Subcont Schedule Pouring Concrete ISBL (31 October 22 - 13 November 22)
Subcont Schedule Pouring Concrete ISBL (31 October 22 - 13 November 22)
Note :
Need Pump Car * "RED" Font : Confirmed
No Need Pump Car
31 1 2 3 4 5 6 7 8 9 10 11 12 13
Mon Tue Wed Thurs Fri Sat Sun Mon Tue Wed Thurs Fri Sat Sun
10.0 15.0 15.0 20.0 15.0 10.0 25.0 10.0
50.0 70.0 65.0 80.0 55.0 40.0 85.0 60.0 55.0 40.0 70.0 65.0
50.0 70.0 65.0 80.0 55.0 40.0 0.0 85.0 60.0 55.0 40.0 70.0 65.0 0.0
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0 20.0 0.0 25.0 0.0 30.0 0.0 0.0 25.0 0.0 20.0 0.0 30.0 0.0
OSBL AREA
f'c 14 MPa Type I
CIV-06 RECON SARANA UTAMA
f'c 28 MPa Type V 281
f'c 14 MPa 5 12 8 21 - - - - - - - - - -
Total Daily
f'c 28 MPa - - 836 - - - - 1,000 - 1,951 213 685 45 -
Remaining Ton 720 720 380 380 380 380 380 - 26 1,474 682 595 317 298 298
Note :
Need Pump Car * "RED" Font : Confirmed
No Need Pump Car
Reference
BRM B/P Kariangau
February
Subcont. Design Type of
PKG Subcon Name Strenght Cement 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Mon Tue Wed Thurs Fri Sat Sun Mon Tue Wed Thurs Fri Sat Sun
f'c 14 MPa 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total Daily
f'c 28 MPa 0 135 135 0 135 135 0 135 135 0 135 135 0 0
f'c 14 MPa 0 0
Total Weekly
f'c 28 MPa 540 540