TWJO-ITP-EMB-0003-CHK-001 Revb Accessories Retaining Wall RRR Method Statement

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

TOKYU-WIKA JOINT OPERATION

Surface Section CP101 & CP102


Construction of Jakarta Mass Rapid Transit Project

RRR WALL CONSTRACTION CHECKLIST

Site Location : Date :


STA / Area : Layer Number :

Witness Point/ Conformance


Retaining Wall Accessories Checking Item Remarks
Information Yes No

Layout and Stacking out before


constraction acccessories Retaining As per approved drawing Information
wall

Installation of Wall Anchor Position should be as per approved drawing Witness Point

Position and cutting length should be as per


Installation of geogrid tensar (RT-3) Witness Point
approved drawing

Installation of L-type Steel frame Position on top of tensar Information

Installation of Preventin Sheet Position on top of L-type steel frame Information

Should be driven in at the slop side of steel


Anchor Pin Installation bar so as that L-type steel frame would not Information
move

Every 4 m2 or as per approved drawing,


Installation of drainage Pipe Filter should be attached at the embankment Information
side

Spread at the corner of L-type steel frame,


Spreading and compaction drainage shall be compacted and shape with tamping
Information
material machine, shocked shall be installed into
drainage material while compaction work

Tensar and preventing sheet rolling up Tensar and preventing sheet shall be fixed
Witness Point
and anchor pit installation by binding wire

Prepare by Checked by Verified by

Supervisor Civil Engineer


(………………………………………………………….)

TWJO-ITP-EMB-0003-CHK-001 revB Page 1 / 1