This guide introduces how to install the cabinet on the concrete plinth.
Version: MN080067CEB_01
NOTE
Select an installation site for the cabinet according to the installation dimension and the space of
the cabinet.
Unit: mm
It is recommended that the front door of the cabinet be facing the direction with the
CAUTION* minimal radiation.
The distance between the cabinet and the nearby
living area must be more than 10m, and the back of
the cabinet faces the dwelling place.
Wear the protective gloves while carrying the cabinet to
avoid scratches on the cabinet and your hands. Unit: mm
Do not directly drag the cabinet to avoid damaging the
painting of the cabinet bottom.
The safety of the worker should always come first, if any
H = 1330
1900
*
Outdoor cabinet 500
The Caution items in this document do not cover all the
safety precautions that must be observed. They provide
only the generic safety precautions for operations.
750
FiberHome is not liable for any consequence that results
from violation of universal regulations for safety Concrete plinth
operations and safety codes on design, production and
equipment use.
1850
Ground
Anchor bolt × 4
Embedded PVC tube
≥300
770±2
Hollow
中 空 121±2
1 Preparation
≥400
300±2
100 400 600
NOTE 900
Prepare the following tools for the installation.
Direction of Front Door
1
2 1 Spatial Planning 2 Front View of Concrete Plinth
3 700
3 Top View of Concrete Plinth 900
TIPS
Hoisting equipment Wrenches Tape measure
Please build the concrete plinth according to the above figures and embed
four anchor bolts M12×220, whose exposed part is 30mm high.
Please check the flatness of the concrete plinth with the level ruler after it is
finished; if uneven, please repair it.
1 Install the lifting lugs from the accessories to 2 Lift the cabinet up with the hoisting equipment.
the top of the cabinet.
Hex Nut M12
Rubber washer