Gantt Chart
Gantt Chart
T W T
1 Memiliih Project Manager 2 days 9/2/22 8:00 AM 9/5/22 5:00 PM
2 Membentuk Tim Proyek 4 days 9/6/22 8:00 AM 9/9/22 5:00 PM 1
3 Membentuk Business Char... 5 days 9/9/22 8:00 AM 9/15/22 5:00 PM 1
4 Membuat Scope Statement 2 days 9/16/22 8:00 AM 9/19/22 5:00 PM 3
5 Membuat Work Breakdown... 6 days 9/20/22 8:00 AM 9/27/22 5:00 PM 4
6 Membuat SKPL 4 days 9/26/22 8:00 AM 9/29/22 5:00 PM 4
7 Membuat Design UI 8 days 10/17/22 8:00 AM 10/26/22 5:00 PM 6
8 Pembuatan Halaman Home 3 days? 10/27/22 8:00 AM 10/31/22 5:00 PM 6;7
9 Pembuatan Halaman Katal... 8 days? 10/31/22 8:00 AM 11/9/22 5:00 PM 6;7
10 Pembuatan Fitur Login 3 days? 11/10/22 8:00 AM 11/14/22 5:00 PM 6;7
11 Pembuatan Fitur Streaming 8 days? 11/15/22 8:00 AM 11/24/22 5:00 PM 6;7
12 Pembuatan Fitur Forum Di... 2 days? 11/25/22 8:00 AM 11/28/22 5:00 PM 6;7
13 Pembuatan Fitur Rating Film 3 days? 11/28/22 8:00 AM 11/30/22 5:00 PM 6;7
14 Pembuatan Fitur Nonton B... 8 days? 1/16/23 8:00 AM 1/25/23 5:00 PM 6;7
15 Pembuatan Fitur Untuk Kr... 3 days? 1/26/23 8:00 AM 1/30/23 5:00 PM 6;7
16 Pembuatan Halaman Subs... 4 days? 1/31/23 8:00 AM 2/3/23 5:00 PM 6;7
17 Pembuatan Halaman Pelen... 5 days? 2/6/23 8:00 AM 2/10/23 5:00 PM 6;7
18 Pembuatan Security System 4 days? 10/27/22 8:00 AM 11/1/22 5:00 PM 6;7
19 Testing 3 days? 2/16/23 8:00 AM 2/20/23 5:00 PM 8;9;10;11;12;13;14;15;16;...
20 Deployment 4 days? 2/21/23 8:00 AM 2/24/23 5:00 PM 8;9;10;11;12;13;14;15;16;...
21 Maintenance 10 days? 2/27/23 8:00 AM 3/10/23 5:00 PM 8;9;10;11;12;13;14;15;16;...
22 Controlling 105 days? 10/27/22 8:00 AM 3/22/23 5:00 PM 6;7
23 Closing 4 days? 3/23/23 8:00 AM 3/28/23 5:00 PM 19;20;21;22
Epi - page1
4 Sep 22 11 Sep 22 18 Sep 22 25 Sep 22 2 Oct 22 9 Oct 22 16 Oct 22 23 Oct 22 30 Oct 22
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Epi - page2
0 Oct 22 6 Nov 22 13 Nov 22 20 Nov 22 27 Nov 22 4 Dec 22 11 Dec 22 18 Dec 22 25 Dec 22 1 Jan 23
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Epi - page3
an 23 8 Jan 23 15 Jan 23 22 Jan 23 29 Jan 23 5 Feb 23 12 Feb 23 19 Feb 23 26 Feb 23 5 Mar 23
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Epi - page4
23 12 Mar 23 19 Mar 23 26 Mar 23 2 Apr 23 9 Apr 23 16 Apr 23 23 Apr 23
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
Epi - page5