Design a layout on a 2X3 grid that satisfies the preferences listed here
A - Absolutely Necessary
I – Important
O – OK
U – Unimportant
X – Undesirable -
2
b. Construct a chart of the operations of the jobs at the two
work centres and determine idle time of each line, assuming
no other activities are involved. Processing times (Hrs.) is as
follows:
JOBS A B C D E F
Machine
1 5 4 8 2 6 12
Machine
2 5 3 9 7 8 15
Machine 1 Machine 2
Job
Idle Operatio Time Time Idle Operatio Time Time
s
Time n time start end Time n time start end
D 0 2 0 2 2 7 2 9
A 0 5 2 7 0 5 9 14
E 0 6 7 13 0 8 14 22
C 0 8 13 21 0 9 22 31
F 0 12 21 33 2 15 33 48
B 0 4 33 37 0 3 48 51
Total Idle time :18 Hrs (Idle time of Machine 1 + (Idle time of Machine 2)
----------
Thank You
3
4