Initiation Memilih Project Manager Membentuk Tim Proyek

Duration 12 days Duration 3 days Duration 4 days


Start 8/17/22 8:00 AM Start 8/17/22 8:00 AM Start 8/22/22 8:00 AM
Finish 9/1/22 5:00 PM Finish 8/19/22 5:00 PM Finish 8/25/22 5:00 PM

Membentuk Business Charte...


Duration 5 days
Start 8/26/22 8:00 AM
Finish 9/1/22 5:00 PM

Planning Membuat Scope Statement


Duration 8 days Duration 3 days
Start 9/2/22 8:00 AM Start 9/2/22 8:00 AM
Finish 9/13/22 5:00 PM Finish 9/6/22 5:00 PM

Executing Requirement
Duration 113 days? Duration 3 days
Start 9/14/22 8:00 AM Start 9/14/22 8:00 AM
Finish 2/17/23 5:00 PM Finish 9/16/22 5:00 PM

Design
Duration 20 days?
Start 9/19/22 8:00 AM
Finish 10/14/22 5:00 PM

Implementation
Duration 65 days?
Start 10/17/22 8:00 AM
Finish 1/13/23 5:00 PM
atement Membuat Work Breakdown S...
Duration 5 days
M Start 9/7/22 8:00 AM
M Finish 9/13/22 5:00 PM

Membuat SKPL
Duration 3 days
Start 9/14/22 8:00 AM
Finish 9/16/22 5:00 PM

Membuat Design UI
Duration 10 days?
Start 9/19/22 8:00 AM
Finish 9/30/22 5:00 PM

Membuat Design Sistem


Duration 5 days?
Start 10/3/22 8:00 AM
Finish 10/7/22 5:00 PM

Membuat Design Basis Data


Duration 5 days?
Start 10/10/22 8:00 AM
Finish 10/14/22 5:00 PM

Pembuatan Halaman Home


Duration 5 days?
Start 10/17/22 8:00 AM
Finish 10/21/22 5:00 PM
Implementation
Duration 65 days?
Start 10/17/22 8:00 AM
Finish 1/13/23 5:00 PM
Pembuatan Halaman Home
Duration 5 days?
Start 10/17/22 8:00 AM
Finish 10/21/22 5:00 PM

Pembuatan Halaman Katalog ...


Duration 10 days?
Start 10/24/22 8:00 AM
Finish 11/4/22 5:00 PM

Pembuatan Fitur Login


Duration 5 days?
Start 11/7/22 8:00 AM
Finish 11/11/22 5:00 PM

Pembuatan Fitur Streaming


Duration 10 days?
Start 11/14/22 8:00 AM
Finish 11/25/22 5:00 PM

Pembuatan Fitur Forum Disk...


Duration 3 days?
Start 11/28/22 8:00 AM
Finish 11/30/22 5:00 PM

Pembuatan Fitur Rating Film


Duration 3 days?
Start 12/1/22 8:00 AM
Finish 12/5/22 5:00 PM

Pembuatan Fitur Nonton Bar...


Duration 5 days?
Start 12/6/22 8:00 AM
Finish 12/12/22 5:00 PM

Pembuatan Fitur Untuk Kreat...


Duration 4 days?
Start 12/13/22 8:00 AM
Finish 12/16/22 5:00 PM

Pembuatan Halaman Subscri...


Testing
Duration 10 days?
Start 1/23/23 8:00 AM
Finish 2/3/23 5:00 PM

Controlling
Duration 113 days?
Start 9/14/22 8:00 AM
Finish 2/17/23 5:00 PM

Closing
Duration 11 days?
Start 2/20/23 8:00 AM
Finish 3/6/23 5:00 PM
Start 12/13/22 8:00 AM
Finish 12/16/22 5:00 PM

Pembuatan Halaman Subscri...


Duration 5 days?
Start 12/19/22 8:00 AM
Finish 12/23/22 5:00 PM

Pembuatan Halaman Pelengk...


Duration 5 days?
Start 1/2/23 8:00 AM
Finish 1/6/23 5:00 PM

Pembuatan Security System Integration


Duration 5 days? Duration 5 days?
Start 1/9/23 8:00 AM Start 1/16/23 8:00 AM
Finish 1/13/23 5:00 PM Finish 1/20/23 5:00 PM

Feature Testing
Duration 5 days?
Start 1/23/23 8:00 AM
Finish 1/27/23 5:00 PM

End to End Testing


Duration 5 days?
Start 1/30/23 8:00 AM
Finish 2/3/23 5:00 PM

Deployment
Duration 5 days?
Start 2/6/23 8:00 AM
Finish 2/10/23 5:00 PM

Melakukan Monitor dan Kont... Melakukan Monitor dan Kont... Melakukan Monitor dan Kont... Melakukan Monitor dan K
Duration 3 days? Duration 20 days? Duration 65 days? Duration 5 days?
Start 9/14/22 8:00 AM Start 9/19/22 8:00 AM Start 10/17/22 8:00 AM Start 1/16/23 8:00 AM
Finish 9/16/22 5:00 PM Finish 10/14/22 5:00 PM Finish 1/13/23 5:00 PM Finish 1/20/23 5:00 PM
sting
days?
23/23 8:00 AM
27/23 5:00 PM

d Testing
days?
30/23 8:00 AM
3/23 5:00 PM

Maintenance
Duration 5 days?
Start 2/13/23 8:00 AM
Finish 2/17/23 5:00 PM

n Monitor dan Kont... Melakukan Monitor dan Kont... Melakukan Monitor dan Kont... Melakukan Monitor dan Kont...
days? Duration 10 days? Duration 5 days? Duration 5 days?
16/23 8:00 AM Start 1/23/23 8:00 AM Start 2/6/23 8:00 AM Start 2/13/23 8:00 AM
20/23 5:00 PM Finish 2/3/23 5:00 PM Finish 2/10/23 5:00 PM Finish 2/17/23 5:00 PM

Melakukan Serah
Duration 3 days
Start 2/20/23 8:
Finish 2/22/23 5:
elakukan Serah Terima Pr... Menyelesaikan Arsip dan Do... Mengadakan Evaluasi Akhir ...
uration 3 days Duration 3 days Duration 5 days?
art 2/20/23 8:00 AM Start 2/23/23 8:00 AM Start 2/28/23 8:00 AM
nish 2/22/23 5:00 PM Finish 2/27/23 5:00 PM Finish 3/6/23 5:00 PM
Closing
Duration 11 days?
Start 2/20/23 8:00 AM
Finish 3/6/23 5:00 PM
Melakukan Serah
Duration 3 days
Start 2/20/23 8:
Finish 2/22/23 5:
elakukan Serah Terima Pr... Menyelesaikan Arsip dan Do... Mengadakan Evaluasi Akhir ...
uration 3 days Duration 3 days Duration 5 days?
art 2/20/23 8:00 AM Start 2/23/23 8:00 AM Start 2/28/23 8:00 AM
nish 2/22/23 5:00 PM Finish 2/27/23 5:00 PM Finish 3/6/23 5:00 PM