Professional Documents
Culture Documents
PMP 1
PMP 1
CHAPTER ONE
INTRODUCTION
SOURCE: PMBOK GUIDE
Overview
PMBOK Guide
What is a Project ?
Project Management
Tailoring Concept
Sample Questions
Overview
4
Project Management is NOT new, it has been in use for many years
By the mid -20th century, PMs began to seek recognition for project
management as a profession.
Temporary
Has a definite beginning and end , not an ongoing effort
The end is reached when the project objectives have been achieved or the
project is terminated
Unique
Projects produces deliverables to fulfill objectives
➢ Resource management
➢ Communications management
➢ Risk management
➢ Procurement management
➢ Stakeholder management
PM Data & Information
20
WP WP WP
Data Information Reports
• Execution • Controlling • Overall Control
• Raw observations • Performance data, • Physical or
• Raw collected, analyzed electronic
measurements (CPI / SPI ...) representation of
• Quality • Deliverable status WPI
measurements (completed, • Status reports
• Start/ finish dates verified, validated) • Dashboards
• Actual costs/ • Change status ( • Updates
durations accepted, rejected) • Recommendations
• Recorded in PMIS • Forecasts
PM Data & Information
21
Tailoring Concept
22
Specific methodology are outside the scope of the guide, it may be;
Developed by organization , purchased from vendors
1. Business case
3. Project charter
A project is:
Answer: D
Q&A
27
Answer: B
Q&A
28
Answer: D
Q&A
29
All of the following are questions that the key stakeholders and project
managers should answer to develop the project success measures
EXCEPT:
Answer: C
Q&A
30
A program is a:
Answer: B
Q&A
31
All of the following are true about projects and operations EXCEPT:
A. Operations are ongoing endeavors that produce repetitive outputs, with
resources assigned to do basically the same set of tasks according to the
standards of a product life cycle, whereas projects are temporary endeavors.
B. Projects require project management activities and skill sets, whereas
operations require business operations management activities and skill sets.
C. Projects can intersect with operations at various points during the product life
cycle. At each point, deliverables and knowledge are transferred between the
project and operations for implementation of the delivered work.
D. Because of their temporary nature, projects cannot help achieve an
organization’s long-term goals. Therefore, strategic activities in the
organization can be generally addressed within the organization's normal
operations.
Answer: D
Q&A
32
B. Process management.
C. Program management.
D. Portfolio management.
Answer: D
Q&A
33
Answer: C
Q&A
34
Answer: B
Q&A
35
All of the following are true about project phases and the project life cycle
EXCEPT:
A. Stakeholder influences, risk, and uncertainty are greatest at the start of the
project. These factors decrease over the life of the project.
B. The ability to influence the final characteristics of the project's product, without
significantly impacting cost, is highest at the start of the project and
decreases as the project progresses toward completion.
D. Cost and staffing levels are generally steady throughout the project life cycle .
Answer: D
Q&A
36
All of the following statements about the project life cycle and the product
life cycle are true EXCEPT:
A. In the project predictive life cycle, the project scope ,time and cost are
determined as early in the project life cycle as practically possible.
B. In the project iterative and incremental life cycles, project phases intentionally
repeat one or more project activities as the project team’s understanding of
the product increases.
C. The product life cycle is the series of phases that represent the evolution of a
product, from concept through delivery, growth, maturity, and to retirement
D. The product life cycle is contained within the project life cycle.
Answer: D
Q&A
37
You are managing a project in which you intend to respond to high levels
of change and ongoing stakeholder involvement. The most suitable
project life cycle for your project is the:
A. Predictive life cycle.
Answer: B
Q&A
38
Answer: B
Q&A
39
D. Are discrete, repetitive events that occur generally at the same level of
intensity throughout each phase of the project.
Answer: A
Q&A
40
C. Processes are linked by the outputs that are produced ,the output of one
process generally becomes an input to another process or a deliverable.
Answer: C
Q&A
41
Answer: C
Q&A
42
B. A document that lists the objectives and reasons for project initiation.
D. An important document that may result in a go/no- go decision for the project.
Answer: C
Q&A
43
The key elements of the benefits management plan are all of the following
EXCEPT:
B. Benefits owner.
C. Assumptions.
D. Strategic alignment .
Answer: A
Q&A
44
Answer: B
Q&A
45
Answer: A
Questions ?
46