Date: CW 35
2021_08_Mo 30 to _09 Sa 04
STATUS REPORT
Author: Soumya Mukherjee

Project : CIMASSO 2 Coustomer : CIM METAL GROUP

Project No.: 21.592 Place : Burkina: Bobo-Dioulasso

Visitor-
Accident Phone DATE-Time TOPIC
Meeting Number

Mr. Marc File 30th August 2021 1) Cimasso presented the current project team
(Intercem) Time -: 10:00 A.M Intercem presented the latest process & plant design
Mr. Olaf for cimasso I & cimasso II.
Michelswirth
(Intercem) 2) Besdie the truck unloading station, the existing raw
Mr. Roland material storage building must be protected. Intercem
Klinke presented the soring solutions to Cimasso & Ayoki.
(Intercem)
Ms. Nadege 3) Intercem confirmed that the same CCR building will
sanou be used for Cimasso I & Cimasso II. Additional MCC
(Intercem) room for the grinding unit will be intregated design.
Mr. Soumya
Mukherjee 4) Ayoki has to submit their project time schedule &
(Intercem) Organisation chart.
Mr. Rahim
Kanazoe 5) Intercem advise to Cimasso & ayoki, during the
(Cimasso) excavation of hopper station all train operation must
Mr. Sere be exaimined & Ayoki need to submit their planning to
Ibrahim complete the hopper station excavation work.
(Cimasso)
Mr. Roland 6) Before starting the excavation of cement silo, Ayoki
ouangraoua must be submitt their method statement for
(Cimasso) excavation, backfilling & compaction control.
Mr. Vinod
(Ayoki) 7) The health, safety & traffic route planning &
Mr. Sreedip protocol must be submitted by Ayoki & approved by
(Ayoki) Cimasso, 3rd party & Intercem.

8) Cimasso approved to provide necessary storage


place for all equipment and installation material to
Intercem & Ayoki. Sensitive equipment must be
stored inside the warehouse.

9) Intercem informed Cimasso that existing cable


channels, and others that are an obstacle for Cimasso
II execution must be re-routed in coordination with
Intercem.
Page 2 of 2

10) Date of readiness of batching plant & slip ring on


site for the Construction of cement silo to be
confirmed by Ayoki.

INTERCEM representative at site:


Name Local phone number Email Position
Mr. Marc file m.file@intercem.ch CEO

Mr. Olaf Michelswirth O.Michelswirth@inter GM


cem.de

Mr. Roland Klinke R.Klinke@intercem.de Project director

Mr. Soumya Mukherjee +226 5584 2812 s.mukherjee@inter Civil supervisor


cem.de

Ms. Nadege Sanou +226 7666 2551 n.sanou@intercem.de Civil supervisor

Performed Work & Preview 1) The topo graphic survey work is under progress.

1) No batching plant fixed yet for the supply of concrete.

2) Excavator and dumper for the start to excavation work, till now did not
fix yet from Ayoki. But ayoki submit their excavator & dumper allocation
planning.

Problems & cause of delays 3) Cimasso till now not finalize the place of install the batching plant.

4) Cimasso till now not finalize their 3rd party control for the project.

5) Ayoki is unable to arrange the cube mold to start the concrete mix
design

Planning of upcoming week Continue the concrete mix design & Topo graphic surveying.