Professional Documents
Culture Documents
8.fixed Network Division Weekly Meeting 13-09-2022-23 (Week 10)
8.fixed Network Division Weekly Meeting 13-09-2022-23 (Week 10)
I: Action Follow up
When t
Observations / Action
No. Agenda Presenter Action to be done. update
Presentation Owner
action
2.1
Provisioning,
O&M Amend FBB target as per the new plan. O&M
Survey and TT
RM &
Since the rainy season is over we should start compensation O&M
2.3 Secondary data O&M
collection work.
3 Support OPMO Project status Identify & select sites to replace concrete pole in to wooden
presented pole hence concrete pole price is increasing/exaggerated and
Week 10
250 MW uplink is not available due to cement cost increment. ENG/
RCM/
project status We have to complete all projects started in Addis before CTO
presented. competition start in Addis.
Handover early completed site to start service, rather than PRO
waiting until the entire projects completed, prepare a
checklist to handover in terms of site to hunt customer
subscription.
Delayed projects should get way out & finalized
Prepare project allowance proposal for PRO staffs by O&M
PRO
specifying start & end date of the projects. ENG
Supply any operational tools for operational teams &
contractors by training them.
Gode & kebridehar PIT work should completed by providing
steel & cement form from Ethiotelecom side.
Always make sure that PIT work is done before deploying
P.O. Box 1047 Addis Ababa Ethiopia
tel.: +251 (0) 115 5157 00
www.ethiotelecom.et
Weekly progress On projects & Tailored solution done by zone & regional PRO
ENG
report updated. team should followed & done by their own force.
O&M
Uplink to be done for federal houses should be supported by PRO
Sisay & inform to Tirfu team. ENG
Week 1
4 Fixed ENG ENG O&M
Hence ADSL is discouraging better to use and replace VDSL
to support ADSL customer. PRO
ENG
Before deploying NE to new area sells team should provide a O&M
preliminary survey.
5 Fixed PRO PRO
Rollout
6 RCM
Contract
Weekly performance Mega projects like Koisha, Chebera churchura & Gorgora is on PRO
report presented. final stage from government side , we have to finalize issue to be ENG
7 EC EC O&M Week 10
done from our side on time since launching of the project is very
close.
P.O. Box 1047 Addis Ababa Ethiopia
tel.: +251 (0) 115 5157 00
www.ethiotelecom.et
Wireless uplink is critical & give priority. network service sales campaign it need special
intervention & follow-up.
Cost saving is critical this time all of us should
be cost conscious & prepare breakdown plan,
analyze cost saving area and evaluate the
work done too.
Whenever we face a new construction in the
city for building(Apartments) we should
communicate the owner to reach out our
service .
2 Oumer Does business case prepare for the amended Since no change on total target no need of RCM/
P.O. Box 1047 Addis Ababa Ethiopia
tel.: +251 (0) 115 5157 00
www.ethiotelecom.et
3 Sintayehu
4 Mersea
Epherem/
5
Addisu
6 Daniel
7 Sisay
Department BSC plan till individual level should be
finalized until Sep/14/2022.
Update department BSC as per the given comment
8 Bayeta by SPM.
Since some department are complaining on some
KPI parameters if it is important we can discuss on
it at division level.
9 Aschenaki
10 Mequannent Region metro work is creating challenge there is Communicate with HR and resolve the issue to begin
P.O. Box 1047 Addis Ababa Ethiopia
tel.: +251 (0) 115 5157 00
www.ethiotelecom.et
Takele/ and cable deployment transport & NID team ENG, PRO with NID & transport teams. however the ALL
11
Abera should involve. work should be done and mange by PRO team to not
miss use it.
END