7 Preparation of dry air (건조공기 준비)

NO. Description Checking by Client

Dry air & its accessory (hose, connecting adapter, regulator, etc) should be
7 available at site. Yes □ No □
건조공기 및 부속부품(주입호스, 연결아답터, 레귤레이터 등)이 현장에 준비되어 있어야
한다.

<NOTE>
※ To reduce moisture saturation in
Transformer inside, inject dry air during
assembly. Also, It is essential to prevent
accidents caused by oxygen deficiency
when worker enters transformer inside to
carry out bushing lead connection &
inside inspection.
외부의 수분이 변압기 내부로 유입되지 않게
하기 위해 조립단계에서는 건조공기를 변압기
내부에 주입해야 한다. 또한, 변압기 내부작업을
위해 작업자가 내부로 들어갈 시 산소부족으로
인한 안전사고를 막기 위해 건조공기는 필수적으로
준비되어야 한다.

<Client comment>

Global Top Energy Solution Provider 13


3.8 Electric power at site (현장 내 전원 공급 유무)

NO. Description Checking by Client

Enough capacity of Electric Power (Generator) and Light are ready


8 Yes □ No □
충분한 용량의 전원 (또는 발전기)와 조명이 준비되어야 한다.

<NOTE>
※ In case that generator is available,
it’s capacity should be above 300kW
for equipment operation.
(For Vacuum & oil filter machine)
현장에 발전기가 준비될 경우, 장비운용을
위해 발전기의 용량은 300kW 이상이 되어야
한다. (진공기, 여과기 용)

<Client comment>

Global Top Energy Solution Provider 14


3.9 Required tools and equipment (필요 공구 및 장비)

NO. Description Checking by Client

All required tools and equipment are ready (see the attached list)
9 Yes □ No □
설치에 필요한 공구 및 장비가 준비되어야 한다. (첨부 필요 공구 및 장비 리스트 참고)

Activity

Initial Inspection 1. Impact recorder inspection


2. Insulation resistance test
3. Main body & packing box check

1. Assembly of transformer’s parts


Parts Assembly - Radiator, bushing, conservator,
Cable chamber
2. Wiring of protective device

1. CT test : polarity, Insulation


resistance,
<Client comment>
BCT & Bushing Test ratio, excitation current
prior to vacuum
2. Bushing : Insulation resistance test
power factor test

1. Internal lead connection


Internal Lead
Connection & (winding lead – bushing terminal)
Assemble gas pipes 2. Inside inspection

1. Vacuum
- Keep vacuum according to
Vacuum & Oil Filling & manufacture’s manual.
Oil Circulation
2. Oil treatment
- Insulation oil filling
- Circulation (Purifying insulation oil)

Pressure test (leak test)


Site testing
Protection circuit check
Electric test of transformer