Professional Documents
Culture Documents
R1 WGFE20-0047 Training Text for M701JAC GT Disassembly Scope of Planned Maintenance
R1 WGFE20-0047 Training Text for M701JAC GT Disassembly Scope of Planned Maintenance
Proprietary and Confidential Information. This document or information cannot be reproduced, transmitted, or disclosed without
prior written consent of Mitsubishi Hitachi Power Systems,Ltd.
© 2018 Mitsubishi Hitachi Power Systems, Ltd. All Rights Reserved. 0
SL 2 ECT -
Contents
Preface
Maintenance Philosophy
Contents
Preface
Maintenance Philosophy
Preface
Contents
Preface
Maintenance Philosophy
SPARE
PARTS NEW PARTS CLEANING Ditto Ditto
OR INSPECTION
REPAIRED PARTS REPAIRMENT
Advantage of Roll-in/Roll-out system:
Shorten Inspection duration = reduce total plant outage duration.
Optimize hot gas path parts management.
Proprietary and Confidential Information. This document or information cannot be reproduced, 7
© 2018 Mitsubishi Hitachi Power Systems, Ltd. All Rights Reserved.
transmitted, or disclosed without prior written consent of Mitsubishi Hitachi Power Systems, Ltd
SL 2 ECT -
INLET
MANIFOLD COMPRESSOR
INLET COMPRESSOR -COMBUSTOR TURBINE EXHAUST EXHAUST
CYLINDER CYLINDER CYLINDER CYLINDER MANIFOLD
CYLINDER
Contents
Preface
Maintenance Philosophy
ROOF PANEL
Fuel nozzle has 3 types of oil piping, 5 types of gas piping, and 1 type
of water piping.
Fuel nozzle cannot be removed without removing all of them.
Also, the lower half of the combustor outer shell has drain piping that
must be removed if it interferes with combustor(nozzle, swirler and
liner) removal.
FILTER BLEED
PIPE
SAMPLE
Enclosure Removal Reassembly
Insulation Removal Repair Reassembly
2. Instrumentation
Electrical & Instrument Disconnection Electrical & Instrument
Igniter & Flame Detector Cable Disconnection Spark Test & Lighter Check Reconnection
CPFM & Accelerator Sensor Disconnection Reconnection
Disc Cavity T/C & BPT T/C Removal Reassembly & Reconnection
3. Pipings
Fuel Branch Pipe Removal Reassembly
Bleed Air Pipe Removal Reassembly
Turbine Cooling Pipe Removal Reassembly
At the beginning of the turbine inspection, the enclosure roof panels and side panels
in the yellow shaded area shown below must be removed.
SIDE PANELS
ROOF PANELS
TURBINE CYLINDER
In the turbine inspection, the upper half piping connected to turbine cylinder
must be removed in addition to the piping removed at CI since the turbine
cylinder is removed. Remove only
turbine side
piping
Remove only
turbine side
piping
COOLING AIR PIPING LOW PRESS. BLEED AIR PIPING MIDDLE PRESS. BLEED AIR PIPING
HIGH PRESS. BLEED AIR PIPING GT CASING COOLING AIR PIPING FUEL GAS SWEEP AIR PIPING
Proprietary and Confidential Information. This document or information cannot be reproduced, 21
© 2018 Mitsubishi Hitachi Power Systems, Ltd. All Rights Reserved.
transmitted, or disclosed without prior written consent of Mitsubishi Hitachi Power Systems, Ltd
SL 2 ECT -
SHORT PIPING
PISTON RING
TURB BLADE
RING ROW 1&2
A
B
COOLING AIR PIPING TURB CYL RIGHT SIDE SECTION AA-AA
BB EXTERIOR
TURB CYL PIPING
AA
BB
SHORT PIPING
AA
PISTON RING
TURB BLADE
RING ROW 1&2
SAMPLE
Preaparation
Enclosure Removal Reinstallation
Insulation Removal Repair Reinstallation
2. Instrumentation
Electrical & Instrument Disconnection Electrical & Instrument
Igniter Cable Disconnection Spark Test Reconnection Reconnection
CPFM & Accelerator Sensor Disconnection Reconnection
Disc Cavity T/C & BPT T/C Disconnection Reassembly & Reconnection
Vibration Sensor & Journal Bearing T/C Disconnection Reconnection
3. Pipings
Fuel Branch Pipe Removal Transfer Reinstallation
Fuel Manifold Pipe Removal Transfer Reinstallation
Bleed Air Pipe Removal Transfer Reinstallation
Turbine Cooling Pipe Removal Transfer Reinstallation
Vapor & Seal Air Pipe Removal Transfer Reinstallation
4. Inlet & Compressor Section
Inlet Manifold & IGV Linkage Mech. Open M/H Final Check & Close
Inlet Manifold Removal Reinstallation
Coupling Cover Removal Reinstallation
Jack Shaft & Coupling Bolt Disconnect Alignment & Coupling connection
Inlet Casing Removal Reinstallation
CompressorCasing Reinstallation
Comp 1st ~ 3rd Blade Ring Removal Reinstallation
Thrust Bearing Cover & Thrust Bearing Removal Reinstallation
#2 Journal Bearing Removal U/H L/H B/H U/H
Compressor Diaphragms Removal Reinstall Bottom
5. Combustor Section The following program parts
Comp. Comb. Cylinder are required for replacement:
7. Exhaust Section
Exhaust Duct Manway Cover Open M/H Final Check & Close
Cooling Air Pipe for Turbine Row4 Blade Removal Reinstallation
Exhaust Cylinder Removal Reinstallation
#1 Journal Bearing Removal U/H L/H B/H U/H
8. GT Rotor Section The following program parts
GT Rotor Lift out Reinstallation are required for replacement:
At the beginning of the major inspection, the enclosure roof panels and side panels
in the yellow shaded area shown below must be removed.
Disconnect the top of the cylinder from the horizontal and remove the
piping.
for EXHAUST
CYLINDER (AFT.)
for EXHAUST
CYLINDER(FWD.)
Supplementary explanation
Owner
TA SCOPE (MHPS scope)
MHPS
Coordinator
Qualification Function
1. To plan and advise on the work (the schedule, necessary manpower, parts and materials).
1. Coodinator 2. To direct/control Technical Advisors.
3. To prepare the post outage report.
1. To advice the allocation and arrangement of the labors.
2. To instruct the labors in the key points of assembly/disassembly as TA deems to be necessary.
3. To ensure the strict requirement for the safety of manpower.
2. Mechanical TA
4. To demonstrate the essential work in assembly/disassembly as the TA judges to be necessary.
Auxiliary TA
5. To observe and assure the assembly/disassembly to be carried out as per correct manner/procedure.
6. To measure the necessary clearances/dimensions, records and compare the data against the criteria.
7. To assure the work to be carried out as per the schedule.
1. To plan the arrangement of the blades.
3. Blade TA 2. To demonstrate the remove/installation of blades with the assistance of labors as the TA judges to be necessary.
3. To measure the blade height to adjust it as required.
1. To advice for dismantle/install work.
4. I&C TA 2. To check/calibrate the instruments.
3. To plan and carry out the interlock test before commissioning.
5. DDC(Direct Digital Control) TA 1. To check and tune DDC(Direct Digital Control).
1. To plan and carry out NDE(Non Destructive Examination) inspection of the parts/components.
6. Inspection TA 2. To judge the result of inspection based on the criteria.
3. To make the inspection report.
1. To plan and carry out start up procedure.
7. Start up TA
2. To plan and instruct to apply the balance weight according to CABS(Computer Aided Balancing System) data, if required.
8. Combustor tuning TA 1. To carry out combustor tuning for starting up GT.