Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

ANNEX 2: INITIAL CONTRACT ACTIVITY HSEP-016

REVIEW (ICAR) GUIDELINE Annex 2

Annex 2.1: Initial Contract Activity Review (ICAR) Checklist

1.0 Objective: To ensure user is following the ICAR requirements using structured checklist.
Review team shall add the additional requirement which related with applicable legal or other authority
requirements when is required.

2.0 Required contractor shall be completed the checklist as per stated below:

Contract/Project SUPPLY, FABRICATE & INSTALL NEW SAFETY SIGNAGE (26 Nos) in
Name: OPERATION AREA KP#1, KUANTAN PORT.

1) Supply and Install 26 Nos of Safety Signage


Scope of Work:

Contract/Project
KP1 Operation Area
Location:
Contract/Project
14 November 2022 until 29 December 2022 (45 Days)
Duration:
Project
Manager/Contact 019-9325356 (Mr. Rizam)
Number:
Process
Owner/Contact 012-491 8800 ( Mr. Voon )
Number:
HSE Requirement according to Fulltime / No of pax request from No of pax from HSE
KPC HSE Contractor Rule: parttime requestor verification
a. Green Book Holder (SHO)
b. Yellow Book Holder (SSS)
c. Any other HSE /Competent
Personnel:
Duration (Days /
45 Days
Weeks)

Date (start to end) 14 November 2022 until 29 December 2022


Location
KP1 Operation Area
(Building LB1)
ANNEX 2: INITIAL CONTRACT ACTIVITY HSEP-016
REVIEW (ICAR) GUIDELINE Annex 2

3.0 Minimum team personnel to conduct the ICAR. Mandatory to be involved.


1. Process Owner (Lead)
2. Contractor Representative
3. Area Owner
4. HSE personnel
5. Related department’s representative as when required

3.1 This table shows the minimum requirement for Initial contract activity review before the mobilization of
contract at Kuantan Port.

Legend: A – Acceptable, O – Observation, U – Unacceptable

ICAR Checklist Items to be highlighted A U O Action Plan (if U or O)


Registered Supplier/Vendor
Assessment
HSE Requirement Checklist Refer to
ATTACHMENT B
Risk Assessment (JSA/EIA and etc.)
Valid license, certificate of fitness
from DOSH, DOE, DID, and other
relevant authority body.
List of tools for inspection
Machinery Inspection
Vehicle Inspection
Method of Statement for all scope of
works
Approved Job Hazard Analysis by
HSE Department
Process Owner shall approve the
working schedule and milestones for
the contract/project/activity.
Other Requirement (If yes, please
specify & attach following
documents)
ANNEX 2: INITIAL CONTRACT ACTIVITY HSEP-016
REVIEW (ICAR) GUIDELINE Annex 2

4.0 ICAR team shall conduct thorough inspection and discussion to complete the checklist and provide the
justification when is required.

Final Review Yes No


Have all of the concerns raised been addressed, and are
adequate and in place safeguards in place?

This activity can be initiated safely

Team Members Designation Name (Print Name Clearly) Signature and Date

ICAR/Activity Owner/Project

Area Owner

Process Owner

HSE personnel

Others

You might also like