Professional Documents
Culture Documents
Accord Electrical Safety Inspection
Accord Electrical Safety Inspection
Wiring drawn through Provide cable tray or PVC pipe Corrected as per follow-
1 flexible PVC conduit is instead of flexible pipe to support 3 WEEKS On 06/03/2015: Corrected. '20/02/2015 up inspection on 6th Corrected
not firmly fixed. the cables. March, 2015
Page 1 of 20
ELECTRICAL SAFETY FOLLOW UP INSPECTION REPORT (12th)
On 20/04/2016: Corrected.
On 29/06/2016: Corrected at
Terminate each power cable at previous follow up but this issue raise
New Finding: single terminal and use proper again because of poor maintenance.
Multiple cables sized cable lug. Multiple cables On 31/10/2016: Not Corrected.
13 1 Month '30/04/2016 Corrected Corrected
terminated at MCCB termination is allowed if all are On 03/01/2017: Not corrected.
terminals/ Bus bar. soldered properly and powering to On 04/04/2017: Not Corrected.
a single circuit. On 20/07/2017: Not Corrected.
On 18/12/2017: Not Corrected.
On 08/04/2018: Corrected
On 29/12/2015: Corrected.
New Finding: On 29/06/2016: Corrected at
Cables terminated at Terminate all the previous follow up but this issue raise Corrected as per follow-
16 electrical bus bar/ power/earth/neutral cable with 1 Month again because of poor maintenance. '29/12/2015 up inspection on 04th Corrected
MCCB without cable proper sized cable lug On 31/10/2016: Not Corrected. April, 2017
lugs. On 03/01/2017: Not corrected.
On 04/04/2017: Corrected.
On 29/12/2015: Corrected.
On 29/06/2016: Corrected at previous
follow up but this issue raise again because
of poor maintenance.
On 31/10/2016: Not Corrected.
New Finding: Thermo graphic scanning for the On 03/01/2017: Not corrected.
Thermo graphic scanning entire electrical system must be On 04/04/2017: Not Corrected.
20 2 Months On 20/07/2017: Not Corrected.
'30/09/2015 Completed Corrected
of the entire electrical performed on a bi-annual basis
system is due. and recorded On 18/12/2017: Not Corrected. Hot spot
also found
On 08/04/2018:Not corrected. Ambiguity
found in repot.
On 17/09/2018: Not Corrected.
On 25/03/2019: Corrected.
On 29/12/2015: Corrected.
On 29/06/2016: Corrected at
Resize earth lead cable/ECC for previous follow up but this issue raise
New Finding: LT panel/MDB/DB; follow again because of poor maintenance.
Earth lead cable/ Earth BNBC 2006 Part 8 chapter 2 On 31/10/2016: Not Corrected.
22 Continuity Conductor section 2.8 for sizing your earthing 2 Months On 03/01/2017: Not corrected. '30/09/2015 Corrected Corrected
size is inadequate/ under cables (Usually ECC should be On 04/04/2017: Not Corrected.
size. equal to the half of the respective On 20/07/2017: Not Corrected.
phase cable). On 18/12/2017: Not Corrected.
On 08/04/2018: Corrected
New Finding:
No space around Corrected as per follow-
Ensure minimum 1.07m working
23 transformer for 1 Month On 29/12/2015: Corrected. '23/05/2015 up inspection on 29th Corrected
space around the transformer
performing any December, 2015
maintenance work
New Finding:
Ensure minimum two earthing
Generator body has been Corrected as per follow-
connection for generator body
25 earthed by inadequate/ 2 Months On 20/04/2016: Corrected. '10/03/2016 up inspection on 20th Corrected
(consult with your generator
improper sized (type) April, 2016
supplier).
cable.
New Finding:
(1)Power bus bar/
(1)Ensure that no power cable
MCCB are installed
touches bare bus bar. Use
congested; and power Timeline extended from 09.08.2016 to Corrected as per follow-
insulated bus bar (just covering
34 cables touch opposite 1 Month 09.09.2016 '09/09/2016 up inspection on 31 Corrected
existing bus bar by heat shrink)
phased bus bar. On 31/10/2016: Corrected. October, 2016
(2)Phase barriers between phases
(2)Phase separators
must be installed.
between phases are not
installed.
New Finding:
Earthing terminals must be Corrected as per follow-
Earthing terminals are
39 covered/capped and rust must be 1 Month On 03/01/2017: Corrected. '10/12/2016 up inspection on 03 Corrected
filled with rust and left
cleaned. January , 2017
open.
New Finding:
Transformer oil test (dielectric
Periodicity of
strength, moisture, and flash point
Transformer Oil Test On 08/04/2018: Not corrected.
test for oil) shall be done at least
42 (dielectric strength, 1 Month Prepare report adequately. '30/01/2017 Corrected Corrected
once in a year. If the operation of
moisture content and On 17/09/2018: Found Corrected.
transformer is 24/7 in the facility
flash point) survey is not
twice in a year is a better practice.
continued.