CENTRE LINE METHOD (CENTRE LINE=7X3.

14=2205M)
ITEM NO. DESCRIPTION NO. UNIT L (m) B (m) H/D (m) QUANTITY REMARKS
1 RCC IN FOUNDATION-M25
a RCC 6 cu m 1 1 0.5 3
2 RCC IN COLUMN-M40
a ABOVE PLINTH 6 cu m 0.3 0.3 3 0.27
b BELOW PLINTH 6 cu m 0.3 0.3 0.45 0.243
TOTAL 0.513

3 RCC IN BEAM-M40
a RCC 1 cu m 22.05 0.3 0.45 2.97675
b OVERLAPS 2 cu m 0.3 0.15 0.45 -0.0405
TOTAL 2.93625

4 RCC IN PLINTH BEAM-M40

RCC 1 cum 22.05 0.3 0.3 1.9845


OVERLAPS 2 cum 0.3 0.15 0.45 -0.0405
TOTAL 1.944

5 RCC IN SLAB-M30
a ABOVE PLINTH 2 cu m 2.8 2.85 0.15 2.394
b BELOW PLINTH 2 cu m 2.8 2.85 0.15 2.394
TOTAL 4.788

6 RCC IN LINTEL-M25
a WINDOW 2 cu m 0.2 2.85 0.2 0.228
b DOOR 2 cu m 0.2 1.5 0.2 0.12
TOTAL 0.348

7 SHUTTERING FOR FOUNDATION 24 sqm 1 0.5 NA 12

8 SHUTTERING FOR COLUMNS


a ABOVE PLINTH 24 sqm NA 0.3 3 21.6
b BELOW PLINTH 24 sqm NA 0.3 0.45 3.24
TOTAL 24.84

11 SHUTTERING FOR BEAM


a EXTERIOR SIDE 1 sqm 19.9 NA 0.45 8.955
b INNER SIDE 2 sqm 11.3 0.3 NA 6.78
c BOTTOM SIDE 1 sqm 18.7 NA 0.45 15.12

TOTAL 30.855

SHUTTERING FOR SLAB- ABOVE


12 PLINTH 2 sqm 2.8 2.85 NA 15.96
b BELOW PLINTH 2 sqm 2.8 2.85 NA 15.96
TOTAL 31.92

13 SHUTTERING FOR PLINTH BEAM


a EXTERIOR SIDE 1 sqm 19.9 NA 0.3 5.97
b INNER SIDE 2 sqm 11.3 0.15 NA 3.39
TOTAL 9.36

14 SHUTTERING FOR LINTEL BEAM


a WINDOW 6 sqm 0.2 1 NA 1.2
b DOOR 6 sqm 0.2 1.5 NA 1.8
TOTAL 3

15 STEEL REINFORCEMENT kg/m^3 RCC QUANTITY


a BELOW PLINTH LEVEL
STEEL REINFORCEMENT FOR
i FOUNDATION 150 3 450
STEEL REINFORCEMENT FOR PLINTH
ii BEAM 180 1.944 349.92
STEEL REINFORCEMENT FOR
iii COLUMNS 180 0.243 43.74

Iv STEEL REINFORCEMENT FOR SLAB 120 2.394 287.28


TOTAL 843.66
b ABOVE PLINTH LEVEL
STEEL REINFORCEMENT FOR
i COLUMNS 180 1.377 247.86

ii STEEL REINFORCEMENT FOR BEAM 180 2.93625 528.525

iii STEEL REINFORCEMENT FOR SLAB 120 2.394 287.28


STEEL REINFORCEMENT FOR LINTEL
iii BEAM 120 0.348 41.76
TOTAL 1105.425