Note On Working Estimate - Package-2
Note On Working Estimate - Package-2
Note On Working Estimate - Package-2
Kindly peruse the reference cited where in the General Manager( Engg) APADCL has submitted the GST
Working estimate for the work “Construction of green field no frills airport in Orvakal Pacakge-2” for
Rs 30.00 Crores and requested to accord technical approval for processing the pending bills
The following points are submitted :
Name of the work : Construction Of Greenfield No frills Airport at Orvakal in Kurnool District
(Package-2
Estimate Cost : Rs.26.50 Crores
Administrative Sanction : G.O Rt No: 123, dt:8.8.2017 of E I & I ( Airport) Dept.
Technical Sanction : TS.No.2/2017-18, dt.17.08.2017 of the Chief General Manager Engg)FAC BIACL,
Hyderabad. .
Name of the contractor : M/s Standard Infratech India Pvt Ltd
Further it is submitted that Technical committee during its meeting held on 18.9.2020 instructed to
complete Passenger Terminal Building Air conditioning with the existing contractor. Accordingly the AC
proposals are modified
The following deviations are already approved by Managing Director APADCL vide this office memo No
APADCL/ package-2/ deviations, dt. 21.09.2020
Sl.No As per original sanction Deviation approved
Further Managing Director ,APADCL approved the following DG sets vide This office Memo.
No. APADCL/ package 2/DG sets deviation s, dt. 29.09.2020.
1 Diesel Generator 125 KVA(3 Nos) Diesel Generator 250 KVA (2Nos)
In his letter the GM ( Engg) has stated that the following items are approved and the rates are not covered in
state SSR and DSR items ,hence based on quotations the Lowest rates are adopted
During DGCA inspection & BCAS inspections the provision of Fire pit is mentioned as mandatory
requirement in Airport and hence taken up with Cement concrete as per standard design
Additional road net work behind ATC Admin Building created to facilitate hassle free moment of fire
tenders from water filling point to CFR road connectivity. This road was not contemplated originally
as the entire area was rocky terrain which was later leveled to facilitate the provision of connecting
from water tank area to fire tenders passing Bay The above two provisions cost worked out to
Rs 13,16,457
5. Non Directional Beacon (NDB)
It is an important Facility in the airport for guiding the aircraft landing and is being handled by Airport
Authority of India. The provision of NDB was not contemplated in the original estimate tender . This
additional work was included in Package-2 as it is to be completed well before the inauguration time. As
per the directions issued by the authority NDB taken up and completed and the Cost worked out to
Rs 20,13,609.30
6. Either side of PTB Horticulture Rs.18,35,017
7. Maintenance to the existing Horticulture for the years 2019-20 and 2020-21 Rs 50,73,998
8. IMD and Runway paintings
The Meteorological equipment & tower installation and connected electrical and Communication net work
taken up as these are mandatory requirements which are not included in civil works of Original tenders.
As per the instructions of authority the IMD related works near the runway and ATC tower were taken up
Also before the inauguration of Airport fresh coating of Runway and apron paintings taken up in
Package-2 as per the directions of authority
9. OFC cable laying for BSNLRs 26,00,850
10. Gate at entrance Rs 18,50,000
The total estimate cost worked out to Rs 30.00crores against original cost of rs 26.50crores. The additional cost
being due to the extra provision required as per DGCA/BCAS/BSNL/IMD/AAI guidelines and instruction
during sections carried out by the respective agencies.
Further the General Manager( Engg) stated that all the major works are completed and the Airport was
commissioned on 28.3.2021 and hence the estimate may be approved for processing the bill and to obtain
revised estimate sanction
In this connection the following points are submitted
As seen from the estimate the total amount is arrived at Rs 30.00Crores
S.NO. DESCRIPTION OF WORKS
As per approved
A CIVIL WORKS working wstimate
Proposed GST Estimate
2,937,4 2,036,963.
1 Cost of Underground Water Tank
42 00
5,403,4 4,649,481.
2 Cost of Sub Station Works
84 00
46,202,7 39,973,584.
3 Cost of PTB Building
27 00
18,283,1 15,183,933.
4 Cost of ATC Building
69 00
15,796,1 13,142,909.
5 Cost of ATC Tower
93 00
5,428,5 4,720,194.
6 Cost of Overhead Water Tank
39 00
12,056,0 5,031,475.
7 Cost of Watch Tower (4 No.s)
96 03
106,107,6 84,738,539.
TOTAL Civil Works
50 03
B OTHER WORKS
11,311,3 4,476,259.
8 Cost of Public Health Works
36 00
71,395,1 95,969,541.
9 Cost of Electrical Works
10 78
6,149,1 6,351,999.
10 Cost of Fire Fighting Works
02 00
3,117,4 1,753,987.
11 Cost of HVAC Works
52 00
33,861,8 34,387,157.
12 Cost of Interior Works (PTB)
12 00
2,946,6 4,037,650.
13 Cost of Signages
00 00
14,032,040.
Aircondition to PTB
00
128,781,41
TOTAL OTHER WORKS 2
161,008,633.78
C OTHER WORKS
179,636.
14 External works around building
00
220,040.
15 Septic Tank and signal square
20
1,241,647.
16 Ground support equipment
41
1,316,457.
17 Fire Pit and road work
34
2,356,585.
18 Non Directional Beacon (NDB)and IMD
30
1,835,017.
19 Eithie side of the PTB building Horticulture
00
Maintenance to the existing Horticulture for the 5,073,998.
20
years 2019-20 and 020-21 00
265,000,0 300,000,0
GRAND TOTAL 00 00
3. All DSR items are to be modified with DSR data duly applying service tax with respective
standard percentages and 5% VAT on materials
4. The quotation rates are to taken into consideration for non scheduled items
5. The GM ( Engg) has also proposed maintenance of Horticulture for two years 2019-20 and 2020-
21@Rs. 5,073,998 in Package -2 estimate
6. All the deviated items mentioned are completed and the Airport was already commissioned
Hence the file is submitted for approval of deviations mentioned above and if agreed Government
may be requested to accord Revised administrative sanction for Rs 30.00crores
Submitted for orders for scruitiny of the estimate