■ Inspection Request List for 04th October 2022 (Witness inspection) - Revised Submitted on: 04-October-2022 Morning

Ref. No. IR / Location Inspection Time


S/N HKN-(IRF/WIR/MIR)- WIR / Description of Inspection Subcon Remarks
07:00- 13:00 - 19:00 -
ST-XXXXX MIR Building Grid Item Level Date Time
13:00 19:00 22:00
ARCHITECTURAL INSPECTIONS

Rooms (2.19.502, 597, 640, 2.20.501, 513, 516,


1 WIR BD2 2.1-2.38/2.H-2.L L19, L20 Fire ceiling final inspection 4-Oct-22 15:30 CSDG Scheduled
671)
Installation of Dry Wall Partitions (Dry wall Frame & One Side
2 WIR BD2 2.33-2.34/2.K-2.L Corridor [Room No: 2.18.607) L18 4-Oct-22 08:00 CSDG Scheduled
Board)

ELECTRICAL INSPECTIONS

Rooms (2.19.591, 610, 2.21.527, 531, 572, 589,


3 WIR BD2 2.1-2.38/2.H-2.L L19, L21 Installation of Conduits and Accessories 4-Oct-22 14:30 Daeil Scheduled
601)

4 WIR BD2 2.12-2.13/2.G-2.H Wine Celler L23 Installation of Conduits and Accessories 4-Oct-22 16:30 Daeil Scheduled

Daeil,Dimo,MIT,S
5 WIR BD2 2.30-2.38/2.J-2.L Zone D1-Kitchen Area (BOH-01) L01 Installation of Cable and Wires 4-Oct-22 15:00 Scheduled
eimens

6 WIR BD2 2.6-2.9/2.H-2.L Bistro Kitchen Corridor L23 Installation of Cable and Wires 4-Oct-22 15:45 Daeil, MIT Scheduled