ASH HANDLING FACILITIES FOR
JAWA 9 & 10 COAL FIRED STEAM POWER PLANT
Document Title
FIELD ITP FOR BUND WALL WORK FOR ASH HANDLING FACILITIES
Document Type
□ Basic Engineering Document □ Detail Engineering Document □ Vendor Document ■ Other
Document No.
J910-DH02-P10ZEN-040007
FIELD ITP FOR BUND WALL WORK FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040007
RECORD OF REVISION
Rev. Date Page Affected Description of Revision
Rev.A 2 of 18
FIELD ITP FOR BUND WALL WORK FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040007
CONTENTS
1. INTRODUCTION.............................................................................................................................4
1.1 Inspection and Test Plan (ITP) ..................................................................................................................... 4
1.2 Acceptance Conditions ................................................................................................................................. 4
1.3 Request for Inspection and Test (RFI) .......................................................................................................... 5
1.4 Documentation ............................................................................................................................................. 5
4. APPENDICES ..................................................................................................................................12
APPENDIX 1 ...................................................................................................................................................... 12
Form No. ITP-M-0001-01 MATERIAL RECEIVING INSPECTION RECORD ............................................... 12
APPENDIX 2 ...................................................................................................................................................... 13
Form No. ITP-M-0001-02 INSPECTION FOR SURVEYING RECORD REPORT .......................................... 13
APPENDIX 3 ...................................................................................................................................................... 14
Form No. ITP-M-0001-03 INSPECTION FOR EXCAVATION RECORD REPORT ........................................ 14
APPENDIX 4 ...................................................................................................................................................... 15
Form No. ITP-M-0001-04 INSPECTION FOR BACKFILL RECORD REPORT ............................................. 15
APPENDIX 5 ...................................................................................................................................................... 16
Form No. ITP-M-0001-05 INSPECTION FOR CONCRETE CHCEKLIST ...................................................... 16
APPENDIX 6 ...................................................................................................................................................... 17
Form No. ITP-M-0001-06 INSPECTION FOR CONCRETE TEST REPORT .................................................. 17
APPENDIX 7 ...................................................................................................................................................... 18
Form No. ITP-M-0001-07 INSPECTION FOR POST-POURING REPORT ..................................................... 18
Rev.A 3 of 18
FIELD ITP FOR BUND WALL WORK FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040007
1. INTRODUCTION
1.1 Inspection and Test Plan (ITP)
a. Scope
The Inspection and Test Plan (ITP) is an engineering document, which described the inspection
and tests to be performed. The inspection is performed in accordance with Owner specification
requirements and specified codes & standards.
b. Composition
This ITP is composed as belows:
- Cover Sheet with project name, Owner name, application and related personnel's name.
- Introduction with general notes
- ITP with Inspection and test activities
a. The equipments, materials are inspected and tested at Site in confirmation of the conditions
specified in the ITP. Each operation refers to the whole or part of a standard, a technical
specification and a regulation.
b. Detailed Legend
Detailed Legend for Inspection activity points shall be designated on the ITP by the related
parties as follows;
P : Performance Point. Responsible to perform or execute the actual works.
R : Record/review Point. Responsible for Generating record/review.
W : Witness Point. Consortium shall send a notification to the Owner prior to perform
the related test or inspection. If the Owner fails to be present, the test or inspection
may be carried out by Consortium without witness of the Owner.
SW : Spot Witness Point. The spot witness point that is handled like as a sample witness
point, it will be witnessed by related parties only for several activities/ item to be
inspected. But, if inadequate working procedures are detected by related parties,
this point will be treated as witness points after the proper action.
S : Surveillance Point. Random attendance at site, no signature required on the
Inspection Request ( IR ) or its accompanying documentation.
H : Hold Point. Consortium shall also send a notification to the Owner prior to perform
the related test or inspection. If the Owner fails to be present, any construction
activities shall not be proceeded by Consortium without attendence or any written
approval of the Owner.
Rev.A 4 of 18
FIELD ITP FOR BUND WALL WORK FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040007
a. RFI will be issued by Consortium through Aconex at least three (3) days in advance for
site/field inspection and 7 days for outside inspection. For overseas inspection, RFI shall be
issued 35 days in advance prior to the inspection and test in accordance with the Contract.
b. RFI is required for all action points excluding Surveillance Point.
c. RFI will contain as a minimum of the following details:
- ITP No./Drawing No./Equiment name/System Name
- Inspection tem/activities on the ITP to be inspected
- Inspection date and time
- Unit No./Area/Building/Location/Elevation
- Any comments to be considered
1.4 Documentation
a. The results of inspections and tests shall be documented in writing and signed by the related
parties as a token of approval
b. Signed documents shall be controlled as a QA records in accordance with the related procedure.
c. Photos related to the work. Minimum captured: before test/inspect, on progress, after.
Rev.A 5 of 18
FIELD ITP FOR BUND WALL WORK FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040007
SHOP / MANUFACTURER
Inspection
Open box Issue HOLD activity as per
Inspection to Tag & NCR approved ITP
check package
inside
SITE
Rev.A 6 of 18
FIELD ITP FOR BUND WALL WORK FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040007
1.2. Method Statement & Contract Book 4, Method Statement Comply with Approved
As per Report P R R -
Risk Assessment Method Statement &Risk Assessment Method Statement.
Equipment &
Equipment & Machinery Comply with Approved
1.3. Equipment & Machineries Machineries As per Report P R R -
certificates inspection records
inspection records
Method Statement, Comply with Approved
calibration
1.4. Calibration Certificate Instrument specification, Valid calibration As per Report P R R -
certificates
Calibration Procedure certificates
2 Excavation
Before proceeding
2.5 Final Survey ITP-C-0001-09 P W SW -
rebar works
Rev.A 7 of 18
FIELD ITP FOR BUND WALL WORK FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040007
Applicable DWG for each Test result meets Once per design
3.1 Design mix Trial Mix Report P W SW -
works & specification targeted grade mix
3.2 Manufactured materials Applicable DWG for each One approval per
Material Approval Approve by IRT/OE P R R -
(Dowel bar, etc.) works & specification material per brand
Rev.A 8 of 18
FIELD ITP FOR BUND WALL WORK FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040007
5.3 Temperature check ACI 301M – 10 ITP-M-0001-06 Less than 32°C Every 50 M3 P W SW -
6.2 Visual inspection of concrete As per clause 5.3.3 and After formwork
ACI 301M – 10 ITP-M-0001-07 P W SW -
surface 5.3.4 of ACI 301M – 10 removal
7 Backfilling
Rev.A 9 of 18
FIELD ITP FOR BUND WALL WORK FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040007
ITP-M-0001-04 or
e) Moisture Content Contract Book 4. Every 1000 Cum P W SW -
Lab. Report
Chapter 4. Attachment
of Design Specifications
2.Technical Comply with contract
7.2. Layer Thickness Specifications for Civil ITP-M-0001-04 specification, Approved Every 1000 Cum P W SW -
Works drawings and ASTM
2.1 Earth Works, D1557 & D2049
Field Density Test
Procedure and ASTM
7.3. Compaction Test ITP-M-0001-04 or
D1557 & D2049 Every 1000 Cum R W W -
Field Density & Moistire Test Lab. Report
- AFC Drawings
- Completion of works
8.2 Punch List Registration & - Approved MS 100% (after work
Punchlist Satisfactory clearance P H H -
Clearance - Inspection Records completion)
of punch list.
Internal Punch List
Rev.A 10 of 18
FIELD ITP FOR BUND WALL WORK FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040007
Note:
Legend Definition: P Perform R Record Review
H Hold Point Sub-Con Subcontractor (HJU)
W Witness EPC Contractor (DHII)
SW Spot Witness IRT/OE Owner (Indo Raya Tenaga) / Owner Engineer
S Surveillance Auth. Authorized third party for the specific item as applicable
Rev.A 11 of 18
FIELD ITP FOR BUND WALL WORK FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040007
4. APPENDICES
APPENDIX 1
Form No. ITP-M-0001-01 MATERIAL RECEIVING INSPECTION RECORD
Vendor/Sup
: _____________________ RFI No. : _________________
p
Unit/Area : _____________________ Date : _________________
Ref.
Project : Ash Handling Facilities for Jawa 9 & 10 CFSPP : _________________
Dwg.Doc
Material Description
Source of materials
Quantity
2 Type
3 Dimension
4 Color
6 Others, if any
The material stated above has been inspected and Approved / Not Approved to take up the works
Note:
Signature
Name
Sign Date
Job Title
Rev.A 12 of 18
FIELD ITP FOR BUND WALL WORK FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040007
APPENDIX 2
Form No. ITP-M-0001-02 INSPECTION FOR SURVEYING RECORD REPORT
INSPECTION FOR SURVEYING RECORD
REPORT (FOR BUND WALL)
As per
approved
drawings
B. Benchmark used
As per
approved
drawings
C. Surveying data
As per
approved
drawings
Note:
Signature
Name
Sign Date
Job Title
Rev.A 13 of 18
FIELD ITP FOR BUND WALL WORK FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040007
APPENDIX 3
Form No. ITP-M-0001-03 INSPECTION FOR EXCAVATION RECORD REPORT
Signature
Name
Sign Date
Job Title
Rev.A 14 of 18
FIELD ITP FOR BUND WALL WORK FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040007
APPENDIX 4
Form No. ITP-M-0001-04 INSPECTION FOR BACKFILL RECORD REPORT
Note:
Signature
Name
Sign Date
Job Title
Rev.A 15 of 18
FIELD ITP FOR BUND WALL WORK FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040007
APPENDIX 5
Form No. ITP-M-0001-05 INSPECTION FOR PRECATE CONCRETE PANEL CHCEKLIST
INSPECTION FOR PRECAST CONCRETE PANEL
CHCEKLIST
Project Title Sub-Contractor
Job No RFI No.
Project Owner Name Date
Owner Engineer Name
Page of
EPC Company Name
Equipment / Location : Revision :
Drawing no : Sheet :
RESULT
NO DESCRIPTION REMARK
Accept Reject
Dimension Alignment
Form Oil Coating
1 Formwork
Stability
Rebar
Cleaning Pouring Place
Slump Test
Stability
2 Concrete Availability Concrete Vibrators (Qty)
Removal Laitance
Appearance of Surface
Curing
Size Type Number
Stability
3 Embedded
Protection
Material
Note:
Signature
Name
Sign Date
Job Title
Rev.A 16 of 18
FIELD ITP FOR BUND WALL WORK FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040007
APPENDIX 6
Form No. ITP-M-0001-06 INSPECTION FOR CONCRETE TEST REPORT
Note:
Rev.A 17 of 18
FIELD ITP FOR BUND WALL WORK FOR ASH HANDLING FACILITIES
J910-DH02-P10ZEN-040007
APPENDIX 7
Form No. ITP-M-0001-07 INSPECTION FOR POST-POURING REPORT
Note:
Signature
Name
Sign Date
Job Title