Professional Documents
Culture Documents
Chapter 4
Chapter 4
Chapter 4
Chapter 4
Economic Analysis
of Transportation
Improvements
98 Economic Analysis of Transportation Investments
Topics:
Interest Equations and Equivalencies, Methods of Economic Analysis, An Application of Economic Analysis
Methods: Optimal Timing of Investments,
4.2.1 Introduction
4.2.2 Equivalent Uniform Annual Cost Method
4.2.3 Present Value of Costs
4.2.4 Equivalent Uniform Annual Return Method
4.2.5 Net Present Value Method
4.2.6 Internal Rate of Return
4.2.7 Benefit Cost Ratio Method
4.2.8 Evaluation Methods Using Incremental Attributes
4.3.1 Introduction
4.3.2 Economic Effect of Postponement
4.3.3 Effect of Multi-Year Implementation of Investments
4.3.4 Multi-stage Implementation of Investments
4.3.5 Optimization of Stage Implementation of Investments
4.3.6 Application of Optimization of Stage Implementation: Optimal Time for Road Paving
The fundamental principle underlying all engineering economic analysis is that the value of money is
directly related to the time at which the value is considered. A given amount of money at the current time is not
equivalent to the same amount at a future year. Typically, the combined forces of inflation and opportunity cost
result in decreasing value of money over time. Inflation refers to the increase in the prices of goods and services
with time, and is reflected by a decrease in the purchasing power of a given sum of money with time. Opportunity
cost is the income that is forgone at a later time by not investing a given sum of money at a current period.
99 Economic Analysis of Transportation Investments
The time stream of amounts of money that occur within a given time period can be displayed either as a
cash flow table or a cash flow diagram. On a cash flow table, there are two columns: one for time and the other for
amount. On a cash flow diagram, time is represented on a horizontal axis, while vertical arrows depict the inflow or
outflow of money at various points in time. The sign of the amount and the direction of the arrows in cash flow
tables and figures respectively indicate the movement of the amount: A popular convention is to represent money
“coming in” (i.e., deposits or benefits) by positive signs and downward arrows pointing towards the horizontal time
line in the cash flow table and figure respectively. This convention also stipulates that money “going out” (i.e.,
disbursements or costs) is represented by negative signs and upward arrows in the cash flow table and diagram
respectively. The entire payment period (often referred to as the contract period, payment interval, planning horizon,
or planning period) is represented by the interval between the present period (denoted by time = 0), and the end of
that period (denoted by time = N). The planning period is typically divided into a number of equal periods called
compounding periods, or simply referred to as period, which is often taken as one year. In economic analysis, it is
conventional to assume that all transactions that occur within the compounding period occur at the end of that
period.
The amount by which a given sum of money differs from its future value is typically represented as
interest. In this respect, a borrower of money from a financial institution at a current time, owes the initial amount
plus interest when the loan is due, to reflect for the fact that the value of the initial amount is not the same as the
value of the amount at the time of payback. Typically, lending institutions also add a small margin for profit.
The ratio of the interest paid at the end of the contract period (the originally agreed time between loan
acquisition and final payment) to the original amount invested at the beginning of the period, is termed the interest
rate. Therefore, a 10% interest rate, for example, indicates that for every dollar borrowed at the initial year, 10 cents
must be paid as interest at the end of each year. Central banks typically control of interest rates to remedy current or
expected economic problems. For instance, in a sluggish economy, the United States Federal Reserve Board
decreases interest rates to discourage saving and encourage individual spending and business investments, while
interest rates are increased when the economy is overheated. The interest rate typically undergoes several changes to
reflect the state of the economy. Therefore, the relationship between interest rate and the supply and demand for
money is a simultaneous one: interest rates are both a cause and effect of the market price of money.
In a stable economy such as those of developed countries, interest rates are typically lower than in
economies that have high inflation and are associated with uncertainty of investment returns. In developed countries,
the Minimum Attractive Rate of Return (MARR) typically ranges from 5-8%, while for most developing countries it
is estimated to be in the order of 10-15%.
100 Economic Analysis of Transportation Investments
The concept of interest rate is the underlying rationale for transforming amounts of or series of money from
one time period to another. This is addressed in Section 4.1.5 of this Chapter.
Figure 4-1 illustrates the various categories of interest rates. Such rates could be simple or compound,
discrete, continuous, fixed or variable.
Interest
Compound Simple
(Interest is earned on (Interest calculation is based only
principal plus the interest on the original principal amount)
earned earlier)
Discrete Continuous
(Interest is calculated (Interest is calculated
and added to the existing and added to the existing
principal and interest at finite time principal and interest at infinitesimally
intervals) short time intervals)
Interest may either be simple or compounded. In simple interest computations, the amount of interest at the
end of each period is the same as each of such amounts are a percentage of the initial amount, or principal. The
amount of compound interest in a given period is the interest charged on the total amount owed at the end of the
previous period, i.e., the sum of the principal and the previous period’s amount of interest. Therefore, amounts
borrowed on compound interest involve higher payments for amortization. Interests are typically computed using
compound interest rates.
101 Economic Analysis of Transportation Investments
Interests that are computed only at the end of each compounding period and with a constant interest rate are
typically referred to as fixed periodic rates, and the compounding period is 1 period for such cases, e.g., a fixed
annual rate, refers to the period of compounding as one year. Very often the compounding period is less than one
year, e.g., quarterly, monthly, or weekly. It is customary to quote interest rates on an annual basis, followed by the
compounding period if different from one year in length. For example, if the interest rate is 6% per interest period
and the interest period is six months, it is customary to speak of this rate as “12% compounded semiannually.” Here
the annual rate of interest is known as the nominal rate, 12% in this case. A nominal interest rate is represented by r.
But the actual annual rate on the principal is not 12% but something greater, because compounding occurs twice
during the year. The actual or exact rate of interest earned on the principal during one year is known as the effective
interest rate. The effective interest rate is computed by incorporating the effect of the multiplicity of compounding
periods. It should be noted that effective interest rates are always expressed on an annual basis unless specifically
stated otherwise. Table 4-1 shows how to compute effective annual interest rates for various scenarios of the
frequency of compounding within a year.
Table 4-1: Effective Annual Interest Rates for Various Compounding Frequency Scenarios
Frequency of Compounding Effective Annual Interest Rate Notation
Once a year =r
r = Nominal
Twice a year = (1 + r/2)2 – 1
Annual
Three times a year = (1 + r/3)3 – 1
Interest Rate
Every quarter = (1 + r/4)4 – 1
m = Number of
Six times a year = (1 + r/6)6 – 1
Compounding
Every month = (1 + r/12)12 – 1
Periods per year
m times a year = (1 + r/m)m – 1
Interest equations, also referred to as equivalence equations, are relationships between amounts of money
that occur at different points in time, and are necessary to transform amounts or series of amounts of money from
one time period to another taking due cognizance of the time value of money. The vital links in such relationships
are the interest factors, which are functions of the interest rate and the payment period. Interest factors are expressed
as a formula (see Tables 4-2 to 4-4), or as values derived from such formula (see Appendix 1).
Interest equations typically involve the following five key variables as shown:
P- The initial amount
F- The amount at a specified future period
A- Periodic (typically yearly) amount
i- Effective Interest rate for compounding period
N- The number of compounding periods, or the analysis period
102 Economic Analysis of Transportation Investments
In a typical problem, three of these variables are given and it is required to find the fourth. The initial
amount, P, refers to the money borrowed or sunk into an investment at the initial period (represented by time 0 on a
cash flow diagram), while F refers to a payment or amount received at a future date. The periodic payment is the
amount paid at the end of every compounding period either to amortize a loan or to set up a sinking fund to achieve
a target amount after a number of years. Periodic payments could be a uniform series, or they can be increasing or
decreasing in a systematic manner (most commonly, arithmetic or geometric). i is the effective annual interest rate
for each period, while N is the number of compounding periods or the payment period.
Tables 4-2 to 4-4 present the formulae, cash flow diagram and notation for various cases of interest
equivalencies and relationships. This is done for discrete compounding and continuous compounding of the interest
rate.
103 Economic Analysis of Transportation Investments
Table 4-3: Interest Formulae for Arithmetic Gradient series with discrete compounding
Description Cash Flow Computational Factor
Diagram Formula Computation
Finding the future
compounded amount (N-1)G F = G * GSCAF
(1 + i ) N − 1
(F) at the end of a GSCAF =
specified period due The Gradient Series i2
to linearly increasing 2G Compounded Amount
annual payments (G), 1G Factor, GSCAF (i%, N)
N
given the interest rate. 0G may be computed as −
shown. i
0 1 2 … N
F?
Finding the amount
of linearly increasing (N-1)G? G = F * GSSFDF
annual payments (G) GSSFDF
that would yield a The Gradient Series
future compounded 2G? Sinking Fund Deposit
amount (F) at the end 1G? Factor, GSSFDF (i%, N) i2
of a specified period, 0G? may be computed as =
given the interest rate. shown.
(1 + i ) N − 1 − N * i
0 1 2 … N
F
Finding the initial
amount, (P) that (N-1)G P = G * GSPWF GSPWF
would be equivalent
to specified linearly P? The Gradient Series Present
increasing annual 2G Worth Factor, GSPWF (i%,
payments (G), given 1G N) may be read off from (1 + i ) N − 1 N
the interest rate. 0G Appendix 1, or may be =[ 2
− ] / [1 + i ] N
computed as shown.
i i
0 1 2 … N
Note: 1) In column 4, upper and lower formulae are for discrete and continuous compounding, respectively.
2) For fixed discrete compounding yearly, i = nominal interest rate and N represents years.
3) When there is more than one compounding period per year, the formulae and tables can be used as long as there is a
cash flow at the end of each interest period. i represents the interest rate per period and N is the number of periods.
4) When the compounding is more frequent than a year, but the cash flows are annual, the formulae can be used with N
as number of years and i as the effective annual interest rate.
105 Economic Analysis of Transportation Investments
Table 4-4: Conversion Factors between Uniform Annual Series and Selected Non-Uniform Series
Linear Gradient
1 N
Series (G) to A = G* i − N *i
Equivalent Uniform e − 1 e − 1
Series (A)
Continuous
Compounding Geometric Series
(M) to Equivalent (1 + t ) N − e Ni e i − 1
Uniform Series (A) A = M * * Ni
1 + t − e e − 1
i
a
GSUAF, Gradient Series Uniform Amount Factor, can also be read off from Appendix 1.
1
The cash flow patterns are changing at a constant rate of t% per period. The initial cash flow in this series, M, occurs at the end
of period 1. The cash flow at the end of period 2 is M(1+t) and at the end of period N is M(1+t)N-1.
In some cases of investment economic evaluation, it may be more appropriate to consider the analysis
period as not finite, but perpetual in time. This is particularly the case where an investment is expected to recur
forever, such as most civil engineering structures (construction of bridges, highways, etc.) that will probably be
needed as long as there is a need for land transportation by humans. Consider the general case of an infrastructure
system that has periodic payments, R, made after every period, N (Figure 4-2). The period N is described as the life-
cycle or service life of that part of the infrastructure system that needs to be provided every Nth year. Such a
provision may involve removal of the existing component and its replacement, or the addition of a new component
on the existing component. The period N is assumed to be constant for this analysis, but it should be noted that N
could be increasing or decreasing as time goes on, depending on the level of usage and technological advances.
106 Economic Analysis of Transportation Investments
Increasing levels of usage, all else being constant would translate to decreasing values of N as time goes on,
and vice versa. Also, increasing quality of materials and other inputs would lead to increasing values of N, all else
being the same. In Figure 4-2, it is assumed that the initial investment, P is not the same as the periodic investments,
as recurring investments typically cover a lesser scope than the initial one. A case in point is highway construction,
where the initial investment includes right-of-way acquisition, embankment construction, relocation of utilities,
wetlands restoration and other costs aspects that are typically not found in recurring investments such as pavement
resurfacing or reconstruction.
P R R R R
Time
N N N N
∞
Present Worth all R payments made every N years in perpetuity is given by:
R R R
PWR ,∞ = + + + ...
(1 + i ) N
(1 + i ) 2N
(1 + i ) 3 N
1 1 1
= R + + + ...
(1 + i ) (1 + i ) 2 N (1 + i ) 3 N
N
1 R
= R − 1 =
1 − 1 (1 + i ) N − 1
(1 + i ) N
107 Economic Analysis of Transportation Investments
In some cases of economic evaluation, not only are there several times the interest rate is compounded
within a year, but it is possible for the frequency of compounding of such rates (and consequently, their periods) to
be so many that the number of compounding periods can be considered infinite. Consider the general case of an
investment where r is the nominal interest rate per year and m is the number of interest periods in a year. This means
that the interest rate per compounding period is given by r/m. The continuously compounded value of a single
amount P, after n years is given by:
m
r *r *n
F = P(1 + r / m) m*n
= P(1 + r / m)
But
m
r r
lim 1 + = e
m →∞
m
Therefore,
F = Pe r*n
er*n is defined as the continuously compounded amount factor for the case of infinitely multiple compounding
periods. Similarly, the continuously discounted value of a single future amount F, after n years is given by:
F
P=
e r *n
1/er*n is defined as the continuously discounted factor for the case of infinitely multiple compounding periods.
For the case of an infinite number of compounding periods in a year, the effective annual interest rate is given by:
F − P P (e r ) − P
= = er −1
P P
4.1.6.3 Present Worth of Continuously Compounded Payments with Continuously Compounded Interest
In yet another instance of economic evaluation, the cash stream may involve continuous compounding of
payments with continuously compounded interest within a year. Consider a general case where Rj payments are
made each year j. i is the interest rate per year, and r is the rate of growth of payments (expressed as a percentage)
per year (Figure 4-3).
108 Economic Analysis of Transportation Investments
R0 R1 R2 R3 Rn-1 Rn
Figure 4-3: Present Worth of Continuously Compounded Payments with Continuously Compounded Interest.
e r e 2r e nr e ( n+1)( r −i ) − 1
PWCCP ,CCI = R × 1 + i + 2i + ... + ni = R × r −i
e e e e −1
PWCCP, CCI = present worth of continuously compounded payments with continuously compounded interest.
The slope measured from a log-normal plot of payments vs. time (Figure 4-4), is r.
Where α is the ratio of future annual value estimate to first year value estimate, F/P,
And n is the number of years (period of estimate).
109 Economic Analysis of Transportation Investments
log ($Value)
log F
r
log P
Time
n years
4.2.1 Introduction
The evaluation of engineering projects is typically carried out using a broad range of criteria that may be
monetary or non-monetary or both. While non-monetary criteria involve effectiveness, the monetary criteria are
based on dollar values, and are therefore associated with project efficiency. In this regard, the fundamental principle
underlying all engineering economic analysis is that the value of money is directly related to the time at which the
value is considered. Therefore, the interest equations studied in Section 4.1.5 are a key aspect of economic analysis.
For economic analysis of engineering projects, benefits and costs are translated to their common dollar
values. For public projects such as non-toll road construction, there are not direct benefits, and therefore reduction in
road user costs is considered a benefit. There are six computational methods for economic analysis as identified and
discussed below. The first two methods are applicable only when all alternatives are associated with the same level
of benefits, and therefore cost minimization is the sole criterion.
1 Equivalent Uniform Annual Cost (EUAC)
2 Present Value of Costs
3 Equivalent Uniform Annual Return
4 Net Present Value
5 Internal Rate of Return
6 Benefit-Cost Ratio
[ ]
n
EUAC = P * USCRF (i, n) + ∑ ( M j + R j ) * SPPWF (i, j ) * USCRF (i, n) − S * USSFDF (i, n)
j =1
110 Economic Analysis of Transportation Investments
[ ] [ ]
n n
PVC = P + ∑ M j * SPPWF (i, j ) + ∑ R j * SPPWF (i, j ) − S * SPPWF (i, n)
j =1 j =1
The use of EUAC and PVC for economic evaluation is associated with the assumption that benefits across
alternatives are similar or their monetary values are difficult to determine. However, using costs alone for economic
analysis is inadequate if there are measurable and significant differences in values of benefits from one alternative to
another.
[ ]
n
EUAR = − P * USCRF (i, n) + ∑ ( B j − M j − R j ) * SPPWF (i, j ) * USCRF (i, n)
j =1
+ S * USSFDF (i, n)
[ ] [ ] [ ]
n n n
NPV = ∑ B j * SPPWF (i, j ) − P − ∑ M j * SPPWF (i, j ) − ∑ R j * SPPWF (i, j ) + S * SPPWF (i, n)
j =1 j =1 j =1
Investments associated with the highest NPV are considered the best investments.
∑ [B ] [ ] [ ]
n n n
∑ [B ]
n
[ ]
n
= P * USCRF (i, n) + ∑ ( M j + R j ) * SPPWF (i, j ) * USCRF (i, n)
j =1
The value of the interest rate that satisfies the above equations can be found using trial and error, or a
computer spreadsheet. If several alternative investments are being evaluated, the best investment is one that has the
highest IRR.
considered to be economically feasible, and the alternative with the highest BCR value is considered the best
alternative. The BCR of an investment is calculated as follows:
EUAB NPB
BCR = =
EUAC NBC
The U.S. Flood Control Act of 1936, in making a reference to the use of BCR for evaluating economic
feasibility, was probably the first organization to use this method of evaluation.
Table 4-5: Economic Evaluation Methods and Criteria for Choice of Best Investment
Criteria for Choice of Best Investment
Method of Economic Evaluation
Individual Approach Incremental Approach
Equivalent Uniform Annual Cost (EUAC) Lowest EUAC Lowest (EUAC - EUACBase Case)
Net Present Cost (NPC) Lowest NPC Lowest (NPC - NPCBase Case)
Equivalent Uniform Annual Return (EUAR) Highest EUAR Highest (EUAR - EUARBase Case)
Net Present Value (NPV) Highest NPV Highest (NPV - NPVBase Case)
Internal Rate of Return (IRR) Highest IRR that exceeds MARR Highest (IRR - IRRBase Case)
Benefit Cost Ratio (BCR) Highest BCR that exceeds 1 Highest (BCR - BCRBase Case)
113 Economic Analysis of Transportation Investments
4.3.1 Introduction
In the previous chapter, the economic evaluation of an alternative was made assuming a given project was
implemented immediately or in year 0. However, varying the time of implementing a project can result in very
different economic returns. Suppose a state government plans to build a four-lane highway through a region. Some
pertinent questions that may be posed include: “Should the highway be built now or some years in the future? If it is
114 Economic Analysis of Transportation Investments
to be delayed, what is the desirable year to start construction?” In the case where the location is such that the
highway will have little traffic if it is built now, the user benefit will not be sufficient compared to the construction
cost. In such cases, the government may prefer to postpone the construction by a certain number of years until such
a time that the new road will have enough traffic to produce sufficient user benefit. This type of decision is
particularly common in many developing countries. Finding a point in time when traffic grows high enough to
justify the project is considered as the optimal timing for the improvement project. The underlying assumption for
such analysis is that there is a growing demand for road services with time, reflected by increasing traffic levels.
This section discusses the procedures for determining optimal timing for transportation investments.
b1 b2 b3 b4 b5 b6 bn-1 bn
0
1 2 3 4 5 6 n-1 n Year
C
A: Implementing the Project immediately
b2 b3 b4 b5 b6 bn-1 bn
0 1
2 3 4 5 6 n-1 n Year
C
In Figure 4-5 the initial investment cost is denoted by C, while the benefit in each year is denoted by bt. Let
NPVt be the Net Present Value in the general case where the initial investment occurs in year t. Assuming that the
benefits associated with the occurrence of an initial investment start accruing in the following year, the Net Present
Value for Case A (ignoring the salvage value) is:
The algebraic difference between the above two equations for NPV0 and NPV1 yields the saving obtained
due to the delay of the postponement by one year, is given as follows:
i * C − b1
=
(1 + i )
The numerator in the above equation is the interest on initial construction cost minus the first year’s benefit
and the denominator is simply SPCAF. If S(1) is discounted to Year 1, the NPV0 equation 1 ends up with interest ion
initial capital minus the first year’s benefit. For the postponement by one year to be justifiable, it is obvious that first
year’s benefit should be less than i*C and it should be tested if additional postponement is also worthwhile.
Additional postponement by another year is worthwhile if NPV2 is greater then NPV1. In other words, S(2) must be
positive in order to justify postponement of the implementation by an additional year. Generally,
i * C − b2
=
(1 + i ) 2
116 Economic Analysis of Transportation Investments
S(2) must generally be positive to make the postponement of the implementation by one additional year
justifiable. Generally,
i * C − bt
S (t ) =
(1 + i ) t
The timing of the initial investment can be delayed as long as the NPV at year t is equal to or greater than
that of the previous year (i.e., as long as S(t) ≥ 0). The year at which NPV is just less than NPV at the previous year
(i.e., when S(t) becomes < 0) is the optimal year for implementing the project by carrying out the initial investment.
In other words, the optimal timing of the investment is the year at which bt is greater than i*C. Therefore the
decision criterion for deferring (or implementing) a project can be stated as follows:
This criterion is called the First Year Benefit (FYB) criterion. Whenever S(t) is less than 0, the interest on
the initial capital investment, C, is less than the first year benefit, bt. Therefore the FYB criterion can be restated as
follows:
1. If the ratio of the first year benefit to the initial cost, bt /C) is smaller than or equal to the interest rate,
defer the project,
2. If the ratio of the first year benefit to the initial cost, bt /C) is greater than the interest rate, then
implement the project.
The ratio bt /C is the first year rate of return. So the second criterion above is referred to as the First Year
Rate of Return criterion. As soon as the project implementation is justified by the criterion, it is imperative that the
implementation begins early enough to open the facility in year t, so that there is full benefit bt obtained by the end
of the first year. If the project implementation period is expected to last for a long time, the project must be started
well in advance, so that the implementation is completed by the start of the year t.
Figure 4-6 shows the gains from delaying a project by one year, S(t), and NPV of the project over a period
of time. NPV keeps increasing and reaches the point at which NPV becomes positive for the first time. This point of
time is called the breakeven year, nBE. From this point of time, the starting of the project is justifiable. From this
breakeven point, postponement of the project by one year will produce a net gain because the benefit increases and
NPV will grow until it reaches the maximum value. The point at which NPV is a maximum is the optimal time, nOPT
for implementing the project. As shown in Figure 4-6, NPV will be a maximum when S(t) is zero. After nOPT, the
gain by postponement by another year becomes negative and NPV starts to decrease.
117 Economic Analysis of Transportation Investments
S(t)
Time of
Implementation
NPV(t)
Time of
Implementation
nOPT
nBE
Figure 4-6: Net Present Value and Gain due to Postponement of Implementation.
Example 4.3-1
A county highway agency intends to build a bridge. The data below shows the cash flow of the project for a
period of 10 years. There will be a major improvement after 10 years. Find the optimal timing for the bridge project.
Assume MARR is 10%.
Year 0 1 2 3 4 5 6 7 8 9 10
3
Construction Cost ($10 ) -1000
3
Benefits ($10 ) -- 83 101 124 138 155 170 188 200 210 215
Year 11 12 13 14 15 16 17 18 19 20
3
Construction Cost ($10 )
Benefits ($103) 225 232 241 255 270 284 300 311 325 329
Solution
Five investment scenarios are considered: Construction in each year from year 0 to year 4. For each
scenario, the cash flows and present (at Year 0) worth of all such payments are calculated, and the net present value
is found (Table 4-6). The table shows that opening the facility in Year 1 produces an NPV of 300 when discounted
to Year 0. Since NPV is greater than 0, the project is feasible. The table also presents the NPV values if the project
were deferred. It can be seen that NPV values keep increasing with postponement of up to 2 years. After 2 years,
further postponement does not yield an increase in NPV. Therefore, the optimal time of implementing the project is
Year 3. Applying the First Year Benefit or the FYRR criterion would yield the same result as shown.
118 Economic Analysis of Transportation Investments
Table 4-6: Cash Flows and Present Worths for Different Project Timing for Example 4.3-1
Construction Starts Construction Starts Construction Starts Construction Starts Construction Starts
in Year 0 in Year 1 in Year 2 in Year 3 in Year 4
Year Cash PW year Cash PW year Cash PW year Cash PW year Cash PW year
Flow 0 Flow 1 Flow 2 Flow 3 Flow 4
0 -1000 -1000
1 83 74 -1000 -893
2 101 81 101 81 -1000 -797
3 124 88 124 88 124 88 -1000 -712 -1000 -636
4 138 88 138 88 138 88 138 88 138 88
5 155 88 155 88 155 88 155 88 155 88
6 170 86 170 86 170 86 170 86 170 86
7 188 85 188 85 188 85 188 85 188 85
8 200 81 200 81 200 81 200 81 200 81
9 210 76 210 76 210 76 210 76 210 76
10 215 69 215 69 215 69 215 69 215 69
11 225 65 225 65 225 65 225 65 225 65
12 232 60 232 60 232 60 232 60 232 60
13 241 55 241 55 241 55 241 55 241 55
14 255 52 255 52 255 52 255 52 255 52
15 270 49 270 49 270 49 270 49 270 49
16 284 46 284 46 284 46 284 46 284 46
17 300 44 300 44 300 44 300 44 300 44
18 311 40 311 40 311 40 311 40 311 40
19 325 38 325 38 325 38 325 38 325 38
20 339 35 339 35 339 35 339 35 339 35
NPV +300 +333 +348 +338 +250
119 Economic Analysis of Transportation Investments
Example 4.3-2
Consider a project that would take 4 years to complete. Figure 4-7A show the cash flow diagram if the
project is started immediately, and Figure 4-7-B shows the cash flows if the beginning of the construction is
postponed by one year. C1, C2, C3 and C4 are the costs for the first, second, third and fourth years of completion
respectively. The benefit streams start at the completion of the project, and they are counted at the end of each year.
The net present worth values for the two cases can be computed as follows:
C2 C3 C4 b4 b5
NPV0 = −C1 − − − + + …
1 + i (1 + i ) 2
(1 + i ) 3
(1 + i ) 4
(1 + i ) 5
C1 C2 C3 C4 b5
NPV1 = − − − − + …
1 + i (1 + i ) 2
(1 + i ) 3
(1 + i ) 4
(1 + i ) 5
The saving from deferring the project by one year, S(1), is obtained by subtracting NPV0 from NPV1, as
shown below:
i (C1 (1 + i ) 3 + C 2 (1 + i ) 2 + C 3 (1 + i ) + C 4 ) − b4 iC * −b4
S (1) = =
(1 + i ) 4 (1 + i ) 4
Where,
C* = C1 (1 + i ) 3 + C 2 (1 + i ) 2 + C 3 (1 + i ) + C 4
C* represents the sum of the discounted values of all the construction costs in the year preceding the
opening of the project. To justify one year delay of the project, S(t) should be greater then 0, or i*C* should be
greater than b4. The First Year Benefit criterion applied to this case in the same way as in the case of one-year
construction except that the construction costs should be compounded in the year preceding the first benefit year.
120 Economic Analysis of Transportation Investments
b4 b5 b6 bN-1 bN
0 1 2 3
4 5 6 N-1 N
C1 C2 C3 C4
b5 b6 bN-i bN
0 1 2 3 4
5 6 N-1 N
C1 C2 C3 C4
Figure 4-7: Cash Flows for Investments with Multiyear Implementation Periods.
Example 4.3-3
Assume a 3-year construction period for a project; benefits begin accruing in the fourth year. The
construction costs spread over three years, and $50,000, $250,000 and $200,000 are spent in the first, second and
third year, respectively. Yearly benefits for four years are tabulated in Table 4-7. The interest rate is assumed to be
6%.
Table 4-7: Yearly Benefits for Example 4.3-3
Year Benefits (in $103)
1998 31
1999 34
2000 37
2001 40
Solution
Table 4-8 shows costs discounted to the year preceding the first benefit year. Using FYB criterion, the first
year S(t) becomes negative is 1999, (b3 = 34, which is more than 521*6%). Since the construction takes 3 years, the
construction should start in 1996.
121 Economic Analysis of Transportation Investments
Example 4.3-4
Consider the following situation where a four-lane roadway is to be constructed to full capacity now or in
two stages (two lane road way is built now and additional two lanes are built n years from now). Construction costs
for the two cases are the following:
Single Stage Construction
Construct four-lane roadway now $1,866,000
Two Stage Construction
Construct two-lanes now $1,200,000
Construct additional two-lanes n years from now $1,866,000
For the purpose of simplifying the example, annual benefits for both cases are assumed to be the same and zero
salvage value at end of the service life. Assuming the service life is infinite, find which option is economically more
viable? Interest rate is 7%.
Solution
Since the annual benefits for both cases are the same, the Net Present Cost method can be used. Present
worth of cost for the single stage construction is:
PW1 = $1,866,000
PW of cost for the two-stage construction case is:
PW2 = $1,200,000 + $1,500,000*SPPWF(7%, n)
Sample calculations of PW2 for several values of n are
n=5 $1,200,000 + $1,500,000*SPPWF(7%, 5) = $2,269,500
n = 10 $1,200,000 + $1,500,000*SPPWF(7%, 10) = $1,962,450
n = 12 $1,200,000 + $1,500,000*SPPWF(7%, 12) = $1,896,000
n = 20 $1,200,000 + $1,500,000*SPPWF(7%, 20) = $1,587,600
n = 30 $1,200,000 + $1,500,000*SPPWF(7%, 30) = $1,397,100
122 Economic Analysis of Transportation Investments
A plot of PW of costs for the two cases is shown in Figure 4-8. The x-axis variable is the time the second
stage construction is conducted. PW of the single stage construction remains constant regardless of the second
construction time of the two-stage construction alternative. The present worth of the two stage construction
alternative decreases as the second construction is done 12 years from now. Until year 12, PW of cost for the two-
stage construction alternative is greater than that of single stage construction alternative. If the second stage is
needed before year 12, PW of cost for the single stage is smaller then PW of the two stage alternative. This implies
that if, in the two-stage construction, the second stage should be constructed before year 12, the single stage
construction is preferred. On the other hand, if the second stage construction is not needed until year 12, it would be
better to wait and build the facility in two stages.
Present
Worth
of Costs
($*106)
3.0
2.0
Single Stage
1.0
2-Stage
Construction
5 10 15 20 25 30
Year
Figure 4-8: Present Worth of Costs for Single Stage and Two-Stage Construction.
Total Costs
C1 C2
Year
Stage 0 Stage 1 Stage 2
(Existing)
t1 t2
The optimal timing of the two improvements in the example should be determined so that the total costs are
minimized. Assuming each stage construction is completed in one year, the present worth (PW) of all costs with
interest rate is:
t1 t2 ∞
PW = ∫ (a0 + b0 * t )e − i*t
dt + C1 * e −i*t1
+ ∫ (a1 + b1 * t )e −i*t
dt + C 2 * e −i*t 2
+ ∫ (a 2 + b2 * t )e −i*t dt
0 t1 t2
It can be noticed that continuous discounting is used for the above equation.
To obtain a set of timings, t1, and t2 that minimizes the present worth value, the PW expression is
differentiated with respect to t1 and t2, and the resulting partial derivatives are set to zero. After simplifying, optimal
values of t1 and t2 can be obtained as shown below:
C1 * i − (a0 − a1 )
t1 =
b0 − b1
C2 * i − (a1 − a2 )
t2 =
b1 − b2
The generalized form of optimal stage construction timing can be stated as:
C j * i − (a j −1 − a j )
tj =
b j −1 − b j
Where tj = optimal timing for any sequential upgrading from stage j to j+1
Cj = upgrading cost
aj, bj = coefficients of linear yearly cost functions
125 Economic Analysis of Transportation Investments
Total Costs
C1 C2
Year
Stage 0 Stage 1 Stage 2
(Existing)
t1 t2
Example 4.3-5
A developing country is planning to upgrade an existing 14.3 mile gravel road first by stabilizing it in a few
years from now and then providing an asphalt surface several years after the first improvement. The project will thus
have three stages and the base year is 1995. A strategy is needed for implementation of the project. The data on the
type of construction and unit cost for each upgrading are as follows:
1. From gravel surface to stabilized surface: $320,000/mile
2. From stabilized surface to asphaltic concrete surface: $400,000/mile
From previous similar type of projects in this particular region, the continuously increasing recurring cost
functions (user and maintenance) are estimated as follows:
Stage 0 (from 1995 to year of stabilizing): 2.93 + 3.41t
Stage 1 (from year of stabilizing to year of asphaltic concrete surfacing): 2.59 + 3.41t
Stage 2 (after asphaltic concrete surfacing): 2.17 + 2.88t
Where t is the number of years from the base year.
What would be the optimal year for successive regarding? Assume that traffic growth is linear and the MARR is
5.5%.
Solution:
Construction cost for each upgrade is as follows:
C1 = $320,000 * 1.43 = $4,576,000
C2 = $400,000 * 1.43 = $5,720,000
126 Economic Analysis of Transportation Investments
Stage j aj bj
0 2.93 3.41
1 2.59 3.14
2 2.17 2.88
Applying the general equation for optimal stage construction timing yields:
So, the stabilizing should be done in 8 years from 1995 and then in another two years the road should be
upgraded to an asphalt surface.
The above example assumes linear increasing function of recurring costs. However, in practice, annual
recurring costs can be rather exponentially increasing (Figure 4-10) because the traffic increase is exponential and
expressed in percent per year. In this case the recurring costs can be expressed as ai + bi*ekt, where k is the annual
traffic growth rate. The optimal timing (tj) for stage construction with exponentially increasing cost function can be
derived in a similar manner, and is given by:
C j * i − (a j −1 − a j )
log e
b j −1 − b j
tj =
k
Example 4.3-6
A two-lane 12.5-mile highway section has a current Average Daily Traffic of 6,500 vehicles. The highway
is in a poor condition causing excessive user and maintenance costs each year. Due to the high demand of this
highway, the county has decided to do a major improvement. It will include the reconstruction of the existing
pavement in addition to building two new lanes. However, because of high cost and funding problems, the county is
planning to do the reconstruction in stages. The county will undertake the setting up of a sinking fund to finance the
project where an annual deposit will be made until the completion of the project. The fund is expected to earn 10%
per year. The recurring annual cost functions (in $105) are exponential and of the form: a + b*ekt where k is traffic
growth rate and t is time.
127 Economic Analysis of Transportation Investments
The plan is to implement the project in the following stages and it is expected that the construction in each
stage can be completed in one year.
0 Current
- 0.62 0.20 -
Reconstruction of the old
1 pavement 4.72 0.413 0.14 5.1
From the given data, we will determine the optimal timing to start each stage. Knowing that the depositing
in the fund will start at the beginning of the project, how much should be deposited annually for each stage? Assume
MARR = 6.5 %.
4.3.6 Application of Optimization of Stage Implementation: Optimal Timing for Paving Low-Volume Gravel
Roads (Bhandari and Sinha, 1985)
Gravel surface roads are generally adequate for most situations of low volume traffic. However, as traffic
increases, the maintenance and vehicle operating costs also increase. Therefore, it is eventually necessary to
consider paving the gravel surface. In order for the paving the road to be economically viable, savings in
maintenance cost and user cost should be substantial enough to justify the construction cost. If maintenance cost is
assumed to be constant over time, traffic volume, which benefits by the improvement, should be large enough to
produce much savings in comparison to improvement cost. In most cases of gravel low-volume road, the base year
volume is low so that investing the capital is hardly returned if construction is conducted in base year (n0). In that
case, it is preferred postponing the construction until it is, at least, economically feasible to pave the road. When the
base year volume is low but increasing with time, it is possible to invest the capital somewhere else in the economy
to obtain returns that are in excess of the benefits foregone during the years that construction is deferred. If the
concept of break-even analysis is applied to determine the cut-off volume (and the corresponding year) above which
it is economically feasible, this volume represents the minimum volume, above which the net present value of
paving is in excess of zero. But, it is more advantageous to postpone construction beyond the break-even volume
128 Economic Analysis of Transportation Investments
until such time when the net present value is maximized. The net present value by paving the road in the year in
which first year benefits are equal to the interest rate by First Year Benefit criterion described in the previous
section. The volume of traffic in this year is referred to as the optimal volume. If the road is paved a year before the
optimal volume, it would mean foregoing excess benefits that could be obtained from an alternative investment in
the economy, while paving the road a year after, would mean losing excess benefits that could have accrued had the
road been paved a year earlier. This typical situation is illustrated in Figure 4-11. The top portion of the figure shows
the stream of annual net benefits arising from paving the road in the year, say n1.
Compared to the benefit patterns in Figure 4-11, annual net benefits is increasing somewhat exponentially
rather than linearly increasing. The net benefits of paving the road in any other year should be the same as shown,
except for the years before paving when the net benefits are zero. For example, the net benefits corresponding to
construction in the break-even year (nbe) and the optimal year (nopt) would be correspond to the lines 0nbepq and
0noptq, respectively. The lower portion of the figure shows the net present value of the entire project, given the year
of construction. The points nbe and nopt correspond to zero and maximum net present values, respectively.
Figure 4-11: Net Present Value as a Function of the Year of Construction [Bhandari and Sinha, 1985]
129 Economic Analysis of Transportation Investments
In order to appropriately analyze the project, it is necessary to properly define important factors such as
service life, costs and benefits. For most road project it is true that a newly constructed facility will have a fixed
physical life varying from 15 to 49 years. However, generally, or often the case, major rehabilitation will be done at
the end of this period and in subsequent periods to perpetuate the useful life of that facility. For road projects, this is
often done in the form of major reconstruction and overlay, whenever the serviceability of the pavement has fallen
below an acceptable level. Under this assumption, benefits may be assumed to accrue indefinitely, for all practical
purposes. Thus, service life is assumed be infinite. The frequency of major rehabilitation is assumed to be planned in
advance, even though the physical life of a pavement is a function of the design standard and the traffic volume that
it is subjected to. Gain in salvage values being zero by deferring construction a few years can be also explained
using the concept of this indefinite service life. The primary costs associated with road projects consist of the
construction, routine maintenance, planned rehabilitation and vehicle operating costs. Construction costs are
assumed to occur only in the first year of construction while routine maintenance costs are assumed to remain
constant over time. Major rehabilitation costs are planned to occur every N years, where N is presumably close to the
physical life of the pavement.
The benefits from paving a gravel road comprise largely of the reduction in the total vehicle operating and
routine maintenance costs. Net benefits are then obtained after allowing for the construction and rehabilitation costs.
Let the variables relevant to a gravel road being considered for paving be defined as follows.
The present value (PV) of various cost elements per km of roadway are obtained as follows:
PV of construction costs
1
= *C
(1 + i ) n
130 Economic Analysis of Transportation Investments
1 R
= *
(1 + i ) (1 + i ) N − 1
n
It should be noted that the road is kept in service indefinitely through periodic rehabilitation.
PV of savings in routine maintenance costs
1 ( m − m' )
= *
(1 + i ) n
i
1 1+ k
= * Qn * 365 * (c − c' )
(1 + i ) n
i−k
for k < i,
Where
Qn = Q0*(1+k)n, and
(1+k)/(i-k) = the discount factor for present value of a geometric series with growth rate k and
discount rate i, over an indefinite period (for k < i).
1 1 + k m − m' R
NPV = * Qn * 365 * ( c − c ' ) + − C −
(1 + i ) n i−k i (1 + i ) N − 1
If the breakeven year is now denoted by n, then the break-even volume, Qbe, may be obtained by setting the
NPV equal to zero in the above equation.
R ( m − m' )
C+ −
(1 + i ) − 1
N
i
Qbe =
1+ k
365 * (c − c' ) *
i−k
131 Economic Analysis of Transportation Investments
Provided the base year volume, Q0, is less than the volume in the break-even year (Qbe), the break-even
year, nbe, may then be obtained as follows:
Qbe = Q0 (1 + k ) nbe
log e (Qbe / Q0 )
nbe =
log e (1 + k )
The optimal year for paving the gravel road is obtained by maximizing the NPV equation with respect to n.
However, as seen in Figure 4-12, with the discount rate equal to the opportunity cost of capital, the net present value
is maximum when the undiscounted net benefits in the year of paving are equal to zero. For such maximum to exist,
it is necessary that the benefits increase monotonically with time. This is ensured as long as the savings in the
vehicle operating costs and traffic growth rate both non-negative. The net benefits in the first year after paving are
given as follows:
Ri
NPV = Qn * (1 + k ) * 365 * (c − c' ) + (m − m') − Ci −
(1 + i ) N − 1
To obtain the optimal volume Qopt, Qn is substituted by Qopt in the above expression and set it equal to zero.
R *i
Ci + − ( m − m' )
(1 + i ) N − 1
Qopt =
365 * (c − c' ) * (1 + k )
Again, if Q0 is less than Qopt, the optimal year of paving, nopt, is obtained as follows:
log e (Qopt / Q0 )
nopt =
log e (1 + k )
The break-even and optimal years obtained from the nbe and nopt equations are rounded to the nearest whole
numbers, in line with the usual assumption of year-end cost outlays.
132 Economic Analysis of Transportation Investments
Net
Present
Value
(NPV)
Year of
0 Implementation
nbe nopt (Construction)
Example 4.3-7
A 40-km gravel surface road on a reasonably good alignment is now carrying an annual average daily
traffic of 100 (10% truck). The traffic is expected to grow at an annual rate of 5% compounded (for each road type
and all vehicles). The minimum attractive rate of return is 10% per annum. It is proposed to pave the road with
minor reconstruction and the rest of the project details are shown below:
Item Value
1. Road Paving or Reconstruction Cost $50,000 per km
2. Road Maintenance
$600 per km/year
a) Existing Road
$450 per km/year
b) Paved Road
3. Vehicle Operating Costs on a Gravel Cars- 10 cents per day
Surfaced-Road Trucks- 12 cents per day
4. Vehicle Operating Costs on a Cars- 7 cents per day
Bituminous Surfaced-Road Trucks- 9 cents per day
$25,000 per km every 10
5. Rehabilitation/Resealing Cost
years
Determine:
1. The optimal year of paving and the break-even year of paving
2. The traffic volumes at the optimal year of paving and the break-even year of paving
3. The first year benefits and costs after the year of paving
4. The sensitivity of break even and optimal traffic volumes (and their corresponding years) with respect
to the interest rate.
Solution
1. Average operating cost per veh-km on gravel surface is:
c = 0.9 × 0.1 + 0.1 × 0.12 = $0.102/veh-km
133 Economic Analysis of Transportation Investments
Using the equations for break-even traffic volume and year, and the optimal volume and year are obtained,
as shown below:
25000 * 0.10
50000 * 0.10 + − (600 − 450)
Qopt = 1.110 − 1 = 558vehs / day
365(0.102 − 0.072)(1 + 0.05)
Ri
= C *i +
(1 + i ) N − 1
25000 * 0.10
= 50000 * 0.10 + = $6568.63
(1 + 0.10)10 − 1
134 Economic Analysis of Transportation Investments
Ri
= C *i +
(1 + i ) N − 1
25000 * 0.10
= 50000 * 0.10 + = $6568.63
(1 + 0.10)10 − 1
3. The sensitivity of the break-even volumes and their corresponding years is presented as follows:
1000
800
600
Traffic Volume
Qbe
Qopt
400
200
0
0 5 10 15 20
Interest Rate (%)
50
40
30
Years
nbe
nopt
20
10
0
0 5 10 15 20
Interest Rate (%)
EXERCISES
1) What is the difference between fixed annual rate and effective annual interest rate?
2) Under what assumption can ‘Equivalent Uniform Annual Cost’ or ‘Present value of cost’ method be used
for evaluation of engineering projects?
3) What is the First Year Benefit criterion? What is the First Year Rate of Return criterion? What are they
used for?
4) What is breakeven year? How is it related to NPV? What is the optimal year?
5) What fixed annual interest rate compounded monthly yields an effective annual interest rate of 19.56%?
6) Derive an expression for calculating the present worth of a geometric gradient series with an interest rate of
i% compounded continuously over a period of n years. The series starts with an amount of M at the end of
first year and grows at the rate of r% per year.
7) Derive a generalized expression to compute the present worth of a geometric gradient series with an
interest rate of i% per year over a period of N years (compounded annually). Assume that the cash flow at
the end of year one is M which grows at f% per year.
8) The rate of growth of traffic on a newly constructed bridge is 3% per year. By the end of first year 500,000
vehicles would have used it. Determine the number of vehicles using the bridge in the tenth year of service.
Assuming that a toll of $0.75 is collected per vehicle, calculate the present worth of the total toll collections
during the ten-year period using the equation derived in problem-6. Assume an interest rate of 10% with
continuous compounding. For simplicity cash flows can be considered discrete, occurring at the end of each
year.
136 Economic Analysis of Transportation Investments
9) Calculate the present worth of the cash flow diagram shown below. Assume interest is compounded
monthly.
0 1 2 3 4 5 (Years)
10) 20 equal annual payments, of $2000 each, are made starting one year from today. What is the future
equivalent value of this series at the end of 20 years? Assume 10% interest per year.
11) Consider the following two alternatives for a transportation project:
Alternative A Alternative B
Initial investment $ 50,000 $ 100,000
Annual maintenance cost $ 15,000 $ 10,000
Annual User Benefits $ 20,000 $ 25,000
Useful life (years) 10 10
Salvage Value $ 20,000 $ 25,000
12) Three alternative designs are being considered for a potential improvement project related to the operation
of an engineering department. The prospective net cash flows for these alternatives are shown below.
MARR is 15% per year.
End of year A B C
0 -$200,000 -$230,000 -$212,500
1 $90,000 $108,000 -$15,000
2 $90,000 $108,000 $122,500
3 $90,000 $108,000 $122,500
4 $90,000 $108,000 $122,500
5 $90,000 $108,000 $122,500
6 $90,000 $108,000 $122,500
Apply the IRR method and the NPV method using incremental analysis procedure to select an
alternative. (Source: Engineering Economy, Degarmo, E. P. et al.)
13) The alternatives for an engineering project are reduced to three designs. The estimated capital investment
amounts and annual savings are shown in the table below. Assume that the MARR is 12% per year, the
study period is six years, and the market value is zero for all three designs. Apply the NPV method to
determine the preferred alternative. (Source: Engineering Economy, Degarmo, E. P. et al.)
Hint: Use the expression derived in Problem-7 for Design-1.
14) You loaned out an amount of $12,500 at an interest rate of 13% per year for a period of six years. How
much total interest would you owe at the beginning of the 4th year? Assume that you make no payments
until the end of loan period and interest is compounded annually.
15) Draw a cash flow diagram for a $15,000 loan which needs to be repaid over a 5 year period in equal
uniform annual amounts. What is the amount of annual repayment if the interest rate is 12%?
138 Economic Analysis of Transportation Investments
16) Answer the following questions with reference to the cash flow diagram shown below:
(i) What future sum can be accumulated in 5 years with equal annual payments of $1,000 if the interest
rate is 10%?
(ii) What is the amount of uniform annual payment required to provide a future sum of $10,000 in 5 years
from now if the interest rate is 10%?
(iii) You want to accumulate a future sum of $15,000, but you can afford to pay only $1000 per year. If the
interest rate is 12%, what is the minimum number of years you will take to accumulate that money?
(iv) You make uniform annual payments of $1,000 each for 10 years. If you accumulate an amount of
$20,000 at the end of 10 years, what is the interest rate?
A A A A
0 1 2 … N
F
17) The initial investment for constructing a road is $500,000. The maintenance is expected to cost $15,000 per
year for the first 5 years of service, followed by $30,000 per year for the next 5 years. A rehabilitation
program is scheduled at the end of 10th year costing $150,000 after which the maintenance costs are
expected to reduce to $20,000 per year. What is the equivalent uniform annual cost over a 20 year period of
service if money is worth 8% per year? What is the equivalent present worth of all the road expenses?
18) A rehabilitation program is scheduled 4 years from now. If the expenditure is expected to be $50,000 then,
what amount should be set aside now to provide for that expenditure? Assume that funds earn 8% interest
per year.
19) A bridge project is considered for which two alternatives are being studied. Under the first alternative, a 4-
lane bridge will be constructed now for $5,000,000. The maintenance cost would be $30,000 for the first
year which is expected to increase by $2500 per year. Economic salvage value at the end of 20 years is
$1,000,000. The second alternative is to construct a 2-lane bridge now costing $3,000,000. Maintenance
would be $30,000 per year for 10 years. At the 10th year 2 more lanes would be added to accommodate for
the expected growth in traffic. This would cost $4,000,000 after which the maintenance cost for the new
facility would be $60,000 per year. Economic salvage value at the end of year 20 is $1,500,000. If the
interest rate is 10%, should the deferment of 2-lanes be preferred?
20) The cash flow table below shows expenditures and benefits for the construction of a parking facility
assuming that the construction takes place now. Find the optimal timing for the project. MARR is 9%.
Year 0 1 2 3 4 5
Construction Cost $100,000
Benefits -- $5000 $8000 $10,000 $13,000 $15,000
139 Economic Analysis of Transportation Investments
21) A transportation facility has a linear cost function given by: $(30,000 + 15,000*t ) where t is in years. A
rehabilitation program is planned in two stages. The maintenance cost function after stage-1 is expected to
be linear given by: $(25,000 + 10,000*t)
And the cost function after stage-2 is given by: $(20,000 + 8000*t)
The costs of implementing stages 1 and 2 are $300,000 and $200,000 respectively. Find the optimal timing
for each stage. MARR is 8%.
22) Find the present worth of the following cash flow diagram if i=18%. (Hint: The given series can be looked
at as a cumulative sum of various uniform and gradient series, positive and negative).
100 100
150 150
200 200
250 250
300 300
350
23) You deposit funds which represent an arithmetic gradient series. The first deposit is at the end of month 2
of amount G. The amount increases by G every month. You deposit till the end of 2 years. What is the
value of G if you want to accumulate $100,000 at the end of 2 years? The interest rate is 12% per year
compounded monthly?
24) The capital investment for a project is $100,000 now. This is to be repaid by a uniform annual series in 5
years. What is the annual repayment amount if the interest rate is 12% per year compounded monthly?
25) What is the effective annual interest rate for a nominal annual interest rate of 13% compounded
continuously?
26) A highway improvement is scheduled every 5 years in perpetuity. Each improvement costs $50,000. What
is the present worth of all the costs of the improvement project if the interest rate is 8% per year?
27) If the current year (beginning of year 1) user benefit from a road improvement is $5 million and the total
project cost is $80 million, what must be the minimum rate of growth of benefit in % per year, for the
project to be economically viable? Assume that the project life is 25 years and the benefit grows
continuously. The interest rate is 8% per year compounded continuously.
140 Economic Analysis of Transportation Investments
REFERENCES
1. AASHTO (1997)
2. Winfrey (1970)
(Full detail of incomplete references will be provided to the students in due course.)