Professional Documents
Culture Documents
OPGW Installation Manual
OPGW Installation Manual
2010. 4. 13
1
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
CONTENTS
1. General
1.1 General
1.2 Attention in general
3. Installation Plan
3.1 Installation plan
3.2 Management materials and fitting
3.3 Preparation of installation
4. Stringing Plan
4.1 Stringing Plan
4.2 Location of drum site
4.3 Location of engine site
4.3 Stringing tension
4.4 Block attachment
4.5 Sagging tension
6. Stringing
6.1 Arrangement of stringing equipment
6.2 Stringing method and procedure
7. Sagging
7.1 Method of sag measurement
7.2 Clipping
7.3 arrangement of accessories and fitting
8. Jointing
8.1 General
8.2 Flow of jointing procedure
8.3 Jointing works
2
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
START
Route Survey
Moving equipment
Prepare Pulling
Stringing
sagging
No
OPGW Test Inspection
Yes
splicing
Final Test
Finish
3
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
1. General
1.1 General
OPGW(Optical ground wire) is generally composed of optical fibers in the center and AW
wire for outer layer. Accordingly, it is necessary to take care of OPGW during stringing to
avoid splicing not only it’s mechanical and electrical properties, but also it’s optical properties.
Installation procedure for OPGW is basically similar to that for conventional overhead ground
wires in overhead transmission line construction, however particular attention must be paid
on the protection of optical components and jointing of optical fibers.
This paper describes the stringing procedure and equipment of OPGW briefly.
1) Water proof
Each ends of OPGW are usually treated as waterproof at the factory before shipment.
Keen attention must be paid to maintain these waterproof treatment without spoiling and
the sealing should be opened at the time of optical fiber jointing after completion of
stringing
2) Bending
For the protection of optical components included, it is very important to avoid the bending
at sharp angle or the kind of OPGW during handling. For instance the minimum diameter
for coiling up of OPGW at site is recommended approx. 1 meter and also the diameter of
the stringing block is recommended to be more than 20 times of OPGW out-diameter.
4) Jointing
Jointing of OPGW is recommended to be made with a joint box, which will be installed on
the tower. The necessary quantity of join box is related to continuous packing length of
OPGW on one reel and arrangement of towers. Also, the total necessary quantity of
OPGW should be calculated from the route length of the transmission line and an adequate
surplus length of OPGW leading down to the joint box.
If necessary, inspection on breakage of optical fibers can be made before paying off the
OPGW at site.
4
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
6) The others
All the bolts of accessories and fitting, especially for strain clamp, must be correctly
tightened up to specified torque by means of qualified torque wrench respectively.
The short of fastening torque causes less gripping force and excess fastening causes
deflection of aluminum tube.
Stringing sectors should be determine that before stringing to make an investigation into the
following.
5
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
3. Installation Plan
3.1 Installation plan
1) Following plans are to be made for the completion of the installation in time.
1) Inspection of material
Tender shall inspect all materials for proper documentation and physical damage.
Any material which is not properly documented or is damaged shall not be used.
All material other than OPGW reels shall be stored off the ground or on wooden pallets.
All OPGW reels shall be identified and stored in group of similar lengths and shall be
braced against accidental rolling.
To storage complement packing condition.
To storage each other use and type.
Extreme care shall be exercised during the loading, transporting unloading and using of
materials.
A reel shall be lifted using a spreader bar protruded through the arbor hole it, or fork lift
truck will be used.
6
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
There must be furnished with cable telephone and wireless telephone so as to be able to
make rapid and affirmative liaison always within the stringing sectors.
High voltage overhead transmission line and low voltage distribute line.
Rail road, Highway and buildings.
Telephone and signal lines.
Fruit trees, ornamental plants and agricultural produce being worried of damages.
The other sites to be regarded as necessary.
In case power lines under construction approaches or being crossed with other existing
power line, a high voltage might occur on the wire by static inductance, electronic
inductance reaction, so that adequate counter measure of inductance prevention must be
taken according to the conditions.
4. Stringing Plan
4.1 Stringing plan
The stringing plan should be decided by taking into account the topography over which the
transmission line shall pass through, suitable work area, stringing distance and situation of
crossed objects.
Drum site should not deviate from the transmission line, and it should be decided by
following.
7
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
Engine puller site should be decided near the transmission line by considering following.
The tensile strength to be added to block attachment wire for stringing must satisfy following
condition.
Out-diameter of block is more than 20 times of OPGW out-diameter(ex.450mm). In case of
end towers such as puller-area, tensioner-area, The block of 25 times of OPGW out-diameter
shall be recommended(ex.600mm block). And If line-angle is more than an angle of 300,
double block shall be recommended.
At sagging works, the sagging tension must be checked in the case of following
8
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
Tensioner 3 ton Ea 1
Block Φ450 Ea 20
Block Φ600 Ea 6
Running Board 20 Kg Ea 4
Swivel 3 ton Ea 10
Reel Winder Ea 6
Shackle Ea 30
Wire Connector Ea 20
Wire Clamp Ea 20
9
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
Knife 1
Pliers 2
Hexagon wrench 1
OTDR 1
Electric reel 1
Electric cord 1
10
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
6. Stringing of OPGW
6.1 Arrangement of stringing equipments
1) Establishment of tensioner
The stringing tensioner should be arranged in consideration of the distance from the first
tower to tensioner. Also, the tensioner should be arranged in the straight position to the
stringing block at the first tower. The distance “L” between tensioner and the first block is
required to be longer than the necessary OPGW length of leading down along with the
tower, which will make the handling works of OPGW easy.
60。
60。
above
above
Engine Puller
Tensioner L : Min. distance
L’ L from 1st tower L
L = tan Θx h
= tan 60。 x h
=2xh
Pull up tension should not be reached to capstan and if necessary, direction switching
11
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
Starting, stop and speed controlling must be done in close contact with respective
working site.
3) Attachment of block
Minimum diameter of stringing block is recommended as not less than 20 times of the
OPGW diameter and also shall be more than 450mm in diameter, and also the surface of
groove should be with aluminum or urethane for protection of OPGW surface.
In case of end towers such as puller-area, tensioner-area, The block of 25 times of
OPGW out-diameter shall be recommended(ex.600mm block).
If line-angle is more than an angle of 300, double block shall be recommended.
In case of high level difference such as an angle of 30o at some tower on stringing,
double block shall be recommended.
12
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
Running board
2 counter weight
Polite Wire
OPGW
Engine
Stringing Block Reel
Puller
winder
Suspension Tower
Suspension Tower
Tension Tower
Drum
Tensioner
Drum Site
Unless other wide specified on the technical specification. Following equation are for
further detailed stringing tension calculation.
Actual stringing tension shall be monitored by pulling tension gages equipped on bull wheel
tensioner.
13
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
Treat the OPGW end part in order to prevent Fiber damage caused by string
Tension or gripping force as below.
- Removal AS Wire and cutting the Al Tube(OP Unit) around 1.2m position.
14
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
- Repositioning the AS Wire and making gap between Al-Tube and Al-Road
2~3cm
Attach the running board with two counter weight tails tandem between the wire rope and
OPGW in order to prevent OPGW from twisting during stringing works.
Swivel
OPGW
Pilot Wire Braid Clamp
Weight
The temporary clamp at leading end of OPGW should provide enough gripping force
against pulling throughout stringing works, and the clamps such as braid clamp,
preformed armor grip and compression type clamp are recommended in proper size.
Attention must be paid to the diameter of OPGW, because it is sometimes different from
that of corresponding conventional overhead ground wires.
Come-along clamp of wedge type can be used to OPGW, but the wedge must be
suitable to it in size and diameter in order to prevent the aluminum tube from excess
deflection.
15
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
Surplus length of OPGW is necessary to lead down from the strain clamp on the top of
tower to the joint box along with the arm and tower structures. The position of joint box is
subject to specific requirement by the customers or the height of tower. For the ease of
stringing works, it is recommended to mark the length approximately in advance at the
drum site.
7. Sagging
For the measurement of sagging, the easy and low tolerance method is applicable among
the following methods.
Methods and procedures for sagging of OPGW are the same as those of normal overhead
ground wire except fittings such as suspension clamp and tension clamp and tool to pull the
OPGW for tensioning.
For determination of sags, the amount of OPGW can be also regarded as equivalent to that
of conventional ground wires.
The sag measured span in the sagging area shall be basically decided to the following
table
Not more than 3 spans Not less than 1 span The longest span
Not more than 6 spans Not less than 2 spans The longest span & the last span
2) After stringing the OPGW shall be sagged using information furnished on the sag and
tension chart. Unless otherwise specified on technical specification.
16
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
4) The sag shall be controlled with transits or scopes using calculated target, horizontal line of
sight or calculated angle of sight method.
At the time of sagging OPGW, the sag of any given phase should be within 6 inches of
the theoretical value for existing temperature condition. The sag of all phase of a circuit
shall have similar tolerances
6) OPGW tension between each sag section shall be equalized and this shall be determined
by the vertical position of the suspension clamps on the last clipped structure of the
preceding sag section.
7) The tension clamp and suspension clamp must be designed taking into account the
slipping strength and the shape which prevents any damage of surface and deformation of
aluminum pipe and optical fibers.
8) For pulling the OPGW with tension, the device of come-along is to be recommended by
experience. Guy-grip is also available instead of come-along, but it is troublesome in
handling to use it as a tool.
9) After completion of sagging and clipping, the surplus OPGW is to be lain temporary in the
tower body in coil (Diameter of coil is approximately 1.0 - 1.5 m) and fixed on the tower. It
is important that precautions must be taken to prevent any damage of OPGW.
10) Vibration dampers must be fitted at OPGW suspension and tension points. Normal type of
dampers shall be attached to the OPGW over the suitable preformed armor rods which
will protect OPGW and its aluminum pipe from any damage.
7.2 Clipping
1) This is one big difference between OPGW and normal overhead ground wire in stringing.
Two lines of OPGW can not be jointed by a mid span joint in a span. Therefor, the jointing
operating shall be made on the tension tower and for this joint it is necessary to add the
surplus of approximately 20m length of OPGW at the either end in one reel.
The length of surplus is accurately to be get in accordance with tower construction and
location of joint box and also with selection of type of jumper device, that is splicing type or
non-splicing type.
2) When only one OPGW reel length is to be strung at once time, the line can be pulled into
place and one end is normally attached to the tower counting on the surplus length.
17
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
1) Typical arrangements of accessories at the tension tower and the suspension tower are
shown from fig.(4) to fig.(6). In order to lead down OPGW to the joint box, the
arrangement of tension assemblies is different from that for conventional overhead ground
wires, while the suspension assembly is almost similar to that for conventional ones.
18
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
2) All bolts of accessories and fittings must be correctly tightened up to specified torque by
means of well qualified torque wrench respectively.
3) The bending radius of OPGW is recommended to be more than 500mm at the corner
position leading from the strain clamp to the arm of tower.
4) Surplus length of OPGW leading down from the strain clamp to the joint box shall be fixed
to the tower along with arm and structures by fixing clamps and racks, as shown in Fig.
(6). Such fittings should be arranged to the tower at intervals of specified of distance
respectively.
5) The balanced length of OPGW should be coiled in a diameter more than 1 meter after
completion of jointing, and then be firmly fixed to the tower as shown in Fig.(6).
6) Installation is shown in Fig. (6). Joint box should be firmly attached to one of the main
tower structures.
19
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
7) The outline of a typical joint box is shown in the drawing for reference and the example of
its installation is shown in Fig. (6). Joint box should be firmly attached to one of the main
tower structures.
Fig.(6)
8) During the works leading down OPGW to the joint box, keen attention must be paid not to
bend or twist OPGW locally, which causes the deterioration of optical properties or
loosening the outer wires for reinforcement.
8. Jointing
8.1 General
1) Jointing works of OPGW must be done usually at the high position on the tower, while
the splicing of optical fibers must be made with high accuracy not to spoil the optical
transmitting properties at the spliced part. For ease of jointing works with such high
accuracy, it is recommended to provide some temporary floor space on the tower in
advance for jointer and equipment. Also, such floor space should be protected against
the heavy wind, strong sunshine, high temperature, rain and dusty atmosphere.
2) Keen attention must be paid not to damage OPGW including its optical components
during the works such as handling, cutting, unstranding of component wires and
jointing.The jointing works of optical fiber itself must be done by well trained and qualified
person.
20
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
3) Before joint work, please check the OPGW fiber, it is recommended to wait around a
week until repositioning Fiber.
5) Spliced part of optical fiber with reinforcement should be accommodated to the qualified
joint box and be free from tension after completion.
Process flow chart of OPGW jointing works is summarized briefly, which is typical instance
as a model case for reference.
Start
21
End
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
Confirm that all of the materials, tools and equipments listed in tables 1 and 2 are
prepared.
In addition to above, it is also important to ensure enough wide working space on a
tower in order to work easily and safely.
Stretch the OPGW coiled beforehand near the joint box, and cut off unnecessary
lengths of the OPGW with a cable cutter.
Put cutting marks on OPGW at positions where the OPGW is to be fixed to glands of
the joint box. Grip each OPGW at a position about 100mm below the cutting mark by
two or three turns binding of copper wire to prevent the AW wires from coming loose
after cutting off the unnecessary parts.
100mm
Binding ≒ 4m
AL-Tube
AW
Notch the AW wires of the OPGW with a hacksaw to the 1/3 to 1/2 depth of the AW
wire diameter. In this case, take care not to be damage the inside AL tube of the
OPGW.
Loose AW wire from the OPGW ends one by one and snap them off at the notched
position.
AL Tube cutting.
50mm
AL Tube
Optical unit
AW
22
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
AL-Spacer
150mm 30mm
OPGW
AL Tube Optical unit
Heat Shrink Tube
Remove the PBT tube of optical units with leaving remain of each suitable length from
the edge of the AL tube.
Make every optical units into loops of about 5 to 10 cm diameter, and stick the optical
units loops to the suitable position of the joint box with adhesive plastic tape in order
not to be damaged during following splicing work.
Cleave length
Bear fiber length is 16mm ±5 after cleaving.
Remove the fiber coating, clean the fiber and then cleave the bare fiber to the
predetermined length. Set the prepared fiber in the v grooves as shown in the figure
below.
23
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
Clamp the prepared fiber exactly by pushing the clamp lever. After clamping the right
and left fibers, close the hood. Make sure that the prepared fiber is not trapped by the
hood, and not caught by any other part of the machine.
24
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
The evaluation of the splice should be done by estimated splice loss and the external
appearance at the splice point.
Caused by
1. Dust on fiber end
2. Condensing
3. Bad cleaving
4. Prefusion time is too short.
5. Arc power is too strong.
(*) In the case where fluorine doped fiber is splicer, a black line will always appear at the splicing point, but does not
cause any damage to the characteristics of the optical transmission.
(2) The following splices are acceptable, even if the external appearance at the splice
point does not look good.
25
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
Dust or scratches
No bad effect to spliced fiber but more care is
necessary in cleaning and cleaving fibers.
When the spliced portion is required to be observed in detail, “FIELD CHANGE” and “FOCUS UP” and
“FOCUS DOWN” SW on top mounted console panel are useful
1) Open the heater cover, the left fiber clamp and right fiber clamp
Fig. 8-5A
2) Open the hood, take out the spliced portion, close the hood, and press the “RESET”
SW.
26
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
Fig. 8-5B
Fig. 8-5C
Note
Make sure fiber coating is clean.
Put the sleeve over the splice as shown in Fig. 4-6C
Don’t twist the fiber.
FPS-1 should be straight.
4) Apply a slight tension and place the splice in the heater, close the right hand heater
clamp by pressing down with the right hand fiber.
5) Next, close the left hand heater clamp while pulling the fiber slightly, and close the
heater cover.
27
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
Fig. 8-5D
Note
Fiber should be straight.
Make sure that there is no dust, or jelly in the protection sleeve.
6) Press the “HEATER SET” SW, and the “working” indicator lights up.
Fig. 8-5E
7) After the tensile proof test(a few seconds), it takes a few minutes until the fiber
protection sleeve is shrunk. A buzzer will indicate the finishing of shrinking the sleeve.
If the fiber breaks, or the fiber is loosely clamped or slips during the tensile proof test,
the buzzer will beep intermittently. Correct the condition before proceeding.
Note 1
Both the splicer and heater can be operated simultaneously.
Note 2
The tensile proof strength can be set from 50 to 500 grams. This value is set
to 200 grams normally.
28
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
bending
29
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
30
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
Apply sealing compound to the edge parts of the AL tube of the OPGW.
Fix the cover to the joint box after having conformed not to be anything left in the joint
box such as tools and dusts.
Check Point
Joint box using the same type OPGW.(Check gland type)
To carry into effect fusion splice in joint box.
Check the status of water proof.
Compounding in gland for holding in check moisture.
Fusion splice working is protection it against dirt, grit and moisture.
Fixed tension member and glass yarn to the joint box.
9.1 General
This article details the procedure for dielectric optical fiber cable inside a continuous duct
running out from a terminal building.
The general precautions to be considered are as follows.
1) A safety values more than the allowable ones for tension and bending applied to
dielectric optical fiber cable during installation shall be considered as standard.
3) Moving of drum
(1) When moving the dielectric optical fiber cable to the pay out location (called a cable
pay out site) during the installation, the drum should be rotated in a direction which
is indicated by an arrow mark ( ) on the side boards of the drum.
31
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
Fig 1
(2) During moving, or when leaving the drum, the drum should not be stacked flat, and
stoppers should be placed properly.
(3) Paying out of dielectric optical fiber cables requires an appropriate area of space for
drum moving, and the selection of the site has to be made carefully.
32
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
Table 1
Steel Tension member cable or
Item
equipment
Pulling Tension Max. 270kg
During
Bending Radius Min. 20D
Installation
Pulling Speed Max. 15m/min
(D : Cable outer diameter)
(4) The value of pulling tension and bending radius depends on the specification.
The essential materials and tools are shown in Table 2 & 3 respectively.
Table 2. Materials
No. Item Description
1 Dielectric Optical Fiber Cable CFOA – SM – DD – G – 24
2 Protective Spiral Sleeve or the like For protection
3 PE(Poly Ethylene) pipe and fitting 28 ~ 36 Φ
4 Steel Pipe and fitting 28 ~ 36 Φ
5 Flexible Tube and fitting 28 ~ 36 Φ
6 Cable tie
7 Binding Rope For binding
Table 3 Tools
No. Item Description
1 Drum Stand
2 Drum Trailer
3 Shovel and Pickax
4 Cable Grip For laying
5 Flexible Cable Guiding Tube 〃
6 Pulling Rope 〃
7 Swivel 〃
8 Cable Cutter For cutting cable
Transmitter and Receiver or Portable
9 Telephone Set
For communication
10 Safety Facilities For safety work
33
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
CAUTION
Dielectric Optical Fiber Cable SM / 24C
Section ~
Date
34
Date of issued 13 / 04 / 2010
Revision No. 002
Power Cable System Team
When pulling through at turning points and bend area shall be protected by the protective
spiral sleeve.
35