BWTS - HYUNDAI HWC-TSM-21 - GI-Power - Fuse Check Method

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Ballast Water Treatment System

HiBallast / Technical Information

Date 2021.03.18 Prepared by Checked by Approved by

Doc. No HWC-TSM-21
H.S.PARK J.W.YU S.H.LEE
Rev. 1.0

• Fuse check method

1. Cautions
(1) Turn off the Main Power prior to maintenance.

2. Maintenance method
Picture Explanation

1 Check fuse error LED on the pcb when rectifier Normal : LED ON LED STATE On/Off
power on Abnormal : LED OFF Module NO.1
(First, make sure that the CN650 connector is well Module NO.2
connected on the pcb) Module NO.3

Module 3 LED Module 2 LED Module 1 LED

<CN650 Connector >

< CN650 connector >

2 Check the 2-wire signal line of CN650


connector using a tester.

Normal : CLOSE
Abnormal : OPEN

Moudle 2 Connector state Open/Close


Module NO.1
Module NO.2
Moudle 3 Moudle 1 Module NO.3
3 Power off rectifier(rectifier off, circuit-breaker off) * Refer to module removal manual
pull-out the module
(Back side : remove bolts inside the hood)
(Front side : Power-line(3-wire), output-line(2-
wire) remove)
4

Micro switch check(FUSE signal check)

Check fuse switch switch Open/Close


Normal : CLOSE Switch 1
Abnormal : OPEN Switch 2
Switch 3

Fuse status check Fuse state Open/Close


Normal : CLOSE Fuse 1
Abnormal : OPEN Fuse 2
Fuse 3