DESIGN OF STEEL AND MASONRY STRUCTURE [15CE61T]

Unit – 1- INTRODUCTION TO LIMIT STATE DESIGN OF STEEL STRUCTURES


Sl.no Question Marks Appeared in
1 State the advantages and disadvantages of steel
5 April 18
structure.
2 What are the different types of load acting on
5 April 18
steel structure?
Unit – 2- BOLTED CONNECTIONS & WELDED CONNECTIONS
Define i) Pitch ii) Gauge iii) Edge Distance
1 5 April 18
iv) Nominal Dia and v) Lap
2 What are the advantage of welded joints. 5 April 18
3 Design a lap joint between two plates of size
of 60 x 10 mm thick and 100 x 8 mm thick so
as to transmit a factored load of 150 kN using 15 April 18
a single row of M16 bolts of grade 4.6 and
410 grade plates.
4 An I S A 150 x 115 x 10 mm angle section is to
be connected to a 10 mm thick gusset plate at
site. Design the fillet weld to carry a load equal 15 April 18
to the strength of the member, fillet weld is
provided all three sides
Unit – 3 -FLEXURAL MEMBER
1 Mention different types of failures in beams 5 April 18
2 A simply supported steel beam of 4m effective
span is laterally supported throughout. It carries
15 April 18
total UDL of 12 Kn/m Inclusive of self weight
Design the section using the steel of grade 410.
Unit – 4 -TENSION MEMBERS
1 Name different modes of failure of tension
5 April 18
member and explain briefly any one.
2 Design a tension member using two angles
back to back on either side of gusset plate of
10 mm thick for an axial factored load of 375 15 April 18
KN use 20 mm diameter Black bolts. Take
Fu=410 N/mm2 and Fy= 250 N/mm2
Unit – 5 -COMPRESSION MEMBERS & COLUMN BASES
1 Mention the end condition of the column with
5 April 18
their effective length as per IS standards
2 Design a column 3.8 m long in a building
subjected to a factored load of 600 kN. Both
the ends of the column are effectively 15 April 18
restrained in direction and position. Use steel
of grade Fe 410.
3 A 3.6 m long ISHB 250@ 536.6 N/m carries
factored axial load of 2500 KN. Design a slab 15 April 18
base for the column which is resting on a

Question Bank – Unit Wise


Department of civil Engineering [Jain Polytechnic, Belagavi] Page 1
DESIGN OF STEEL AND MASONRY STRUCTURE [15CE61T]

concrete pedestal of M25 concrete also design


the pedestal for SBC soil 280 KN/m2. Use M20
Dia Bolts.
Unit – 6 - ANALYSIS AND DESIGN OF MASONRY DAMS AND RETAINING WALL
1 Name the various condition for stability of
5 April 18
dam
2 A masonry retaining wall of trapezoidal
section is 5m height and 1m wide at the top. It
retains soil up to the top of the wall. Face of
the wall in contact with soil is vertical. Soil
15 April 18
and masonry way 16KN/m3 and 23 KN/m3
respectively. Calculate minimum bottom width
of wall so that no tension is induced at the
base. Take angle of repose as 30 degree

Question Bank – Unit Wise


Department of civil Engineering [Jain Polytechnic, Belagavi] Page 2
Project Management and valuation [15CE62T]

Unit-1 INTRODUCTION TO PROJECT MANAGEMENT


Sl.no Question Marks Appeared in
1 What is construction management? List objects
5 April 18
of construction management.
2 What is Job layout? Write the Job layout for
5 April 18
construction of a building.
3 Define organization Explain Line (or) military
5 April 18
organization.
4 Explain the various stages in construction of a
10 April 18
project from concept to realization.
Unit-2-PLANNING & SCHEDULING (1 Question Compusory)
What is Pre-tender planning & Post-tender
1 5 April 18
planning?
2 List the different types of schedule. Explain any
10 April 18
two with the schedule format.
3 Define following. i) Activity ii) Event iii) total
5 April 18
float iv) EST v) Duration
4 Difference between CPM and PERT 5 April 18
5 Draw a network diagram from the following
activity and find the critical path duration of the
project.
Activity Duration in (days)
1-2 13
2-3 08
3-4 10
3-5 11 10 April 18
4-6 09
5-6 10
5-7 06
6-8 08
7-8 07
8-9 14
9-10 18
Unit-3- CONSTRUCTION PROJECT PRACTICES
1 What is contract explain lump sum contract. 5 April 18
2 Explain the following i) EMD ii)
5 April 18
Administrative Approval.
3 Explain the procedure of calling, opening,
10 April 18
security and acceptance of tender.
4 Write short note on following
10 April 18
i) Imprest Account ii) Site order book
Unit-4- SAFETY & QUALITY MANAGEMENT
1 What are the causes of Accidents in a
5 April 18
construction Project

Question Bank – Unit Wise


Department of civil Engineering [Jain Polytechnic, Belagavi] Page 1
Project Management and valuation [15CE62T]

2 What is measurement book? Explain the rules


to be followed in recording measurements in 10 April 18
measurement book.
3 Define safety and check list taken in the
10 April 18
following works. i) Excavation ii) Scaffolding
4 What is meant by total quality management.
Write the stages of inspection and quality 10 April 18
control for RCC works.
Unit-5- VALUATION OF BUILDINGS
1 Define valuation. Write six purpose of
5 April 18
valuation of the building.
2 A building costing Rs. 15lakhs has been
constructed on a free hold land measuring
100sqm. Recently in big city prevailing rate of
land is the neighbourhood of Rs. 4500 per sqm.
10 April 18
Determine the net rent of the property if the
expenditure on an outgoing including sinking
fund is Rs. 42000 per annum. Work out also the
gross rent of the property per month.
Unit-6- ENTERPRENEURSHIP
1 List any five areas in which civil engineering
5 April 18
can become an entrepreneur.

Question Bank – Unit Wise


Department of civil Engineering [Jain Polytechnic, Belagavi] Page 2
Town Planning [15CE63EA]

Unit-1 Introduction
Sl.no Question Marks Appeared in
1 Mention the features of satellite town 5 April 2018
2 What are the factors considering while
10 April 2018
selecting an ideal site for a town
Unit-2 Surveys & Planning and Zoning
List the various methods adopted for collecting
1 5 April 2018
details for town planning survey.
2 Discuss difference between urban and rural April 2018
10
planning
3 What is the necessity of regional planning 10 April 2018
4 Distinguish the difference between profit
10 April 2018
making and nonprofit making use of the land
Unit-3 Housing, Slums and Public buildings & Industries
1 How are residential building are classified 5 April 2018
2 How can formation of slump can be prevented 10 April 2018
3 What are the factors examine at the time of site
10 April 2018
selection for the public building.
Unit-4 Recreation measures and Master Plan
1 What are the objects of building bye-laws 5 April 2018
2 Write a short note on:
10 April 2018
i) Park ways ii) Boulevards
3 What are the data required for the master
10 April 2018
planning.
Unit-5 Re-planning Existing Towns
1 What are the objects of re- planning. 5 April 2018
2 What are the principle of golden city 5 April 2018
3 Define smart city. what are the features. 10 April 2018
Unit-6 Urban Roads and Traffic Management
1 Mention the requirement of a good city road. 5 April 2018
2 What are the necessity of street lightening 5 April 2018
3 What are the causes of accidents. 10 April 2018

Question Bank – Unit Wise