Professional Documents
Culture Documents
Naveed E&I Engr
Naveed E&I Engr
NAVEED
E‐Mail: engr.naveedawan90@gmail.com
CELL NO # 059 603 9440 (KSA)
Iqama Transferable: YES
QUALIFICATION: Bachelors of Science in Electrical Engineering
ELECTRICAL & INSTRUMENTATION ENGINEER
Extensive experience in EPC Projects in term of Engineering | Procurement |Construction| Commissioning| Project
Planning Estimation |Project Execution in Saudi Aramco projects & renewable energy Wind Power projects.
Core Competencies
PROFESSIONAL PROFILE
Offering 8 years of enriched cross‐cultural experience as an Electrical and Instrumentation Engineer in Saudi
Aramco Projects pipelines (Remote Headers, Valve Station, GGM, LSS, GCP, OPTF & Aramco buildings) and
Renewable wind power projects and huge Oil and Gas production plants in Pakistan.
Develop and familiar with Aramco standards & drawings , Method Statements, Scope of work, BOQ, MTO ,
Preparation of Material Requisitions, raised TQ when required , review contractual documents ,
Execution of Electrical (LV and MV), Instrumentation, cathodic protection (Temporary and Permanent) &
communications works . Complete construction activities (erection of all electrical and field
Instrumentation equipment’s and its associated cable laying and termination. Erection of OHPL power lines,
stringing and tie in with existing line, CCTV, IVPS, Communication System (OSP & ISP).
COMPANIES NAME:
i. CHINA PETROLEUM PIPELINE ENGINEERING KSA
ii. ARAKD ENGINEERING AND CONSTRUCTION KSA
iii. DESCON ENGINEERING LIMITED PAK
PROJECTS WORKED:
Saudi Aramco North Gas Compression Plants Pipelines NGCP HWYH LSS, HWGCP‐1, HWYH GGM, (HWYH LSS
NORTH HRDH GGM, HDGCP (1 & 2), HWYH OSB REMOTE HEADERS & OPTF’S).
Mazalij and Abu Jifan Saudi Aramco pipeline project (Khurais Al crude increment project ‐300 MBCD
50 MW Metro Wind Power Project, 132/22KV Hybrid Grid Substation, N100 Wind Turbines Nordex.
50 MW Yunus Wind Power Project 132/22KV Hybrid Grid Substation, N100 Wind Turbines Nordex.
50 MW Gul Ahmed Wind Power project, 132/22KV Hybrid Grid Substation, N100 Wind Turbines Nordex.
MOL PAKISTAN OIL AND GAS CO. B.V (GPF and CPF Facilities)
China Petroleum Pipeline Engineering Company | Saudi Aramco | NGCP Project
February 2019‐ Present
E&I ENGINEER
My job responsibilities was under the scope of all electrical , Instrumentation and telecom works in , Remote Headers
and valve stations (Total NOs 26) , OPTF (Total NOs 189) and 13.8 KV Overhead power Lines (OHPL) total Length 60 km
, cathodic Protection (Temporary and Permanent) and Communication system (OSP & ISP) .
Submit daily report, one day look‐ahead plan, and 3‐Weekly look ahead schedules to management/client and attend
meetings with procurement on material delivery schedule on weekly basis.
Making the Redlines drawing, as built drawing as per site condition meanwhile conduct meetings and get approval
from Saudi Aramco. In case of deviation as per IFC, generate TQ (Technical Query) to design department.
As changes are approved, revised MR (Material Requisition) and follow up revised PO and update procurement to
purchase the item on basis of new MR.
Attend weekly meeting with PMT of Saudi Aramco, develop strong co‐ordination with sub‐contractors, vendors and
commissioning team with providing technical support to construction team.
Coordinate with operation department and permit issuer for Tie‐in (temporary shutdown of OHPL for modification of
existing poles or replacement wooden pole for new tap‐off pole) & working in Aramco existing facilities.
Coordinate with engineering & procurement department in case of any technical issues for execution of work, SOW
(scope of work) and preparing method statement and JSA and get approval from client.
Follow up with procurement department for pending material on daily basis for priority activities and coordinate with
planning department for achieving milestone within time.
Installation/termination & Erection of Pad mounted transformer, Switch racks, power panel, lighting control panel,
Dry type transformer, Power supply to Motor Operated Valve (MOV’s) and RTU components inside the remote
headers and valve stations.
Installation of cable laying MV , LV and DC power cables as per drawing and ensure cable shall be direct buried or pre‐
cast duct bank along with warning tapes , cable marker and approved backfill material.
Follow up and make sure that site execution team perform Megger test of MV and LV cable before/after cable laying
and HIPOT test for medium voltage cable and also make sure that testing equipment is calibrated.
Installation and energization of mounting pole terminal transformers and pad mounted transformer and before
energization testing of transformer (Resistance test of all windings, Ratio and polarity test.
Installation/laying of grounding grid with its associated grounding cable, grounding rod and connection (thermo weld
/clamp) and provide connection to transformer , switch‐rack , fence ,lighting poles and skid mounted equipment
meanwhile perform ground resistance test.
Installation of area lighting, task lighting, security lighting (Solar Panel) and indoor lighting providing lux as per Aramco
standards and also execute photocell control for outdoor lights.
Conduct complete survey and field marking of all types of overhead poles and make sure that new pole is at proper
distance from existing facilities, transmission lines & underground cables.
Installation / erection of different types of overhead pole which includes Tangent riser pole , Dead end riser pole ,
double dead end riser pole , angle poles and terminal poles with complete accessories and modification of existing
steel pole to New tap off pole and meanwhile stringing/pulling of conductor as per approved procedure.
Installation of communication cabinet, fibre patch panel, laying of FOC cable, splicing for foc cable, Installation of HDPE
conduit and sub ducts.
Developed instrument datasheets, specifications, Instrument Loop Diagrams (ILD), Wiring diagrams, Instrument Hook‐
up Diagrams, Cable Routing Layout & Point and lines diagrams, Control Room Layout, Cable/JB schedules, Index, I/O
lists, MTO.
Functional Tests of Pressure, Flow, Temperature, Level instruments, Analyzers, Control / On‐Off Valves, Fire&
Gas Instruments
Installation of CCTV cameras, camera JB and its associated cable laying with termination.
Provide temporary cathodic protection & permanent cathodic protection for the protection of new and existing
pipeline.
Installation of test station (3 pin & 1‐pin) after every KM intervals & bonding box (2T, 3T & 5T) should be done in
accordance with IFC drawings.
For installation of ICCP (Impressed current cathodic protection) perform drilling up to 120 Meter by vertical drilling
machine, after installing UPVC casing and perform leak test, lowering of 18 Anodes (high silicon cast iron) with
accessories.
Installation & termination/tagging of positive junction box, negative junction box and CP rectifier (20A/100VDC)
with remote monitoring unit and laying of CP cable should be done in accordance with Saudi Aramco CP procedures.
ARKAD Engineering and Construction CO. | Saudi Aramco | Mazalij Project
Jan 2017 to Jan 2019
Electrical Engineer
My responsibilities was related to all the electrical activities inside the valve stations and remote headers , including
OHPL activities and cathodic protection (Temporary and permanent )
Installation of different types of overhead pole with complete accessories and execute stringing/pulling of conductor
as per deadline and perform test during inspection.
Laying of 13.8KV medium voltage (MV) cable between the riser poles and pre‐cast duct bank, if crossing underground
pipelines & supervise the MV cable splicing.
Erection of pole & pad mounted transformer, Switchracks, power panel, lighting control panel, Dry type
transformer, area lighting poles, task lights and receptacle.
Grounding for equipment, steel platforms, lighting poles and fence grounding install all necessary grounding
connection & tie in to main grounding grid.
Laying of power cables, underground / on road crossing laying of cable via duct bank, ensuring the separation of
power cable, instrument cable & communication cable and providing the necessary cable route marker/post marker
& standards sign as per Saudi Aramco standard.
Installation , pre‐commissioning & commissioning of pad mounted transformer , pole mounted transformer and
dry type transformer 300KVA , 34.5KV /480V 3Ph to feed switch rack , MOV receptacles circuits ,power panel &
lighting contractor panel for new task lighting.
Supply and installation of Switch racks inside valve stations to feed motor operated valve, corrosion inhibitor skids
& new power panel for area lighting, task lighting & power receptacles.
The installation /soaking of galvanic anodes (magnesium) & cad welding its respective cable to crude pipeline and
measure the pipe to soil potential with reference to Cu/CuSO4 reference electrode.
Perform the holiday testing (rating up to 18KV) to ensure the cable (HMWPE) is not damaged before lowering of
anode.
For installation of ICCP (Impressed current cathodic protection) perform drilling up to 120 Meter by vertical drilling
machine, after installing UPVC casing and perform leak test, lowering of 18 Anodes(HSCI) with accessories.
The backfilling of coke breeze in borehole without water mixing and check the resistance of each anode as the coke
breeze is being installed.
Installation & termination/tagging of positive junction box (20T), negative junction box (5T) and CP rectifier
(20A/100VDC) & connect the Ethernet cable from CPMS to patch panel for monitoring and laying of CP cable should
be done in accordance with Saudi Aramco CP procedures.
Installation of test station (3 pin & 1‐pin) after every KM intervals & bonding box along pipelines and inside the valve
stations.
DESCON ENGINEREING LIMITED | 150 MW WIND POWER PROJECTS |GRID STATIONS
Nov 2014 to Dec 2016
QC Engineer –Electrical
Working on a turnkey project of 150 MW Wind Power Project includes Installation, testing and
commissioning 132/22KV Hybrid Grid Substation (Alstom) & 40 Wind Turbines provide by Nordex.
Ensure and review all Electrical technical documentation is in accordance with the project requirement
for quality inspection plan (QIP), Budget of quantity BOQ, work order (WO), Division of responsibilities
(DOR), standards and codes.
Inspection of Electrification in which including loop testing and lighting circuit verification , related cable
pulling & termination in Distribution board , allocation of lighting fixture & power socket as per
approved drawing and ensuring approved material is used .
Supervision of cable termination of rotor and stator at wind turbine nacelle side and meanwhile power
cables jointing at Top, M2 & M1 section of turbine and termination of all power cable at converter.
Turbines are provided by NORDEX.
Cable laying of MV cable from turbine to turbine & substation. & its meggering (IR) & HIPOT test of
power cables. All the results should compliance with FAT reports.
Installation & Testing of Power Transformers, Grounding transformers, Surge arrestors, current
transformer , voltage transformer, , Earthing mesh and Lightning protection system.
Conduct physical inspection of turbine step up transformer over current & earth fault relay.
Megger test of Instrument Transformer from primary to ground, secondary to ground & primary to
secondary windings including turn ratio and polarity test.
Inspection of earthing to verify grounding connection, continuity & ground resistance measurement.
Inspection of power transformer includes verification of ratio & functional test for buchloz relay,
thermal relay, and oil level and temperature indicators for transformer.
Perform field inspection services of Electrical related works at site. Attend daily applications for
inspection as per the Inspection and Tests procedures and the quality plans and systematically report
inspection results.
Ability to make quality inspection plan, method statement & raise the request for inspection,
meanwhile generate NCR & FQA when required. Inspection of Incoming material & keeping record
update.
Good understanding of Layout Drawings, schematic drawings, SLD, Control and interlocking diagrams,
Protection and Logic diagrams.
DESCON ENGINEREING LIMITED | MOL PAKISTAN OIL/GAS PROJECT |GPF FACILITIES
Jan 2013 to April 2014
Assistant Engineer‐Electrical
Good understanding about all drawing SLD single Line diagram, power layout, lighting layout, grounding
layout and schematic diagram etc.
Inspection for Laying of power cable & control cable in trench or cable tray & termination of cable.
Installation & Inspection of Cable tray (Ladder & perforated) i.e. ensure that cable tray routing, hot dip
galvanized condition & approved vendor material
Perform and ensure continuity test and Megger (IR) test of power cables, control cables & motor
winding and record the results for pre‐commissioning
Perform the HI‐Potential Test of power HV Cables & measures the leakage current
Installation Inspection & Testing of Bus bar Installation.
Erection & commissioning of three phase motors and insulation resistance of winding) & Solo Run Test.
Conduct Motor No Load test and Full Load test.
Installation/Inspection/ Testing of Motor. (Temperature, Vibration, Rotation & Bearing sound).
Perform transformer turn ratio (TTR) of Power transformer and Dry type transformer.
Familiar with hazardous area classification & IP ratings, QA/QC, QIP’s, MTC, check lists Method
Statement, Punch list close out.
Installation, Commissioning, testing of power generators driven by WAUKESHA gas engine model #
G3516C,(2.5MW,415V,50Hz) and diesel Generator of Model DG‐3406 series by caterpillar
(1020KW,415V,50Hz).
Installation, Commissioning, testing and Maintenance of A.C UPS 32 KW and DC UPS 5.5 KW by GUTOR
Electric Ltd Switzerland.
Training and Certifications
Registered in Saudi Engineering Council SEC
Registered in Pakistan Engineering Council PEC
Degree Attested by Higher Education Commission HEC
Attend training of Project Management professional PMP
Safe electrical lock out, tag out and try procedures
Skylotec Rescue & Climbing Training from International organization (MIRA)
Successfully completed Hazard Recognition & Control
AutoCAD
Primavera P6 Version 17 ( From Primavera Institute)
QUALIFICATION
Bachelors of Science in Electrical Engineering from HITEC University Taxila (2008‐2012).
PERSONAL DOSSIER