1. Purpose Statement
The aim of the project is to launch the new Credit card which targets the Generation Z. As the
distribution is mainly done via Call Centre and Company website, there is a need to get the
employees trained about the new features, uses and optimal interest rates to successfully
launch and maintain the project. So, the purpose of procurement is to have an agreement
with a supplier which has prior knowledge in the kind of system being developed and can help
employees to scale up to support the project once it goes live.
2. Scope Statement
The scope for procurement is mainly focused on procuring the training organization who can
develop the training material and deliver the training for the employees on product and sales
techniques. It is mandatory for the training organization to conduct the trainings in in-class
room sessions. There are 300 employees eligible for the training where 240 employees are
English speakers and the other 60 are French speakers. So, the study material must be
formulated for both the languages. The trainers must be good in both the languages (English
& French). Since the employees come to the office in different shifts and prefers language, the
training schedule must be drafted in accordance to their schedule and language
understandability. As the launch is scheduled to happen on October 1, 2020, the trainings
must be finished by a week before. In addition, the supplier is responsible for providing all the
platforms to work on the product materials.
Deliverable Description
Training Material Complete product and sales techniques material must
be provided in English and French languages.
Schedule for Training The training must be conducted in in-class room
sessions with different batches for people working in
different shifts and different language preferences.
Infrastructure Supplier to provide all the platforms to work on the
This study source was downloaded by 100000832949465 from CourseHero.com on 10-14-2022 19:28:34 GMT -05:00
https://www.coursehero.com/file/110399942/Procurement-SOW-Team-5docx/
material.
5. Cost Estimate
The total budget of the project is $1,000,000
6. Milestone-level Schedule
The project is scheduled to start on August 1, 2020. The key milestone level schedules are
listed below:
This study source was downloaded by 100000832949465 from CourseHero.com on 10-14-2022 19:28:34 GMT -05:00
https://www.coursehero.com/file/110399942/Procurement-SOW-Team-5docx/
7. Key Stakeholders List
Launch event for the credit card will be completed by the end of October 1, 2020.
Employees should be able to communicate in both languages.
The budget for the project is $1,000,000.
The deadline of the training completion is September 24, 2020.