Professional Documents
Culture Documents
J910-DH02-P10ZEN-040001 Field ITP For Earth Work For Ash Handling Facilities - Rev.1 (AFC)
J910-DH02-P10ZEN-040001 Field ITP For Earth Work For Ash Handling Facilities - Rev.1 (AFC)
APPROVED
by OE
01-Mar-22
ACKNOWLEDGED
AND
SIGNED
Owner’s Engineer Date: Mar 01, 2022
Contractor b
Approved
by IRT on Mar 01, 2022
Sub-Supplier
Project
ASH HANDLING FACILITIES FOR
JAWA 9 & 10 COAL FIRED STEAM POWER PLANT
Document Title
Document No.
J910-DH02-P10ZEN-040001
Ash Handling Facilities For Jawa 9&10 Coal Fired Steam Power Plant_ITP Review Comment Sheet
From : DHII Mr. Jongpyo.kim
To : OE Mr. Iskandar Jamil Comment Sheet Document No : J910-DH02-P10ZEN-040001_CS
cc : OE Mr. Yusri Yaakob
Dwg Title : Field ITP for Earth Work for Ash Handling Facility
Dwg No : J910-DH02-P10ZEN-040001
Purpose : FC
Review Category
A = Approved
B = Approved with comments, forward final document
C = Not Approved
I = Accepted for reference (For information only)
No. Rev. Sheet/ Page/ Sect. O/E Comments Consortium Response Status
Please rename this ITP as "Field ITP for Earth Work for Ash Handling
1 A 1 Repaired Closed
Facilities".
Preparation work
This content should be mentioned in Method Statements and it is not
2 A 7/1 Closed
to verify area/land not dispute condition, no any clash other found applicable to ITP.
facilities, no negative affects to another work/subject.
9 0 2 EPC should add CRS from the previous revision. Repaired Closed
RECORD OF REVISION
Rev. Date Page Affected Description of Revision
Rev.1 2 of 13
FIELD ITP FOR EARTH WORKS FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040001
CONTENTS
1. INTRODUCTION .......................................................................................................... 4
1.1 Inspection and Test Plan (ITP) ............................................................................................................ 4
1.2 Acceptance Conditions ......................................................................................................................... 4
1.3 Request for Inspection and Test (RFI) .............................................................................................. 5
1.4 Documentation ........................................................................................................................................ 5
2. FLOW CHART OF THE INSPECTION..................................................................... 5
2.1 General Inspection Flow Chart ........................................................................................................... 5
2.2 Flow Chart for Field Inspection of Earth Works ........................................................................... 6
3. DETAIL ITP FOR EARTH WORK ............................................................................ 7
4. APPENDICES............................................................................................................... 11
APPENDIX 1......................................................................................................................................... 11
Form No. ITP-C-0001-09 INSPECTION FOR SURVEYING RECORD REPORT ....... 11
APPENDIX 2......................................................................................................................................... 12
Form No. ITP-C-0001-10 INSPECTION FOR EXCAVATION RECORD REPORT ..... 12
APPENDIX 3......................................................................................................................................... 13
Form No. ITP-C-0001-11 INSPECTION FOR BACKFILL RECORD REPORT ........... 13
Rev.1 3 of 13
FIELD ITP FOR EARTH WORKS FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040001
1. INTRODUCTION
1.1 Inspection and Test Plan (ITP)
a. Scope
The Inspection and Test Plan (ITP) is an engineering document, which described the inspection
and tests to be performed. The inspection is performed in accordance with Owner specification
requirements and specified codes & standards.
b. Composition
This ITP is composed as belows:
- Cover Sheet with project name, Owner name, application and related personnel's name.
- Introduction with general notes
- ITP with Inspection and test activities
a. The equipments, materials are inspected and tested at Site in confirmation of the conditions
specified in the ITP. Each operation refers to the whole or part of a standard, a technical
specification and a regulation.
b. Detailed Legend
Detailed Legend for Inspection activity points shall be designated on the ITP by the related
parties as follows;
P : Performance Point. Responsible to perform or execute the actual works.
R : Record/review Point. Responsible for Generating record/review.
W : Witness Point. Consortium shall send a notification to the Owner prior to perform
the related test or inspection. If the Owner fails to be present, the test or inspection
may be carried out by Consortium without witness of the Owner.
SW : Spot Witness Point. The spot witness point that is handled like as a sample witness
point, it will be witnessed by related parties only for several activities/ item to be
inspected. But, if inadequate working procedures are detected by related parties,
this point will be treated as witness points after the proper action.
S : Surveillance Point. Random attendance at site, no signature required on the
Inspection Request ( IR ) or its accompanying documentation.
H : Hold Point. Consortium shall also send a notification to the Owner prior to perform
the related test or inspection. If the Owner fails to be present, any construction
activities shall not be proceeded by Consortium without attendence or any written
approval of the Owner.
Rev.1 4 of 13
FIELD ITP FOR EARTH WORKS FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040001
1.3 Request for Inspection and Test (RFI)
a. RFI will be issued by Consortium through Aconex at least three (3) days in advance for
site/field inspection and 7 days for outside inspection. For overseas inspection, RFI shall be
issued 35 days in advance prior to the inspection and test in accordance with the Contract.
b. RFI is required for all action points excluding Surveillance Point.
c. RFI will contain as a minimum of the following details:
- ITP No./Drawing No./Equiment name/System Name
- Inspection tem/activities on the ITP to be inspected
- Inspection date and time
- Unit No./Area/Building/Location/Elevation
- Any comments to be considered
1.4 Documentation
a. The results of inspections and tests shall be documented in writing and signed by the related
parties as a token of approval
b. Signed documents shall be controlled as a QA records in accordance with the related procedure.
c. Photos related to the work. Minimum captured: before test/inspect, on progress, after.
SHOP / MANUFACTURER
Inspection
Open box Issue HOLD activity as per
Inspection to Tag & NCR approved ITP
check package
inside
SITE
Rev.1 5 of 13
FIELD ITP FOR EARTH WORKS FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040001
2.2 Flow Chart for Field Inspection of Earth Works
Rev.1 6 of 13
FIELD ITP FOR EARTH WORKS FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040001
Rev.1 7 of 13
FIELD ITP FOR EARTH WORKS FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040001
3 Excavation
Contract Book 4.
Chapter 4. Attachment As per approved
3.2.Line & Grade
of Design Specifications
ITP-C-0001-10
drawings
P W SW -
2.Technical
Comply with contract
Specifications for Civil
specification, Approved
Works
drawings
2.1 Earth Works,
3.3. Soil condition at the bottom of AFC Drawings, Before pouring
excavation
Lab Report
Lean concrete
P W SW -
Approved Method
Statement
Before pouring
3.4.Dewatering (if water rises) ITP-C-0001-10
Lean concrete
P W SW -
Before proceeding
3.5. Final Survey ITP-C-0001-09
rebar works
P W SW -
Rev.1 8 of 13
FIELD ITP FOR EARTH WORKS FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040001
4 Backfilling
ITP-C-0001-11 or
e) Moisture Content Every 1000 Cum P W SW -
Contract Book 4. Lab. Report
Chapter 4. Attachment
of Design
4.2. Layer Thickness Specifications ITP-C-0001-11 Every 1000 Cum P W SW -
2.Technical
Comply with contract
Specifications for Civil
specification, Approved
Works
drawings and ASTM
2.1 Earth Works,
D1557 & D2049
Field Density Test
4.3. Compaction Test Procedure and ASTM ITP-C-0001-11 or
a) Field Density & Moistire D1557 & D2049 Every 1000 Cum R W W -
Lab. Report
Test
Rev.1 9 of 13
FIELD ITP FOR EARTH WORKS FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040001
Contract Book 4.
5.1. Check completeness of Chapter 4. Attachment
Works of Design P H H
Specifications
2.Technical Punch List
5.3. Punch List Registration Comply with contract s 100 % (after
& Clearance Specifications for Civil pecification, completion of P H H
Works Approved drawings works)
2.1 Earth Works,
5.4. Issuance of Mechanical AFC Drawings,
Completion Certificate Approved Method Stat
(MCC) ement MCC P H H
Site Work
All Inspection and Test Reviewed & signed-off
6 Final Review of Documentation
Records
Conformance File
by all parties
100 % (All records) R R R -
(SWCF)
Note:
1) Related Method Statement will be attached along with the RFI
2) Related drawing will be attached along with the RFI
Rev.1 10 of 13
FIELD ITP FOR EARTH WORKS FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040001
APPENDICES
APPENDIX 1
Form No. ITP-C-0001-09 INSPECTION FOR SURVEYING RECORD REPORT
As per
approved
drawings
B. Benchmark used
As per
approved
drawings
C. Surveying data
As per
approved
drawings
Note :
Rev.1 11 of 13
FIELD ITP FOR EARTH WORKS FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040001
APPENDIX 2
Form No. ITP-C-0001-10 INSPECTION FOR EXCAVATION RECORD REPORT
Rev.1 12 of 13
FIELD ITP FOR EARTH WORKS FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040001
APPENDIX 3
Form No. ITP-C-0001-11 INSPECTION FOR BACKFILL RECORD REPORT
Note :
Rev.1 13 of 13