Professional Documents
Culture Documents
15-501-EP-RP-001 Rev.1 (Process Description Report)
15-501-EP-RP-001 Rev.1 (Process Description Report)
Doc. #: 15-501-EP-RP-001
Rev. 1
CLIENT: K-ELECTRIC
REVISION INDEX
Table of Contents
1.0 INTRODUCTION.............................................................................................................. 4
2.0 SCOPE OF DOCUMENT ................................................................................................. 5
3.0 PROCESS DESCRIPTION .............................................................................................. 6
4.0 PROCESS HYDRAULICS ............................................................................................... 9
5.0 SAFETY & EMERGENCY INTERLOCKS .................................................................. 9
1.0 INTRODUCTION
K-Electric Limited (KE) aims to develop a RLNG Spur Pipeline to fulfill the gas
requirement of the 900 MW RLNG Combined Cycle Power Plant (CCPP) Project.
KE have engaged Gasco engineering Pvt. Ltd. (GEPL) for laying the Pipeline along with
metering for supply of 250 MMSCFD RLNG at 59-85 barg to a delivery point (TP-03 &
TP-04) at the RLNG Supplier’s main pipeline which is connecting the Bin Qasim Power
Station-I(BQPS-I) with the Custody Transfer Station, positioned at 2.0 KM
approximately. This spur pipeline shall connect the delivery point situated at KE’s BQPS-
I with the main pipeline through a tee- off connection as designated by RLNG Supplier in
its facility.
Scope of work includes engineering, procurement, construction, testing and
commissioning (EPCC) of this project, GEPL will execute and commission the project on
turnkey basis, within the stipulated timeline.
This report presents the process description of this project that involves an overall process
operability and instrumentation controls related to pipeline from supplier and delivery
stations.
2.1 Abbreviations
KE K-Electric Limited
GEPL Gasco Engineering Pvt.Ltd.
RLNG Regasified Liquefied Natural Gas
CCPP Combined Cycle Power Plant
BQPS Bin Qasim Power Station
MW Mega Watt
MMSCFD Million Standard Cubic Ft. per Day
ESDV Emergency Shutdown Valve
IG Instrument Gas
FCV Flow Control Valve
PRV Pressure Regulating Valve
Currently FOTCO is supplying 600 MMSCFD RLNG via 30” Pipeline and Engro is
supplying RLNG gas via 24” Pipeline respectively metered through dedicated Custody
Metering station. These two pipelines are combining and total RLNG is routed to
SSGC network via 42” Pipeline.
During RLNG Spur Pipeline project, a new tie-in will be taken from existing 30” line
with the required isolation to transport RLNG to KE BQPS-I, which will further be
reduced into 14” line as per hydraulic requirement.
RLNG will be metered through New Custody Metering station at Supply Station prior
to be routed to KE BQPS-I metering station. The new pipeline will be equipped with
battery limit isolation valves at SSGC fence as well as KE fence.
The first tie-in will be taken in the supplier side. It starts with 30” tie-in (TP-01) and
converted into 14” pipeline which is designed to handle flow rate of 250 MMSCFD to
KE BQPS-I. The line is designed to provide pressure of 59 barg to 85 barg at KE plant
tie-ins (TP-03 and TP-04). This Supply station will be operated as a small independent
facility adjacent to existing FOTCO plant.
The 14” piping at supplier station is provided with Flow control valve (FCV-001) to be
controlled with FT-001 that will maintain required flow towards the delivery station.
At supplier station, a dedicated gas metering skid (comprises of Flow meter –
Ultrasonic type) is provided on 14” line to meter the gas required for custody transfer.
The metering skid also includes the gas quality monitoring tools i.e Gas
Chromatograph, H2S analyser, Hydrocarbon dew point analyser.
Initially 150 MMSCFD Metering skid will be installed as provided by KE. Later-on,
250 MMSCFD metering skid will be replaced with 150 MMSCFD skid. The future
cold connections with isolation valves are installed for future metering skid of 250
MMSCFD installation.
Automatic Blow down valve (BDV-001) is installed after metering skid considering
safety for emergency shutdown in fire case, as advised by KE. This will provide safety
to personal and asset if any unforeseen event of fire happened. Adequate vent stack is
provided to disperse gas during fire case at a safe location. Line will be isolated during
emergency of fire (2 out 3 voting basis) or gas detection (2 out of 2 voting basis) via
ESDV-005 and ESDV-002 within the Supply Station that will be trigged during auto
fire detection via fire and Gas detection or a manual call point push button. Same
ESDV will be closed to protect line during pressure high high (PSHH-001A//B/C) at
upstream and pressure low low (PSLL-001 A//B/C) at downstream scenarios via 2 out
of 3 voting scheme.
A manual depressuring line for 14” pipeline is provided and connected to new vent
stack at supply station.
The gas will further route via 14” pipeline and approximately two (02) km at delivery
tie-in point within KE BQPS-I plant.
Supplier side is independent facility, hence provided with Instrument Gas Buffer
Vessel (V-15-01). Two tap-off are taken from 14” line, before and after metering skid.
This will serve driving force for instrument loops/ESDV/BDV/Control valves to
operate as an alternative to instrument air. The instrument air provision is not available
at supplier station.
Pressure will be regulated with pressure regulated valves provided in series. The
pressure regulators shall be of Anti-freeze type at upstream of Instrument Gas Buffer
Vessel (V-15-01). Emergency shutdown valve ESDV-003 is provided at supply line to
isolate the vessel during fire case and pressure high high generated through PSHH-003.
Vessel is also protected with Pressure safety valve PSV-001 on over pressure during
fire case.
This buffer vessel is designed to provide 15min backup to instrument loop and
streamed flow for control valves.
Height 15 meters
Stack Dia 8 inch
Instrument air is available at delivery station and will be supplied from existing KE
plant. This will serve driving force for instrument loops/ESDV.
Plant simulation including hydraulics have been performed using Aspen HYSYS V11
version. Process flow diagram (PFD) and heat mass balance (HMB) generated in Aspen
HYSYS is provided in Hydraulic report (15-501-EP-RP-002).
For safety and emergency interlocks at Supply and Delivery stations considering
confirmed fire & gas detection, manual push buttons and high high or low low pressure
scenarios, the respective primary safety devices action are defined in Cause and Effect
Diagram (Doc No. 15-501-EP-CE-001).