Professional Documents
Culture Documents
Saep 1151
Saep 1151
SAEP-1151
Inspection Requirements for Contractor Procured Materials and Equipment
Document Responsibility: Project Quality Standards Committee
Contents
Summary of Changes.................................................................................................... 3
Scope ...................................................................................................................... 5
References .............................................................................................................. 5
Terminology ............................................................................................................ 6
Summary of Changes
Modification:
• Procurement Risk Evaluation
Guidelines changed as per RBI
WI
• Procurement Risk Mitigation
Guidelines
Addition & Addition:
Appendix Appendix
Modification • Project Management Evaluation
Guidelines
• Proponent Evaluation Guidelines
• 30%, 60% and 90% PO Focused
Assessment Checklist
Scope
This document, together with the purchase order and appropriate project
specifications define the minimum mandatory inspection requirements for
Contractor procured materials and equipment on projects.
Commentary Note:
As per the Procurement Manual 3.1.2, Short-form and Mid-form Contracts are also within the
scope of this procedure.
Any deviation from the requirements herein shall follow internal company
procedure SAEP-302.
References
All referenced specifications, standards, codes, drawings, and similar material
are considered part of this (Engineering Procedure, Engineering Standard,
Material System Specification) to the extent specified, applying the latest
version, unless otherwise stated.
Other References
Schedule Q Quality Requirements
Terminology
Acronyms
Quality Control (QC): The operational techniques and activities that are used
to fulfill requirements for quality.
Inspection and Test Plan (ITP): An ITP is a document based on the detailed
manufacturing, fabrication and, construction program and identifies each
process description. The ITP will set out related sequence of activities to be
inspected, examined, and tested.
Procurement Risk Register: A list of contractors planned and actual POs with
assigned level of risk (i.e., critical, high, moderate, or low).
Definitions
Review Point: Is the point at which a work activity cannot proceed without first
ensuring the review and approval of applicable documents or personnel
qualifications by a designated organization or authority.
This section is applicable to all Type-A and Type-B projects with the intent of
providing a systematic approach to manage and implement risk-based
inspection coverage in line with ISO 9001:2015.
5.1 The risk level for each PO is a product of the probability of failure, and the
associated impact of failure.
5.2 Contractor POs are evaluated by the Project Team according to weighed
factors, as tabulated in Table.1. The measure of probability and impact of
failures are estimated for each PO as shown in Appendix I, Appendix II, and
Appendix III.
Notes :
5.3 Contractor, within one month from developing the Material Takeoff (MTO) list,
shall develop the risk register and submit it to Company for review.
5.4 Contractor risk register shall include as a minimum the following: material
requisition/PO, 9COM, inspection level and awarded vendor/manufacturer.
5.5 SAIR shall coordinate with Project Management Team and Proponent to evaluate
and score the probability and impact of failures for each PO, noting that scoring
mechanisms outlined under Appendix II and Appendix III are general guidelines
for Project Management and Proponent and can be modified accordingly to
determine the risk levels.
5.6 The final list shall be reviewed and concurred upon in writing by the Project
Quality Manager (PQM), with a copy sent to Quality Monitoring Unit Supervisor.
5.7 SAIR and/or PQM shall have the authority to change risk levels or mitigation
guidelines based on project stakeholder’s (PMT & Proponent) agreement, with
proper documented justification.
5.8 Critical and High-Risk POs shall be officially relayed to the Responsible
Inspection Office (RIO) upon the approval of a PO’s Inspection Assignment
Package (IAP). The risk level shall be indicated in the IAP, and noted in the
corresponding Inspection Lot by SAIR.
5.9 Contractor shall submit updated risk registries on monthly basis highlighting new
POs and/or purchase requisitions, POs progresses, and conducted PO Focused
Assessments. Monthly updates shall also consider risk assignments based on
technical alerts, major lessons learned, and deteriorating manufacturer
performances.
Commentary note:
In case of risk level change, PQM approval is required as per para. 5.7 above.
5.10 Contractor shall closely monitor and assess critical-and high-risk POs, to ensure
quality and minimize rework.
5.12 Contractor should notify Company of PO progress milestones at 30%, 60% and
90%, for Critical and High-Risk POs.
5.13 Risk mitigation guidelines shall be as outlined in Appendix IV, noting that PO
Focused Assessments by PMT, Proponent, and Technical SMEs are optional
and subject to availability and resources.
5.14 PO Focused Assessments shall follow, as a minimum, the formats outlined under
Appendix V, Appendix VI and Appendix VII.
6.1 Purchase requisition originators shall identify the applicable fabrication and
1inspection requirements stated in approved requisition shall be reflected in
purchase orders.
6.2 Purchase requisition originators may also modify the content of a coded SA-175
form for certain purchase orders provided the following procedure is followed:
6.3 After PO award, contractor shall submit sub-vendor list for Company review
and approval. It shall include as a minimum the following: material description,
specification, 9COM, approved sub-vendor (Name and ID) and inspection level.
7.1 The vendor and/or sub-vendors shall prepare detailed ITP’s for all assigned
equipment and materials in accordance with all relevant Saudi Aramco
inspection forms (SA-175 forms), Schedule Q, and purchase orders.
7.2.1 Detailed inspection activities and the required tests which include, as
minimum, inspection hold, witness, review points, inspection frequency
as per applicable 175 form and assigned inspection level.
7.2.3 Clearly defined roles and responsibilities for each inspection activity.
7.3 Sampling plan availability does not relieve the vendor of the responsibility to
ensure compliance with Company requirements.
7.4 SAIR reserves the right to increase inspection activities and sampling plan criteria
in coordination with Company Subject Matter Expert (SME) based on the
criticality of the purchase orders and past performance of selected
manufacturers.
7.5 As part of IAP submittal, Contractor shall provide review and approval status of
vendor and/or sub-vendor Non Material Requirements (NMR-601 documents),
quality control procedures such as welding, NDT, heat treatment, and the
required related procedures for that specific purchase order, as required by
Company standards and/or project specifications.
7.6 Contractor shall ensure the comments raised and agreed during the PIM on ITP
are properly incorporated through new form revision. Contractor shall ensure
distribution of revised ITP to all the relevant parties.
8.1 Some inspectable materials do not have coded SA-175 forms linked to them.
When these materials are procured, the purchase requisition originators shall
specify source inspection requirements for materials, by filling in the blank special
SA-175 form.
8.2 The contractor is responsible to develop and maintain full document control of
issued special SA-175 forms during a project in term of numbering and
identification, approval, revisions and records preservation.
8.3 The PQM and/or SAIR are responsible to review contractor generated special
SA-175 forms, as applicable. special SA-175 forms shall be subject to SCC
approval.
8.4 For packaged, skid mounted equipment or any main equipment, separate SA-
175 form shall be applied on each inspectable sub-component in accordance
with main SAMSS and SA-175 form, in addition to the SA-175 form for the overall
equipment.
9.2 The following system of coding the level of planned inspections shall be used to
define the inspection requirements:
Level 0: Documentation requirements only as specified in applicable
SA-175 form; no vendor inspection required.
Level 1: Only final inspection including release for shipment is required
prior to shipping.
Level 2: Includes pre-inspection meetings, one or more unspecified “in
progress” surveillance visit/s, all witness and hold points, final
inspection, and release for shipment.
Level 3: Includes pre-inspection meetings, one or more unspecified “in
progress” surveillance visits, all witness and hold points, final
inspection, and release for shipment. Inspections shall be on
a regular basis (daily, weekly or bi-weekly).
Level 4: Resident inspector continually monitoring the work.
All inspectable material covered under the inspection levels as defined above,
shall be procured from Saudi Aramco approved manufacturers.
9.3 Minimum inspection levels by project contractor for procured materials and
equipment shall be as per the Company provided list of inspection levels
extracted from SAP per 9COM at the project cut-off date.
9.4 VID provides quality monitoring and inspection support for projects in
accordance with approved ITP. SAIR will determine which purchase orders and
vendor activities to be monitored based on guidelines in Appendix IV.
9.5 Inspection levels might be elevated or lowered by SAIR on case by case basis,
based on criticality of procured materials, performance of selected manufacturer
and qualification of contractor’s inspector, etc.
9.6 When vendor does not meet the specified performance requirements in the
purchase order, or Company has placed the vendor on-hold after the Company
has issued a “No Objection” letter to contractor, contractor shall increase the
inspection level to the next highest level for the purchase order without additional
cost to Company, subject to Company approval.
9.7 In case of materials/equipment not listed in the list as described in paragraph 9.3,
the SAIR and/or PQM will determine the appropriate inspection level. Inspction
level for non-listed materials/ equipment shall be approved by SCC.
9.8 Contractor shall not release material with punch list items unless approval is
obtained from Company representative.
9.9 SAIR is responsible to determine the criticality of material and severity of punch
list items during the release, and escalate to appropriate Quality Notification as
applicable.
10.1 SAIR and/or PQM is responsible to verify the assignment of appropriate level of
inspection. They are also responsible to determine the level of inspection for non-
listed materials/ equipment. Inspction level for non-listed materials/ equipment
shall be approved by SCC.
Document History
18 November 2012 New Saudi Aramco Engineering Procedure.
30 January 2017 Editorial revision to transfer document responsibility from Inspection Engineering
to Project Quality Standards Committee and other changes.
1 November 2017 Major revision for two main reasons; (1) to update the listed IR Codes and
associated equipment descriptions to reflect the current selection of inspectable
materials, and
(2) to make inspection levels more dynamic by obtaining inspection levels per the
project cut-off date from SAP. This revision will therefore no longer reflect
inspection levels.
12 January 2020 Major revision to reflect risk-based inspection requirements and other changes.
Appendix I
Criteria
Score Failure Preservation and
Manufacturing Complexity Vendor Performance MSAERs Availability
Frequency Handling
No Previous
0 N/A N/A N/A N/A
EDR or NCR
Normal preservation
1 2 EDR/NCR Final inspection RVL with VQI ≥ 85% and handling (e.g. only
or less MSAER and SA-175 box packing)
Forms available
Normal preservation
In-Process inspection – No RVL with VQI 85-
2 3 EDR/NCR and handling with
special processes review 75%
shade requirements
(Score 2 without PIM and
RVL with VQI 75- Controlled
3 4 EDR/NCR 3 with PIM) MSAER available and
70% environment
Special-175 Form
RVL with VQI 70-65% required Special preservation
4 5 EDR/NCR First time purchased –Non-RVL (e.g. N2, Oil, VCA)
engineered equipment – RVL with VQI ≤ 65%
Licensed equipment – – RVL on Hold –
MSAER not available
6 EDR/NCR Special preservation
5 Special design conditions and Special-175 Form
or more Newly Approved and handling
and metallurgy required
Vendor
Appendix II
Criteria
Score
Cost Schedule (Option A) Schedule (Option B) Schedule (Option C)
Acceptable delay ≥6
1 PO value ≤$10MM Float ≥6 months Bulk material
months
5 PO value ≥$50MM Project critical path Project critical path Project critical path
Appendix III
Criteria
Score
Operation Quality (Option A) Operation Quality (Option B)
0 N/A N/A
5 Operation disruption with production impact Fatal hazard – loss of life or assets
Appendix IV
Critical ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
High ✓ ✓ ✓ ✓ ✓
Medium ✓*
Low
*Applicable to Inspection Level 2 material and above, unless otherwise directed by SAIR.
**PO Focused Assessments by PMT, Proponent, and Technical SMEs are optional and subject to availability and resources.