Note On Working Estimate - Package-2

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 6

Note submitted :

Sub: APADCL—Construction of green field no frills airport in Orvakal Pacakge-2- Working


estimate-2 submitted by GM( Engg) for approval – Req – Reg.
Ref: Letter no Nil /APADCL/Package-II works/Kurnool Airport/2021-21 dt 20.6.2021 of the
GM( Engg),APADCL

Kindly peruse the reference cited where in the General Manager( Engg) APADCL has submitted the GST
Working estimate for the work “Construction of green field no frills airport in Orvakal Pacakge-2” for
Rs 30.00 Crores and requested to accord technical approval for processing the pending bills
The following points are submitted :
Name of the work : Construction Of Greenfield No frills Airport at Orvakal in Kurnool District
(Package-2
Estimate Cost : Rs.26.50 Crores
Administrative Sanction : G.O Rt No: 123, dt:8.8.2017 of E I & I ( Airport) Dept.
Technical Sanction : TS.No.2/2017-18, dt.17.08.2017 of the Chief General Manager Engg)FAC BIACL,
Hyderabad. .
Name of the contractor : M/s Standard Infratech India Pvt Ltd

Date of agreement : 18.08.2017.


Date of Handing over of site : 18.08.2017
Period of Contract : 9 months up to 17.5.2018
EOAT already granted : upto 31.12.2020
Contract value : Rs.22,56,68,043/-
Working estimate -1 was approved by CGM(Engg) dt 17.11.2018
Now the GM ( Engg) has submitted GST working estimate for Rs 30.00 Crores for technical approval

Further it is submitted that Technical committee during its meeting held on 18.9.2020 instructed to
complete Passenger Terminal Building Air conditioning with the existing contractor. Accordingly the AC
proposals are modified

The following deviations are already approved by Managing Director APADCL vide this office memo No
APADCL/ package-2/ deviations, dt. 21.09.2020
Sl.No As per original sanction Deviation approved

Septic RCC tank proposed until finalization of


1 In the BOQ the STP is proposed with FRP TANK.
STP as recommended by GM( ngg)

Windows and frames in ATC Admin Building to be


2 Aluminum Windows and frames
changed to UPVC
Providing and fixing SMC panel tank of approximate
capacity 50000 liters (2 No’s) standard approved make Single 90kl SMC Panel tank.as work is already
3
including installation at approximate height of 15 commenced
meters complete in all respect as per site requirement.
Electrical poles and accessories for approach As per the deviations proposed by GM( Engg)
4
internal and pheripheral lighting Items 1 to 7 only approved
Supply & fixing of senstronic concealed type
Flat back half stall urinal (590 x 375 x 390) (Jaquar
5 flushing valve urinal complete set with installation
make) sanitary item
box with control cock, chrome plated.
There is No proposal in Original Estimate for Pump 2 No. of mono block Kirloskar make 5HP – 3-
6
sets to OH tank Phase pump sets are proposed

500KVA (2 No’s) (Wet type) Transformers as


Cast Resin (Dry type) Transformers KIRLOSKAR
7 additional power requirement and instruction by
400 KVA (2 No’s).sanctioned
Managing Director APADCL during site visit.

9 Fire Alarm system & Accessories As recommended by GM ( Engg)


In place of 6sqmm
2 core XLPE ,6sqmm 4 core XLPE cable shall be
10 Alternate proposal for laying Electrical cable
used . The laying of cable shall be as per actual
layout of main feeder, sub feeder and light poles
   

Further Managing Director ,APADCL approved the following DG sets vide This office Memo.
No. APADCL/ package 2/DG sets deviation s, dt. 29.09.2020.

Sl.No As per original sanction Deviation now approved

1 Diesel Generator 125 KVA(3 Nos) Diesel Generator 250 KVA (2Nos)

In his letter the GM ( Engg) has stated that the following items are approved and the rates are not covered in
state SSR and DSR items ,hence based on quotations the Lowest rates are adopted

1. DSP based audio Controller


2. EPABX fully computerized IP system
3. 4 level IVR software with 6 different languages
4. Digital phones
5. Full HD LED professional Display monitor
6. 500 Watt RMS single channel class D audio power amplifier
7. 8 passenger elevator
8. MAIN LT Panel
9. Capacitor panel(150KVAR)
10. MDB-3 Pump room panel
11. 3 phase, 415, 50Hz, water cooled multi cylinder diesel generator set
12. PVC rain water pipes
13. High pressure laminate screens
14. Glass door with Alexa systems
15. Frame less glass doors
16. Single double sided sign boards
17. Hand baggage X-BIS with all accessories
18. SMC panel tanks
19. Soil waste vent pipes
20. Aerocon panel…..etc
Additional works proposed by GM ( EEngg) and completed now and sought for approval ( Enclosed the
GM( Remarks)
1. External works around buildings Rs. 1,79,636
2. Septic Tank Rs.86,533.20
3. Ground support equipment
To park all ground handling vehicles near apron a stable black top or cement conctrete surface is
required. The provisio is not contemplated in original estimate. As the authority instructed to provide a
black top surface to the east side ofPTB, a 20mx20m black top surface taken up urgently as airport
inauguration proposed on 25.8.2021. The cost of the provision worked out to Rs 12,41,647
4. Fire pit and Roads: works to connect waters upply location to fire tenders

During DGCA inspection & BCAS inspections the provision of Fire pit is mentioned as mandatory
requirement in Airport and hence taken up with Cement concrete as per standard design
Additional road net work behind ATC Admin Building created to facilitate hassle free moment of fire
tenders from water filling point to CFR road connectivity. This road was not contemplated originally
as the entire area was rocky terrain which was later leveled to facilitate the provision of connecting
from water tank area to fire tenders passing Bay The above two provisions cost worked out to
Rs 13,16,457
5. Non Directional Beacon (NDB)
It is an important Facility in the airport for guiding the aircraft landing and is being handled by Airport
Authority of India. The provision of NDB was not contemplated in the original estimate tender . This
additional work was included in Package-2 as it is to be completed well before the inauguration time. As
per the directions issued by the authority NDB taken up and completed and the Cost worked out to
Rs 20,13,609.30
6. Either side of PTB Horticulture Rs.18,35,017
7. Maintenance to the existing Horticulture for the years 2019-20 and 2020-21 Rs 50,73,998
8. IMD and Runway paintings
The Meteorological equipment & tower installation and connected electrical and Communication net work
taken up as these are mandatory requirements which are not included in civil works of Original tenders.
As per the instructions of authority the IMD related works near the runway and ATC tower were taken up
Also before the inauguration of Airport fresh coating of Runway and apron paintings taken up in
Package-2 as per the directions of authority
9. OFC cable laying for BSNLRs 26,00,850
10. Gate at entrance Rs 18,50,000

The total estimate cost worked out to Rs 30.00crores against original cost of rs 26.50crores. The additional cost
being due to the extra provision required as per DGCA/BCAS/BSNL/IMD/AAI guidelines and instruction
during sections carried out by the respective agencies.
Further the General Manager( Engg) stated that all the major works are completed and the Airport was
commissioned on 28.3.2021 and hence the estimate may be approved for processing the bill and to obtain
revised estimate sanction
In this connection the following points are submitted
As seen from the estimate the total amount is arrived at Rs 30.00Crores
S.NO. DESCRIPTION OF WORKS    
As per approved
A CIVIL WORKS working wstimate
Proposed GST Estimate
2,937,4 2,036,963.
1 Cost of Underground Water Tank
42 00
5,403,4 4,649,481.
2 Cost of Sub Station Works
84 00
46,202,7 39,973,584.
3 Cost of PTB Building
27 00
18,283,1 15,183,933.
4 Cost of ATC Building
69 00
15,796,1 13,142,909.
5 Cost of ATC Tower
93 00
5,428,5 4,720,194.
6 Cost of Overhead Water Tank
39 00
12,056,0 5,031,475.
7 Cost of Watch Tower (4 No.s)
96 03
106,107,6 84,738,539.
  TOTAL Civil Works
50 03
B OTHER WORKS    
11,311,3 4,476,259.
8 Cost of Public Health Works
36 00
71,395,1 95,969,541.
9 Cost of Electrical Works
10 78
6,149,1 6,351,999.
10 Cost of Fire Fighting Works
02 00
3,117,4 1,753,987.
11 Cost of HVAC Works
52 00
33,861,8 34,387,157.
12 Cost of Interior Works (PTB)
12 00
2,946,6 4,037,650.
13 Cost of Signages
00 00
14,032,040.
  Aircondition to PTB  
00
128,781,41
  TOTAL OTHER WORKS 2
161,008,633.78
     
C OTHER WORKS    
179,636.
14 External works around building  
00
220,040.
15 Septic Tank and signal square  
20
1,241,647.
16 Ground support equipment  
41
1,316,457.
17 Fire Pit and road work  
34
2,356,585.
18 Non Directional Beacon (NDB)and IMD  
30
1,835,017.
19 Eithie side of the PTB building Horticulture  
00
Maintenance to the existing Horticulture for the 5,073,998.
20  
years 2019-20 and 020-21 00

Estimate for the OFC ( Optical fibre cable ) laying 2,600,850.


21  
Charges 00
Estimate for construction of steel gate at 1,850,000.
22  
entrance 00
16,674,231.2
TOTAL OTHER WORKS  
5
234,889,06
A+B+C 262,421,404.06
2
424,36 500,000.
23 Seignorage charges
6 00
11,744,453. 31,490,568.
24 Add 12% GST
00 49
25 Add 1% Labour Cess 2,348,890. 2,624,214.
00 04
904,3 262,421.
26 Insurance 0.385% / NAC 0.1%
22 40

Unforseen items such as Contingencies, and price 14,688,9 2,701,392.


27
escalation etc., 07 00

265,000,0 300,000,0
  GRAND TOTAL 00 00
     

Which is 13.20 % excess over original sanction of Rs 26.50crores

Original Estimate amount put to tender is Rs. 23,06,50,085


Working estimate-1 ECV Rs. 23,48,89,062
GST Working estimate ECV RS. 262,421,404.06
which is13.77% excess over original ECV

Hence submitted the following


1. The estimate cost was increased from Rs 26.50Crores to Rs 30.00Crores Hence revised
administrative sanction is to be obtained
2. All the rates are to be corrected to GST reformulated SSR

3. All DSR items are to be modified with DSR data duly applying service tax with respective
standard percentages and 5% VAT on materials
4. The quotation rates are to taken into consideration for non scheduled items
5. The GM ( Engg) has also proposed maintenance of Horticulture for two years 2019-20 and 2020-
21@Rs. 5,073,998 in Package -2 estimate
6. All the deviated items mentioned are completed and the Airport was already commissioned

Hence the file is submitted for approval of deviations mentioned above and if agreed Government
may be requested to accord Revised administrative sanction for Rs 30.00crores
Submitted for orders for scruitiny of the estimate

PM( Engg) GM(Engg) CGM(T) MD & CEO

You might also like