SM2 Process
Scope
Each facility shall have a documented process that covers all maintenance requirements arising from preventative maintenance. This process must include
Repair order close out and communication of unit status.
Objective
To maintain all CSC equipment efficiently and uniformly in accordance with WI-OSD-WSD-01, enabling the equipment to perform the task for which it is
designed, in the safest and most cost efficient manner.
Employee and Management Responsibility:
Performing Commentary SM2 on time is the responsibility of the GMS. However, the GMS will need everybody’s effort to ensure proper reporting of
equipment conditions and updated meter reading. A monthly report will be generated to monitor the need for SM2 before 90 days and then enhance proper
planning along with operations personnel.
MTs/ETs will be accountable to perform a commentary SM2 on equipment with complete reporting.
Technician review pervious SM1 and GMS to assign technician to perform
SM2 inspection
Technician use SM2 checklist to Create Work Order
inspect and note all defects on it
Are all or
Procure spares or materials No some parts
available?
Yes
Discuss the need of the unit and its
current limitation with CL
Repair defects
Yes
Unit status must be confirmed Use the unit while following up on
red tagged with operation spares
CL: Cell leader
GMS: General Maintenance Manager
"Note: For any question on this SM-2 Process, please refer to WI-OSD-WSD-01Maintenance 'or contact GMS or Location SQ for any help or more guideline.