installation of the 3
slewing tower 0%
lubrication pump box
Horiwontal screw new routing installation 0% voith
vertical screw new routing installation 0% voith