“CONTRACTS AND ACCOUNTS”

(22601)

UNIT NO – 01

PWD PROCEDURE TO EXECUTE


THE WORK

PROF. NIKLESH YASHWANT KANK

(BE.CIVIL , ME. CMA)


1. Engineering department which deals with construction &
Maintenance of Public Work ....

a) PWD
b) WORD
c) PMRDA
d) MHADA

Ans-(A)

2. In PWD Sub Divisional Officer is also known as

a) SE
b) SDO
c) AE
d) SO

Ans-(C)

3. For any work in PWD which approval is required First?

a) Technical Approval
b) Administrative approval
c) Budget provision
d) PWD approval

Ans-(B)

4. Sub Divisional Officer is responsible to for execution of work in sub


division.

a) Assistant Engineer
b) Divisional Officer
c) Administrative Officer
d) Chief Engineer

Ans-(B)
5. Which of the following is not function of Junior Engineer?

a) Taking measurement of all work in MB.


b) Carry out field survey for proposed project.
c) Give administrative approval of work under his control and prepare
budget.
d) Preparation of bills

Ans-(C)

6. when no contractor is willing to accept the Work due to Small


margin of Profit then work is carried out by which
method in the PWD

a) Item rate method


b) Departmental Method
c) Percentage rate method
d) All of above

Ans-(B)

7. Full form Of NMR

a) Normal Muster Roll


b) Normal Muster Role
c) Nominal Muster Roll
d) None of Above

Ans-(C)

8. Following is not the method used in PWD for carrying


out works

a) Rate list method


b) Contract method
c) Approximate work method
d) Piece work method
Ans-(C)

9. For decorative plastering work following method used in


PWD.

a) Day's work method


b) Approximate work method
c) Rate list method
d) Department method

Ans-(C)

10. The method of valuating work on the basis of the quantity


of work actually done by petty worker known as

a) Day's work method


b) Piece work method
c) Rate list method
d) Contract method

Ans-(b)

11. Chief engineer has power to sanction any work


a) Full Power
b) Up to 25 Lakhs
c) Up to 10 Lakhs
d) Up to 5 Lakhs

Ans-(a)

12. What is full form of MHADA


a) Maharashtra housing and Development Authority
b) Maharashtra housing Development Authority
c) Maharashtra housing And Area Development Authority
d) All of the above

Ans-(c)
13. Who is works under Junior engineer
a) Skilled labour
b) Semi-Skilled labour
c) Unskilled Labour
d) All the above

Ans-(d)

14.Which of the following is not function of AE

a) Check work in progress


b) Maintain construction accounts
c) Check Muster roll
d) None of the above

Ans-(d)

15. Who has power to sanction work upto 15 lakhs.

a) Chief Engineer
b) Superintending Engineer
c) Executive Engineer
d) Junior Engineer

Ans-(b)

16. How many methods of Execution of work


a) 2
b) 3
c) 5
d) None of the above

Ans-(c)
17. Nominal muster roll has which no.of form.

a) Form no. 21
b) Form no. 23
C) Form no. 24
d) Form no. 27

Ans-(a)

18. Executive Engineer has power to sanction any work

a) upto 25 lakhs
b) upto 10 lakhs
c) upto 5 lakhs
d) None of above

Ans-(c)

19. Piece work method is used for

a) Works uptoRs. 2000


b) Urgent petty works
c) Both (a)&(b)
d) None of the above

Ans-(c)

20. Expenditure sanction can be exceed upto

a) 5%
b) 10%
c) 15%
d) 20%
Ans-(b)

21. Technical sanction means

a) Sanction of the detailed estimate and design calculation


b) Quantities of works and rates
c) Both (a) & (b)
d) None of above

Ans-(c)

22. Find out incorrect function of Superintending Engineer

a) Inspect work in his circle


b) Administrative and technical control of the circle
c) Inspect division in his circle and report to CE
d) Maintain construction account

Ans-(d)

23. After Administrative Approval project going for

a) Budget provision
b) Expenditure sanction
c) Technical sanction
d) None of above

Ans-(c)

24. Rate list method is use to below

a) Rs. 1000
b) Rs. 2000
c) Rs. 3000
d) Rs. 5000
Ans-(c)

25. Piece work method is used up to

a) upto 1000
b) upto 2000
c) upto 3000
d) upto 4000

Ans-(b)

26. In the following activity which is not a Day work method

a) Various plaster design


b) Under water work
c) Architectural finishes
d) RCC Work

Ans-(d)

27. Full form of PWD

a) Public workers Department


b) Public worker Division
c) Public work Department
d) All of above

Ans-(c)

28. Who is directly responsible to Chief Engineer

a) Junior Engineer
b) Executive Engineer
c) Superitending Engineer
d) All of Above
Ans-(c)

29. Following which work is carried out under PWD Department

a) Construction of Roads
b) Construction of Bridges
c) Construction of Dams
d) All of the above

Ans-(d)

30. After the acceptance of technical sanction which is next step.

a) Administrative Approval
b) Expenditure sanction
c) Budget Provision
d) All of Above

Ans-(c)