DETAILED ESTIMATE FOR CONSTRUCTION OF HUME PIPE CULVERT

NAME OF ROAD CHAINAGE VILLAGE GP- JP


DISTRICT - RATLAM RATES USED FROM SECURE SOFT UNDER MGNREGS
S.No. secure Description No. Length Width Height/ Qty. Unit Rate Amount labour rate Labour
sw itm Depth Component
no.
1 2 4 5 6 7 8 9 10 11 12 13 14
Excavation in trenches for foundations and for pipes, cables, etc. not
exceeding 1.5m in width and for shafts, cesspits and the like not exceeding
63.03.08.
1 10 sqm on plan including dressing of sides and ramming of bottoms, lift
1
upto 1.5m including getting out and stacking the excavated soil and
disposal of surplus excavated soil as directed within a lead of 20m
Disintegrated or soft rock (not requiring blasting)
face wall 2 6.30 1.5 1.3 24.57
pipe bed 1 5.44 1.8 0.1 0.9792
appron 2 3 1 0.2 1.20
26.75 Cum 317.76 8499.83 281.20 7521.88
Providing and laying in foundation, plinth and under floors cement concrete
63.04.13.
2 with 40mm nominal size graded stone aggregates (metal) i/c ramming in
3
layers and curing complete excluding cost of form work
(c) C.C. 1:4:8 (1cement, 4sand, 8metal)
face wall 2 6.30 1.50 0.100 1.89 Cum 2829.72 5348.17 412.54 779.70

Providing and laying in foundation, plinth and under floors cement concrete
63.04.1
3 with 40mm nominal size graded stone aggregates (metal) i/c ramming in
3.2
layers and curing complete excluding cost of form work
(b) C.C. 1:3:6 (1cement, 3sand, 6metal
face wall 2 6 0.9 3 32.40
below bed pipe 1 5.44 1.8 0.1 0.98
appron 2 3 1 0.2 1.20
34.58
deduction
pipe 2 1.13 0.7 1.58
33.00 Cum 3170.2 104603.3917 412.54 13612.10
Providing and laying in foundation, plinth and under floors cement concrete
63.04.1
4 with 40mm nominal size graded stone aggregates (metal) i/c ramming in
3.1
layers and curing complete excluding cost of form work
(a) C.C. 1:2:4 (1cement, 2sand, 4metal 2 0.4 0.4 0.6 0.19 Cum 3823.54 734.11968 412.54 79.21

1
S.No. secure Description No. Length Width Height/ Qty. Unit Rate Amount labour rate Labour
sw itm Depth Component
no.
1 2 4 5 6 7 8 9 10 11 12 13 14
63.20.3 Providing and laying reinforced cement concrete pipes N.P.3 for culverts
5
5.2 including pointing ends, and fixing collar with cement martar 1:2 complete.
(b) 1000 mm dia. 3 2.5 7.5 rm 3765.13 28238.475 138.96 1042.20
Centering and shuttering including strutting , propping etc. and removal of
6 63.4.41
form work for P.C.C. work in foundation, footing, bases for column
2 6.3 3 37.80
2 6.3 3.31 41.71
8 0.4 0.6 1.92
deduction for pipe -2 1.130976 -2.26
79.16 Sqm 161.09 12752.53649 32.31 2557.79

160176.52 25592.87

SUB ENGINEER ASSISTANT ENGINEER


RES RATLAM RES RATLAM