Professional Documents
Culture Documents
6 Quality
6 Quality
1Introduction:
The Project Quality Management Plan documents the necessary information required to
effectively manage project quality from project planning to delivery. It defines a project’s
quality policies, procedures, criteria for and areas of application, and roles, responsibilities
and authorities.
The Project Quality Management Plan is created during the Planning Phase of the project. Its
intended audience is the project manager, project team, project sponsor and any senior
leaders whose support is needed to carry out the plan.
1
6.4Responsibilitie
Project Manger:
1. Report to Business Unit Director on quality performance and issues
(Project Director/ Deputy Project Director)
2. Establish and ensure implementation of the execution strategy, policies and
organizational structure required for on time, on budget, safe and to
specified requirements completion of the Project
3. Lead all Project Departments and resources to achieve all Project Objectives
4. Select key staff and delegation of duties to principal staff members
5. Set the agenda and schedule for principal meetings, convene and chair meeting.
6. Authorize principal Project documents
Quality Manager:
1. Lead effectively a team of Senior and Quality Engineers to achieve project
specified inspection and testing requirements on-site and off-site
2. Development, maintenance and monitoring of implementation of PQP
3. Scheduling, conduct and reporting of audits of subcontractors and suppliers as
deemed necessary
4. Lead continual improvement practices for the Project lifecycle by direct
involvement, supervision or support to achieve performance objectives and
targets
5. Development, maintenance and monitoring of implementation of PIP/ITP
Site engineer
1. Exercising full control over the workforce on site.
2. Ensuring that work is executed in accordance with the contract drawings and
specifications, agreed procedures and method statements.
3. Preparation of designated procedures.
4. Monitoring all Sub-contractors work closely to ensure that the Quality of the work is
as per specification and is completed on time.
5. Completing all necessary Q.A. documentation related to the work under his direct
7
control and co-ordinate daily site inspections.
The focus of the Quality Assurance is on the processes used in the project. The Quality
Assurance aims to ensure that the processes in the project and the work packages are used
effectively to develop quality project deliverables.
1. Needed inspections
a. Excavation
b. Filling
1. Prior to commencement of filling, the Consultant’s representative shall be
requested in writing to inspect and approve the fill starting level.
2. Filling shall be carried out using approved materials in accordance with the
specification which can either be selected from the material on site or
imported from selected and approved sources.
3. Filling shall be carried out as per approved method and as per the contract
specification
7
sufficient thickness.
4. Forms have corrected coordinated of center lines and control points, correct
elevations and grades and correct orientation and vertical and horizontal
alignment.
5. Forms have adequately sized, spaced and. nailed ribs, and strong backs.
6. Forms have adequate size, number and spacing of form ties and have
adequate bracing, shoring, spacers and supports.
7. Form joints have no cracks or holes that will allow undesirable grout leaks.
8. Form surfaces are clean, have proper form coating and satisfactory
to produce desired appearance of final concrete surface.
9. Chamfer strips, can’t strip, construction joints, keyways, water stop and
expansion joints are placed properly and workmanship is satisfactory.
Pockets formwork shall be correctly sized and located, properly fixed and
shaped in such a way to be easily dislocated. No burning is allowed to clear
the pockets.
10. Performed tiller material is an approved type and correctly installed.
11. All clean-out and inspection doors are securely replaced.
12. Concrete weather protection is available (at request).
13. Horizontal and vertical construction joints have been cleaned as required by
project specifications and surfaces wet down and cemented before fresh
concrete is placed. Standing water is removed before concrete is placed.
14. Method of placement is following design documents, equipment such as
cranes, chutes, concrete buckets, conveyors and pumps are ready for the
placement.
7
11. Check that vibrators are inserted near vertically and at the spacing and time
intervals consistent with good practice.
12. Check that finishing operations are initiated at the proper time.
13. Check that reinforcing steel, embedment and forms are not moved
during placement.
1. Ensure that the concrete is protected from adverse weather and extreme
temperatures, curing compound or wet jute could be used (according to
project specifications).
2. Ensure that the concrete support systems remain in place until the concrete
has attained sufficient strength to support all applied loads.
3. Check that removal of formwork in accordance with test results and design
documents.
4. Check on finishing (be worry of “honeycombs”) ensure protection/painting if
required.
5. Review and document the results of all cube tests.
6. Check that grouting shall be specified in project drawings and specifications,
the application shall be in accordance with the manufacturer’s instructions.
7. Applied loads shall not be allowed for concrete foundations unless ensuring
that the required concrete strength in accordance with the design
requirements has been attained.
f. Quality Control
It is the tests to be conducted to ensure compliance of materials and construction
procedure with standards and project specifications. construction quality control
starts once the product has been manufactured and is normally performed by the
contractor to be able to monitor and control quality of a construction project.
7
2. Checklist for Concrete Pouring
YES NO Comment
Check slump test as specified [ ] [ ]