Professional Documents
Culture Documents
A81598-3 NEB Condition 9 Quality Management Plan - A5I5Z1
A81598-3 NEB Condition 9 Quality Management Plan - A5I5Z1
A81598-3 NEB Condition 9 Quality Management Plan - A5I5Z1
Document # 01-13283-GG-0000-RPT-CM-0002
Rev Prepared by/ Reviewed by/ Approved by/ Accepted by/ Pages Remarks
No. Date Date Date Date Revised
T.Rath
0 P. Poos D. Safari Issued for Use
2017-1-27
B
C
Date: 2017-1-27
Trans Mountain Expansion Project
Revision No.: 0
01-13283-GG-0000-RPT-CM-0002 Quality Management Plan Page 2 of 25
TABLE OF CONTENTS
LIST OF APPENDICES
APPENDIX A: QMP Dashboard .............................................................................................. 23
LIST OF FIGURES
Figure 1: TMEP Quality Management Organization ................................................................ 24
Figure 2: TMEP Quality Management Program Block Diagram............................................... 25
1.0 Introduction
1.1 Scope of this Document
While full time quality practitioners shall be assigned to implement the requirements of
the QMP, Trans Mountain also holds each individual associated with TMEP accountable
for quality.
25 (1) Pressure testing shall be performed under the direct supervision of the
company or an agent appointed by it.
• ultimate responsibility for quality lies with the TMEP Vice President, which
ensures that the management of quality processes and results has equal
attention to other Project directorship responsibilities;
• the independent third-party Director of Quality reports to the TMEP Vice
President ensuring that quality management is not influenced by other Project
drivers; and
• Quality Leads reporting to the Director of Quality are embedded in all Project
scope silos as shown in figure 2, thus enabling and ensuring effective QMP
program implementation.
This QMP standard serves as the umbrella document for all QMPs which governs TMEP
scope, and defines the parameters and expectations for all Project component, or
specific QMPs. All sub-QMP plans will be submitted to TMEP Director of Quality for
approval to ensure the intent of and specific requirements of this umbrella QMP are met
or exceeded. Approvals will be carried out by the relevant TMEP Subject Matter Experts,
the Engineer of Record and scope specific stakeholders. These plans will be approved
at least one (1) week prior to placing equipment and materials orders or entering into
contracts for TMEP-related products and services.
The hierarchy of quality management plans across the project is shown in Figure 2.
TMEP Quality Management Program Block Diagram.
Visibility around the efforts and results achieved under the TMEP QMP will be essential
to proactively ensuring quality. A balance between leading indicators and lagging
indicators needs to be established in this reporting.
• the process to collect accurate raw data for the report in a manner that is not
onerous;
• the existence of a clear dashboard measuring progress on proactive and
reactive quality activities;
• identification of quality issues and opportunities complete with assignments and
status for resolution; and
• use of Key Performance Indicators (KPIs) to provide a measureable indication of
quality management health.
The intent of the QMP dashboard is to create high visibility around the proactive and
reactive components of QMP execution in order to build confidence of Trans Mountain
management and other stakeholders in the effectiveness of the program. In addition the
entities accountable and responsible for QMP execution can use the dashboard to
assess the need for course corrections.
The KPIs include but may include but are not be limited to:
• supplier and contractor QMP approvals count to ensure that all supplier and
contractor QMPs are approved;
• Inspection and Test Plan (ITP) approvals count ensuring tactical level
documents are in place and approved by Trans Mountain to ensure equipment,
materials, and services meet TMEP codes, specifications and standards;
• Inspector Qualification approvals count ensuring that the individuals executing
quality checks understand their respective subject matter;
• Prefabrication meeting count to ensure that face to face contact occurs to
ensure quality requirements are understood and will be actioned as intended;
• Factory Acceptance Testing (FAT) testing count to ensure that FAT testing
supports early verification of equipment and materials functionality; and
• Non Conformance Report (NCR) status metrics to ensure that immediate action
can be taken to correct quality program issues contributing to NCRs.
The TMEP Quality Lead shall generate the Quality Report. The Quality Report shall be
attached to the TMEP monthly report provided to the Trans Mountain senior
management team. The Quality Report shall contain, at a minimum,:
Lessons learned are root cause observations made on past actions that influence future
similar actions. They can be either negative or positive thus curtailing negative actions
while encouraging positive actions in the future. An effective lessons learned process
ensures implementation of findings before the next occurrence of the next action.
A workshop shall be held early in Detailed Design. The intent of the workshop will be to
record lessons learned relevant to TMEP and relevant to detailed design through to
start-up with focus on engineering, manufacturing and construction quality.
Lessons learned shall be included in the Quality Report. The intent is to reference
positive lesson’s learned as well as negative lessons learned. If a lesson learned may
affect remaining scope on TMEP, then responsibility for implementation shall be
established.
6.0 Engineering
6.1 Definition of Success: Engineering Quality
Plans shall be submitted for information prior to award of the engineering contract.
Plans shall be submitted for information prior to award of the engineering contract.
The responsibilities of the engineer of record shall be documented in the APEGA PPMP
or APEGBC Organizational Quality Management Program, as the case may be.
The engineer of record shall originate all Issued for Construction (IFC) deliverables
including Construction Work Packages (CWP).
The specifications for the TMEP are listed in TMEP Specification List document TMEP
Engineering Standards Specifications and Procedures List KMC Doc # 01-13283-GG-
0000-TEC-EP-0005.
Each specification deviation shall be identified as “one time only” or “project wide”.
A cold eyes review of the key design deliverables shall occur. Key design deliverables
may include but are not limited to P&IDs, Design Basis Memorandum, Control
Quality Management Plan
https://portal.kindermorgan.com/projects/tmep/Compliance/Conditions/NEB Condition 9
Quality Management Plan.docx
Date: 2017-1-27
Trans Mountain Expansion Project
Revision No.: 0
01-13283-GG-0000-RPT-CM-0002 Quality Management Plan Page 10 of 25
The scope of the cold eyes review shall be determined in advance of the review and
shall be documented in a cold eyes review charter. Each charter shall establish the
scope, timing, and resources required to conduct the review.
A cold eyes review summary report shall be issued and shall contain:
• Executive Summary
• Scope Description
• Findings
• Recommendations
• Action Plan for Resolving Recommendations
• Timing and Responsibility
• Appendices including all related documentation including the Charter
Third party engineering services shall operate under the requirements of the engineer of
record quality program.
The engineering contractor’s master deliverables register (MDR) shall list all deliverables
to be provided. The MDR shall identify documents that will be required externally for
regulators, or other authorities having jurisdiction. These documents include but are not
limited to:
The engineering contractors supplier data requirements (SDR) form shall be used on all
purchase orders and contracts to indicate documentation which shall be submitted by
the supplier or contractor and shall further identify documents that will be required
externally for regulators, or other authorities having jurisdiction. Documents to be
identified on the SDR shall include but are not limited to:
• vendor P&IDs;
• NDE results;
• hydro test results;
• vendor weld procedures;
• factory acceptance test (FAT) and site acceptance test (SAT) test results;
Quality Management Plan
https://portal.kindermorgan.com/projects/tmep/Compliance/Conditions/NEB Condition 9
Quality Management Plan.docx
Date: 2017-1-27
Trans Mountain Expansion Project
Revision No.: 0
01-13283-GG-0000-RPT-CM-0002 Quality Management Plan Page 11 of 25
• certifications; and
• inspection and test plan (ITP).
The Constructor’s MDR shall list all documents that shall be submitted to the engineer of
record for review and or confirmation of design.
The MDR shall be reviewed by the engineer of record prior to contract award to ensure
completeness.
Documents to be identified on the constructor’s MDR shall include but are not limited to:
• NDE results;
• NCRs;
• RFIs;
• as-builts;
• specification deviation requests;
• care and preservation records;
• hydrotest records;
• installation checks (e.g. pipe flange alignment checks, machinery alignment,
loop checks etc.); and
• certifications.
The distribution of NCRs and NCR status reporting shall include but may not be limited
to Trans Mountain’s:
From time to time technical bulletins are generated by various regulators and authorities
having jurisdiction. The engineer of record shall be responsible for ascertaining the
existence of technical bulletins, determining their applicability and advising TMEP of their
implications to the Project if any.
Trans Mountain will directly and indirectly (through contractors) purchase materials and
equipment required to construct TMEP. A process shall be in place to ensure that these
materials and equipment meet the design requirements of Trans Mountain.
• a process exists to ensure the accuracy of all supplier and contractor purchase
orders and contract documents with respect to technical requirements;
• all technical deviations and exceptions to the purchase order or contract
documents are identified, approved and recorded;
• all materials and services are provided in accordance with the approved
purchase order technical documents;
• all inspection and test plans are part of the purchase order;
• hold points are witnessed as called for in the ITP; and
• release of shipment certificates are issued prior to shipment.
Purchase order documents shall be reviewed and approved by Trans Mountain’s TMEP
Oversight Team Project Vice President, Engineering Design Manager, Director of
Quality and relevant SMEs.
• process conditions specified conform to the relevant DBM P&ID or other key
guiding documents;
• suppliers are selected through the TMEP approved manufacturers List (AML)
and the AML change process;
• scope of supply is correct;
• specification deviations are identified;
• testing and inspection requirements are correct; and
• seller drawing and data requirements are correct.
• scope of work;
No formal qualification of vendors listed on the AML will occur until such a time that an
award is imminent but prior to issuing a purchase order or contract.
Qualifications for owner issued equipment and materials will be conducted by the Owner
in advance of vendor or contractor selection and shall:
• line pipe;
• line pipe coating;
• mainline pumps and motors .
The qualification of other vendors will occur via the established protocol of each supplier
or contractor. The proposed protocol shall be submitted for TMEP Team SME approval
in advance of the qualification activities. TMEP may choose to participate in some or all
of the qualification activities.
Sub vendor quality shall fall under the responsibilities and programs of the suppliers’ or
contractors’ own QMPs. In the case of TMEP, sub vendors means any supplier or
contractor that does not have a purchase order or contract directly with the TMEP
Contractor.
Specific TMEP specifications and industry codes set out scope relevant criteria for
vendor qualification which shall be addressed during initial quality audit.
Ultimately each supplier or contractor shall submit an Inspection and Test Plan (ITP)
which reflects the requirements of the purchase order or contract (datasheet or scope of
work) as well as the manufacturer’s or contractor’s own standard inspection activities.
The ITPs shall be approved by the Trans Mountain Oversight Team SME.
Criticality assessment is required to ensure that the level and scope of inspection is
appropriate to the equipment or service.
The criticality level will determine the appropriate level of inspection and may include
some or all of the following depending on the inspection criticality level:
The criticality level shall be approved by the Trans Mountain Oversight SME and shall be
documented in the procurement strategy document.
A scale of 1 to 4 shall be employed. The scale will reflect that “4” is the highest criticality
level and thus requires the most comprehensive inspection level while “1” would be the
lowest criticality level and would require the most basic inspection level.
7.7 Commissioning
• verify and document that all systems are constructed in accordance with TMEP
planned designs, specifications, codes, standards;
• verify and document that all systems function as intended; and
• identify and correct any deficiencies and document.
• Pre-commissioning and;
• Wet commissioning
Wet commissioning activities will include but are not limited to:
Facilities transfer of control from TMEP to KMC Operations occurs at the completion of
pre-commissioning.
FAT testing is designed to energize the system being tested to the maximum extent
possible at the manufacturing location, before it is installed in the field. In some cases
this is done on a purpose built test stand and is governed by common industry standards
(Hydraulic Institute, API, NEMA), in other cases a project specific protocol for testing will
be developed and approved prior to FAT. The intent of the FAT is to verify that the
equipment functions as designed before it arrives in the field to the maximum extent
possible.
Depending on the equipment, an additional SAT may occur. In some cases SAT’s may
be mandatory and will need to be witnessed by authorities having jurisdiction (e.g. fire
water systems) and/ or safety codes officers (e.g. electrical installations, pressure piping
and vessels).
Items on TMEP which will be subjected to FAT testing will include but may not be limited
to:
• mainline pumps;
• mainline pump motors;
• mainline pump motor variable frequency drives;
• mainline isolation block valves;
• VRU / VCU system;
• electrical Buildings; and
• fire water / foam skid.
Items on TMEP which will be subjected to SAT testing will include but may not be limited
to:
The scope for each of the FATs and SATs will be developed and approved at least six
(6) weeks in advance of the test.
A FAT/SAT plan shall be developed in spread sheet form indicating what FAT/SATs are
planned along with other relevant details such as:
The FAT/SAT plan shall be updated periodically as driven by project needs. Once FATs
start the intent would be to update on a weekly basis.
The quality of pipe fittings and components shall be achieved by the same processes
outlined in 7.2 through 7.7 above.
7.9 SCADA
The Supervisory Control and Data Acquisition (SCADA) system which will be in service
for TMEP is Clear SCADA. Redundant servers are located in Edmonton, Alberta and
communicate with existing ControlLogix PLCs at each site via primary and backup
Ethernet Wide Area Network (WAN).
FAT shall be executed during the final part of the detailed design engineering phase.
FAT shall include PLC Test by loading each individual program. FAT shall be done at
Edmonton control room by using SCADA Test Bed. SAT shall be done at site and
verified from Edmonton.
The purpose of FAT/SAT is to review and verify configuration, graphics, alarms, status,
commands and communication links of PLCs, LOIs and SCADA.
The following documents are required for the FATs and shall be IFC and stamped by a
professional engineer:
• P&IDs;
• SCADA data map; and
• graphic displays hard copy.
• trade school, college or university training relevant to the ITP item for which they
are responsible;
• minimum of 15 years experience directly applicable to the ITP item for which
they are responsible;
• previous inspection activities completed at the selected manufacturing site or of
the selected constructor; and
• holds up to date certifications specific to the inspection activities as mandated by
relevant industry and regulatory body regulations and codes.
Inspectors shall not be assigned multi discipline scope unless they meet the above
requirements in all disciplines relevant to the ITP item for which they are responsible.
For example an inspector qualified in welding inspection shall not be given electrical
installation ITP scope unless he is also suitably qualified for electrical scope inspection.
Prior to shipping inspected materials and equipment, the Inspector shall generate a
punch list. The punch list shall identify all items that are not in compliance with the
purchase order or are otherwise classified as discrepancies. The documentation
package associated with the scope of work shall also be reviewed. Each punch item
shall be accompanied by a rough (+-30%) cost estimate indicating the cost to rectify the
discrepancy in the field by others.
The decided path forward and financial agreements shall be documented on the punch
list.
8.0 Logistics
8.1 Definition of success: Logistics Quality
TMEP faces unique logistics challenges including the wide geographic separation and
remote nature of delivery points as well as the worldwide sourcing of components.
The logistics quality shall be governed by the logistics companies’ quality plans. These
quality plans shall be submitted to Trans Mountain for approval where logistics are
arranged by Trans Mountain directly. Where logistics are arranged by contractors, it may
be approved under the requirements of the contractors’ quality plan.
Detailed requirements for preservation and preparation for shipment are contained in
equipment specific TMEP specifications and manufacturer supplied documentation.
Components such as pipe spools, electrical modules, pipe modules, and equipment
modules that will be assembled offsite must leave the module yard and arrive at site in a
state which minimizes site construction hours, minimizes site testing, is complete with all
required documentation, has the appropriate care and has preservation measures
implemented.
The constructors’ quality plans governing their module yard and pipe shop scope shall
apply. The constructors’ quality plans shall be submitted to Trans Mountain for approval.
As a minimum it is expected that the module yard and pipe shop quality plans address:
10.0 Construction
10.1 Definition of Success: Construction Quality
TMEP faces numerous unique construction challenges. These include remote and
difficult terrain, multiple construction sites, construction at operating facilities and multiple
construction contracts.
The constructors’ quality plans governing the module yard and pipe shop scope shall
apply. The constructors’ quality plans shall be submitted to Trans Mountain for approval.
Document management will play a critical role in retaining records which indicate that
TMEP has been designed and constructed to the required standards, commitments and
authorizations.
All supplier and contractor documents shall be submitted in accordance with scope
specific specifications in TMEP Engineering Standards Specifications and Procedures
List KMC Doc # 01-13283-GG-0000-TEC-EP-0005.
Supplier and contractor document management standards shall be submitted for review
along with any exceptions to the relevant specifications.
Project quality audits will form an integral part of the overall QMP and span all TMEP
scope and activities. The primary purpose of project quality audits shall be to pre-empt
project quality issues. In some cases project quality audits may also be conducted as an
after action activity.
Each supplier and contractor shall conduct at least one (1) quality audit per quarter. The
scope and methodology shall address the success factors above. Trans Mountain’s
Oversight Team may participate in any of the TMEP quality audits.
Scope for proposed quality audits shall be provided in confidence to the TMEP Director
of Quality for approval prior to executing the quality audit.
Quality audit reports shall be forwarded to the TMEP Director of Quality and as a
minimum shall contain:
• executive summary;
• scope description;
• findings;
• recommendations;
• action plan for resolving recommendations;
• timing and responsibility; and
• appendices including all related documentation.
A quality audit log shall be maintained by the TMEP Director of Quality, indicating all
quality audits planned, quality audits completed, findings and status of resolution.