Professional Documents
Culture Documents
PMP Question
PMP Question
1.A manager and the head of engineering discuss a change to a major work
package. After the meeting, the manager contacts you and tells you to complete
the paperwork to make the change. This is an example of:
A-) Management attention to scope management.
B-) Management planning.
C-) A project expediter position.
D-) A change control system.
Answer is C. In this situation, project manager acts as the secretary of the project
and does the paper work. So this is an example of project expediter position
where project manager does not have any authority and power. Project manager
does only paper work.
2. During a team meeting, a team member asks about the measurements that will
be used on the project to judge performance. The team member feels that some
of the measures related to activities assigned him are not valid measurements.
The project is BEST considered in what part of the project management process?
A-) Initiating
B-) Executing
C-) Monitoring & Controlling
D-) Closing
Answer is B. Executing. Questions states that team member feels some of the
measures on his activities are not valid. Therefore, he must be working during the
executing phase of the project where project deliverables are produced and
project members perform most of the work they should do.
3. Your company just won a major new project. It will begin in three months and
is valued at 2m USD. You are the project manager for an existing project. What is
the FIRST thing you should do once you hear of the new project?
A-) Ask management how the new project will use resources
B-) Resource level your project
C-) Crash your project
D-) Ask management how the new project will affect your project
Answer is D. Ask management how the new project will affect your project. Since
this is another project that your company is going to execute, you need to be sure
whether it will impact your project.
4. You are a new project manager who has never managed a project before. It
would be BEST in this situation to rely on _____ during planning in order to
improve your chance of success.
A-) Your intuition and training
B-) Stakeholder analysis
C-) Historical information
D-) Configuration management
Answer is C. Historical information. First thing to explore before starting a new
project is the historical information about similar projects in the organizational
process assets library of the organization.
5. During project executing, a team member comes to the project manager
because he is not sure of what work he needs to accomplish on the project.
Which of the following documents contain detailed descriptions of work
packages?
A-) WBS Dictionary
B-) Activity List
C-) Project scope statement
D-) Scope management plan
Answer is A. WBS Dictionary. Work packages in a Work Breakdown Structure
contain only nouns or a couple of words regarding a work or deliverable. Detailed
information on what needs to be done, responsible, prerequisites, successors,
due date etc. are included in the Work Breakdown Structure Dictionary.
6. During a meeting with some of the project stakeholders, the project manager is
asked to add work to the project scope. The project manager had access to
correspondence about the project before the project charter was signed and
remembers that the project sponsor specifically denied funding for the scope
mentioned by these stakeholders. The BEST thing for the project manager to do is
to:
A-) Let the sponsor know of the stakeholders’ request.
B-) Evaluate the impact of adding the scope.
C-) Tell the stakeholders the scope cannot be added.
D-) Add the work if there is time available in the project
schedule
Answer is C. Tell the stakeholders the scope cannot be added. After the scope of a
project is finalized and scope baseline is determined, it can be changed only with
the approved changed requests. If there is not an approved change request,
existing scope baseline must be valid and project team must work on to deliver
that scope only. In the scenario, scope is defined already but some stakeholders
ask to add new work to the scope. This cannot be done unless there is an
approved change request. Therefore, stakeholders must be informed that this
new work cannot be added.
7. Your project management plan results in a project schedule that is too long If
the project network diagram cannot change but you have extra personnel
resources, what is the BEST thing to do?
A-) Fast track the project.
B-) Level the resources.
C-) Crash the project.
D-) Monte Carlo analysis.
The answer is C, crash the project. Because, in first sentence, it is mentioned that
schedule is too long, therefore the aim is making a shorter schedule. And in the
second sentence it is mentioned that you have extra personnel resources. If you
have resources, you can put more resources in an activity to complete it in a
shorter time. And this is actually a description of crashing an activity or crashing
the project. If you look to the other options, fast tracking was performing
activities in parallel instead of series, therefore it is irrelevant. Leveling the
resources was for fixing the over-allocation of resources and distributing the tasks
to all your resources uniformly. And Monte Carlo analysis was another estimating
tool which is irrelevant choice as well. Therefore, here the best answer is C.
8. An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early
finish (EF) of day 9, and a late finish (LF) of day 19. The activity:
A-) Is on the critical path.
B-) Has a lag.
C-) Is progressing well.
D-) Is not on the critical path.
Answer is D. is not on the critical path. Because if you look to the early start and
late start values of the activity, you can find the float or the slack of activity’s time
by subtracting early start, 3 days, from the late start, 13 days. And it gives 10 days
of float for this activity. You will find the same result if you go through subtracting
the early finish, 9 days, from the late finish, 19 days. Since the float of activity or
the slack of the activity is greater than zero, it’s not on the critical path.
Remember the critical path activities was having zero float, therefore the answer
is D.
9. Early in the life of your project, you are having a discussion with the sponsor
about what estimating techniques should be used. You want a form of expert
judgment, but the sponsor argues for analogous estimating. It would be BEST to:
A-) Agree to analogous estimating, as it is a form of expert judgment
B-) Suggest life cycle costing
C-) Determine why the sponsor wants such an accurate estimate
D-) Try to convince the sponsor to allow expert judgment because it is typically
more accurate.
Answer is A. Agree to analogous estimating, as it is a form of expert judgment.
Since analogous estimating is a type of expert judgment you can accept it. This is a
tricky question.
10. A schedule performance index, SPI, of 0.75 means:
A-) Project is over budget.
B-) Project is ahead of schedule.
C-) Project is progressing at 75% of the rate originally planned
D-) Project is progressing at 25% of the rate originally planned
Answer is C, project is progressing at 75% of the rate originally planned. A, is
irrelevant because SPI is a schedule performance index. We cannot derive any
conclusion about budget performance of the project with this index. B, is not
correct because SPI is less than one, therefore, the project is behind schedule.
And D, says that you have completed 25% of the work that you have originally
planned, so it’s not correct. The correct answer here is C, because SPI 0.75 means,
you have completed 75% of your work that you have originally planned.
11. You are the program level manager with several project activities underway.
In the executing process group, you begin to become concerned about the
accuracy of progress reports from the projects. What would BEST support your
opinion that there is a problem?
A-) Quality Audits
B-) Risk Quantification Reports
C-) Regression Analysis
D-) Monte Carlo Analysis
Answer is A. quality audits. If you read the second sentence again, it says that you
are concerned about the accuracy of progress reports from the project. In order
to check whether the standards of your organization have been applied in the
projects that you are responsible of, you can conduct a quality audit and find out
whether there is really a problem. Therefore, here the best answer is A, Quality
Audits.
12. You are a project manager for a major information systems project. Someone
from the quality department comes to see you about beginning a quality audit of
your project. The team, already under pressure to complete the project as soon
as possible, objects to the audit. You should explain to the team that the purpose
of a quality audit is:
A-) Part of an ISO 9000 investigation
B-) To check if the customer is following its quality process
C-) To identify inefficient and ineffective policies
D-) To check the accuracy of costs submitted by the team
How would you explain it to your team if you were in this case? The best answer
is C, to identify inefficient and ineffective policies. B and D are irrelevant options
because quality audit is done in order to check whether you are meeting the
quality standards, whether you are following the quality procedures of your
company. Therefore, it’s not related whether the customer is following its quality
processes. Or it is not related about accuracy of costs submitted by the team.
13. During every project team meeting, the project manager asks each team
member to describe the work he or she is doing, and the project manager assigns
new activities to team members. The length of these meetings has increased
because there are many different activities to assign. This could be happening for
all the following reasons EXCEPT:
A-) Lack of a WBS
B-) Lack of a responsibility assignment matrix
C-) Lack of resource leveling
D-) Lack of team involvement in project planning
Answer is C, lack of resource leveling. If you read the clauses again, here the
problem is the activities or the tasks that need to be performed in the project are
not clear. So, the reasons of these ambiguities, or these unclear points about the
tasks that will be performed can be lack of a WBS. If you could not decompose
your project activities and creation of WBS, then this might be causing the
ambiguities in your project tasks. Also, if you do not have a clear and concise
responsibility assignment matrix, then the resources of your project will have
unclarity about who will do what in the project. Also, if the team was not involved
in project planning, maybe you could not have identified the required steps,
required tasks, activities that need to be performed in the project. So, options A,
B, and D are the possible reasons for this case mentioned in the question.
However, lack of resource leveling might be causing a scheduling problem.
Resource leveling is a technique used in schedule management knowledge area,
which was enabling the uniform distribution of tasks and activities in a project.
14. Conflict resolution techniques that may be used on a project include
confronting, smoothing, forcing, and:
A-) Withdrawing
B-) Directing
C-) Organizing
D-) Controlling
Which of the options is a conflict resolution technique? Answer is A,
Withdrawing, or in other words, avoiding. The other three are directing,
organizing, and controlling, are not types of conflict resolution techniques.
Therefore, the answer is A.
15. All of the following about communication models is true EXCEPT:
A-) Sender encodes his thoughts and sends to receiver.
B-) Information is sent by the sender to receiver with the assistance of medium.
C-) Receiver acknowledges if he agrees with the information he received.
D-) Message is decoded by the receiver into thoughts.
Which one is not correct about communication models? The answer is C, Receiver
acknowledges if he agrees with the information he received. If you remember,
acknowledgement was saying that the receiver got the message, but it does not
mean that he or she agrees with the received message. Acknowledgement means
only that the message sent by the other party has been received. Therefore, it
does not mean an agreement, and here the best answer is C.
16. A project manager is quantifying risk for her project. She needs expert opinion
in this process and related experts are spread over to different geographical
locations. How can she continue?
Using Monte Carlo analysis online
Applying the critical path method
Determine options for recommended corrective action
Applying the Delphi Technique
Answer is D, applying the Delphi Technique. If you remember from our previous
lectures, that technique was asking the experts opinion on a topic or on a
problem and collecting their feedback anonymously and then sending back the
results back to the experts again, and recollecting their responses again. And
reiterating this process until a consensus is reached by all participants, by all
experts. Therefore, since expert opinion is important for this case and experts are
spread over different geographical locations, we can use Delphi Technique.
17. During risk management activities, 236 risks have been identified which are
caused by 13 root causes. You could eliminate the 234 risks by your risk
management activities. For remaining 2 risks, you, together with your team, could
not find a way to mitigate or insure the risks. Also these 2 risks cannot be
outsourced or removed from project scope. What is the best solution?
A-) Accept the risk
B-) Mitigate the risk
C-) Avoid the risk
D-) Transfer the risk
Answer is A, accepting the risk. When you read the case, the project manager
tried first to eliminate the risk, then tried to mitigate or insure the risk. But all
these options did not work. And the last step is the risk should be accepted by the
project team and continuous reserves should be allocated in order to
accommodate risks or in order to overcome the bad impacts of these risks when
they occur. Therefore, the best answer here is accepting the risk and also
planning contingency reserves.
18. The project team is arguing about the prospective sellers who have submitted
proposals. One team member argues for a certain seller while another team
member wants the project to be awarded to a different seller. The BEST thing the
project manager should remind the team to focus on in order to make a selection
is the:
A-) Procurement documents
B-) Procurement audits
C-) Evaluation criteria
D-) Procurement management plan
Answer is C, evaluation criteria. The source selection criteria, or evaluation
criteria defined in plan procurement management process actually defines, in an
objective way, how quantitatively, the potential sellers will be evaluated in
conduct procurements process. Therefore, if you have applied specific metrics,
specific categories to evaluate, or assess a potential seller in conduct
procurement process, then you have to use that metrics, use that categories to
evaluate each seller one by one. And the sellers, which got the highest scores
should be awarded with contract. Therefore, the team members should not go in
argument about the selection of the sellers. Because you have already a
quantitative metric to evaluate which seller is best matching to your source
selection criteria.
19. A project manager is in the middle of creating a request for proposal (RFP).
What part of the procurement process is she in?
A-) Conduct procurements
B-) Plan Procurements
C-) Control Procurements
D-) Close Procurements
Answer is B, she is in plan procurements process. Because procurement
statement of work, procurement documents are prepared in plan procurements
management process. And RFP is a procurement document as well. Therefore, it
is prepared in plan procurements process. RFP was defining what the buyer is
requiring from the seller.
20. You want to group your project stakeholders based on their authority and
involvement in the project. Which of the following is appropriate model for this?
A-) Power/Interest Grid
B-) Power/Influence Grid
C-) Influence/Impact Grid
D-) Salience Model
Answer is B. Power/Influence Grid. Authority of a stakeholder represents power
of the stakeholder and involvement of a stakeholder represents the influence
level of the stakeholder. Therefore, answer is B. Power/Influence Grid.
21. Which of the following is NOT true for a project?
A-) Projects are constrained by limited resources
B-)Projects are planned, executed, and controlled
C-) Projects create a unique product or service
D-) Projects are ongoing and repetitive
Answer is D. A project is a temporary endeavor undertaken to create a unique
product, service, or result. The temporary nature of projects indicates a definite
beginning and ending.
22. In the context of a desirable model of communication between a sender and a
receiver, all the following statements are correct EXCEPT:
A-) Noise should be at minimum level.
B-) Receiver must reply the message after decoding the message.
C-) Receiver should acknowledge first and then agree with the message sent by
the sender.
D-) Receiver should send a feedback message to the sender.
Answer is C. As part of the communications process, the sender is responsible for
the transmission of the message, ensuring the information being communicated is
clear and complete, and confirming the communication is correctly understood.
The receiver is responsible for ensuring that the information is received in its
entirety, understood correctly, and acknowledged or responded to appropriately.
However, receiver may not agree on received message
23. ohn is a project manager of a complicated project. When he started creating a
work breakdown structure for his project, he realized that it is too complex to
complete work breakdown structure on a single sheet. You, as a colleague of
John, recommend using a work breakdown structure numbering system to John
to:
A-) Determine the complexity of the project
B-) Help in automating the WBS using appropriate software
C-) Provide a hierarchical structure for each WBS element
D-) Present risks of the project
Answer is C. The WBS is finalized by assigning each work package to a control
account and establishing a unique identifier for that work package from a code of
accounts. These identifiers provide a structure for hierarchical summation of
costs, schedule, and resource information.
24. You are trying to establish a cost performance baseline for your project in
Determine Budget Process. You can use the following tool and techniques
EXCEPT:
A-) Cost aggregation
B-) Bottom-up estimating
C-) Expert judgment
D-) Historical relationships
Answer is B. Tools and techniques used in Determine Budget Process are:
Cost aggregation
Reserve analysis
Expert judgment
Historical relationships
Funding limit reconciliation
Working card
Salary
Personal Life
Relationships at work
Security
Status
Building trust
Resolving conflict
Active listening
Overcoming resistance to change
29. There has been several changes in your project and this affected your cost and
schedule estimates. This has invalidated the original estimating assumptions.
What is the estimate at completion (EAC) for your project based on following
parameters?
BAC = $ 360,000
AC = $ 120,000
EV = $ 180,000
CPI = 1.2
ETC = $ 145,000
A-)$ 300.000
B-)$ 265.000
C-)$ 325.000
D-)$ 360.000
Answer is B. EAC = AC + ETC = $ 120.000 + $ 145.000 = $ 265.000
30. Portfolio managers are responsible of managing:
A-)Dependency of different projects
B-)Operational projects only
C-)Projects, programs and operations
D-)Functional work and projects
Answer is C. The relationship among portfolios, programs, and projects is such
that a portfolio refers to a collection of projects, programs, sub-portfolios, and
operations managed as a group to achieve strategic objectives
31. Your Company has entered into a joint venture with Service Company to
develop a software program. Which of the following should be cooperatively
prepared by both the buyer and the seller during teaming agreement process?
A-)Contract
B-)Contract, Procurement statement of work
C-)Request for proposal
D-)Human Resource Plan
Answer is B. In some cases, the seller may already be working under a contract
funded by the buyer or jointly by both parties. The effort of the buyer and seller in
this process is to collectively prepare a procurement statement of work that will
satisfy the requirements of the project. The parties will then negotiate a final
contract for award.
32. There are three projects that are possible to be executed in your company:
Based on Net Present Value (NPV) criterion, which project should be selected?
A-)Project A
B-)Project B
C-)Project C
D-)None of them, they all have equal value
Answer is A. Project A has highest NPV of $ 300,000. Time value of money is
already taken into account when calculating NPV of a project. Since Project A has
the highest NPV, it should be selected.
33. You are trying to gather ideas related to project and product requirements.
Which technique is appropriate for this?
A-)Brainstorming
B-)Nominal Group Technique
C-)Affinity Diagram
D-)Multi-criteria Decision Analysis
Answer is A. A technique used to generate and collect multiple ideas related to
project and product requirements.
34. Your colleague Wayne, a project manager, completed a mp3 player
development project. While he was telling his experiences from his project, he
mentioned that they delivered “adjustable screen timeout duration” feature,
without a deviation from the plan, although the customer did not require and was
not in scope of the project. He added that customer was very surprised and happy
when they saw this additional feature at the end of the project. Which of the
following is correct about this story?
A-)Gold plating was done in the project
B-)Customer satisfaction increased with an additional feature which they did not
expect
C-)Change request has been delivered successfully
D-)Unnecessary risk has been taken by adding a new feature to product.
Answer is A. Gold plating refers to continuing to work on a project or task well
past the point where the extra effort is worth the value it adds (if any). After
having met the requirements, the assignee works on further enhancing the
product, thinking the customer would be delighted to see additional or more
polished features, rather than what was asked for or expected.
35. You have documented all possible risks that can affect your project with
appropriate risk responses when they occur in your risk management plan. All
other remaining risks are called as:
A-)Risk Triggers
B-)Unmanageable Risks
C-)Residual Risks
D-)Accepted Risks
Answer is C. Residual risks that are expected to remain after planned responses
have been taken, as well as those that have been deliberately accepted.
36. You are working as a project manager in a company. You have the highest
degree of authority, you are working full-time for your project and you manage
the budget of the project. What is the organization structure in your company?
A-)Strong Matrix
B-)Projectized
C-)Functional
D-)Balanced Matrix
Answer is B. In a projectized organization structure, project manager has the
highest level of authority, works full-time and manages the budget of the project.
37. You are the project manager of a software project team consisting of 2
analysts, 4 software developers and 3 test engineers. One new test engineer will
join the team in two weeks. What will be the number of communication channels
after new test engineer joins the team?
A-)55
B-)50
C-)45
D-)36
Answer is A. The total number of potential communication channels is n(n-1)/2,
where n represents the number of stakeholders.
Your team has 10 team members already (2 analysts, 4 software developers, 3
test engineers, and you as a project manager). After new test engineer joins,
there will be 11 team members.
Number of communication channels = 11*(11-1)/2=11*10/2 = 55
38. All of the following are tools and techniques that can be used in Identify
Stakeholders process EXCEPT:
A-)Expert Judgment
B-)Stakeholder Register
C-)Meetings
D-)Stakeholder Analysis
Answer B. Stakeholder analysis, Expert Judgment and Meetings are tools and
techniques that can be used in Identify Stakeholders process. Stakeholder
Register is an output of Identify Stakeholders process.
39. The seller`s project is undertaken on contract and you are an employee of the
seller. Since you earlier worked with XYZ Factory, the buyer, you happen to be
aware of the evaluation criteria used in XYZ Factory to select sellers. You
understand that this could be a potential conflict of interest situation. How do you
propose to act?
A-)Do nothing and continue to work as before
B-)Take appropriate person in XYZ Factory into confidence and discuss this issue
with her
C-)Disclose the evaluation criteria to your (seller) organization and help their
business growth
D-)Remove yourself from the project
Answer is B. Since the evaluation criteria are proprietary information of XYZ
Factory, it is important for you to discuss the matter directly with the appropriate
person in the XYZ Factory.
40. During project planning phase, which of the following steps come latest
compared to others?
A-)Hold kick-off meeting
B-)Gain formal approval of the plan
C-)Develop Budget
D-)Develop Schedule
Answer is A. Following is the order of steps in planning phase:
Develop schedule
Develop budget
Gain formal approval of the plan
Hold kick-off meeting
Kick-off meeting is the last step of planning phase.
48. If a risk event has a 90 percent chance of occurring and the impact will
be $10,000, what does $9,000 represent?
a. Risk value
b. Expected value
c. Real value
d. Contingency budget
Answer option b. This question requires that you calculate the Expected
Monetary Value (EMV), which is: EMV = Probability x Impact. In the problem,
“90 percent chance of occurring “is the Probability, while “impact will be
$10,000” is obviously the impact. Therefore: EMV = 0.9 x $10,000
= $9,000, which is answer option b., the “Expected value.”
51. There are five levels of stakeholder engagement. What are they?
a. Unaware, Resistant, Neutral, Supportive, Influencing
b. Aware, Resistant, Neutral, Supportive, Leading
c. Unaware, Resistant, Neutral, Supportive, Leading
d. Aware, Resistant, Interested, Supportive, Leadinga
Answer option c. is the correct answer, as highlighted on the PMBOK
52. Which of the following is not true?
(a) Every project is unique
(b) A project gives some output
(c) Projects are not repetitive
(d) Car manufacturing is an example of project
Explanation: As per the definition, a project is unique, non-repetitive,
and gives some output. Therefore, options a, b, & c are definitely the
characteristics of a project. Car manufacturing is repetitive production
process; hence, it is not a characteristic of a project.
58. You hired a programmer for $25/hour for two months. What kind of
contract is this?
(a) CPIF
(b) Fixed Price
(c) Time & Material
(d) CPAF
Explanation: A Time and Material contract is mostly used for temporary hiring, or hiring experts
in cases where you cannot define the exact scope of work quickly.
59. A person who is directly or indirectly involved with your project, or affected
by your project or its outcome, is known as:
(a) Customer
(b) Manager
(c) Team Member
(d) Stakeholder
Explanation: This is the definition of the stakeholders
65. Which of the following strategies is not used for negative risks?
(a) Exploit
(b) Transfer
(c) Avoid
(d) Mitigate
Explanation: Exploit is the strategy where you do everything to realize the opportunity. This
type of strategy cannot be used with negative risks.
69. For your project you need to outsource some work, so you sign a fixed
price contract with a contractor. In this contract, the price above which the
seller bears all costs of cost overrun is known as:
(a) Point of Total Assumption
(b) Cost Overrun
(c) Target Cost
(d) Target Price
Explanation: This is the Point of Total Assumption (PTA). PTA is a point
above which total cost overrun is borne by the seller.
70. Which of the following statement is true about the Project Charter?
(a) It authorizes the existence of a project
(b) It is a bidding document
(c) It is used to rank the risks
(d) All of the above
71. You have been given 100,000 USD to complete the project. 60,000 USD
has been spent, though as per the schedule, 55,000 USD should have been
spent to complete the same work. What is the Budget at Completion (BAC)?
(a) 55,000 USD
(b) 100,000 USD
(c) 60,000 USD
(d) 105,000 USD
72. You have six team members working under you. How many lines of
communication will you have in your communication plan?
(a) 16
(b) 15
(c) 21
(d) 30
Explanation:
Communication lines = N*(N–1)/2
=21
73. A Risk that is caused by the response of another risk, is known as:
(a) Primary Risk
(b) Secondary Risk
(c) Residual Risk
(d) Negative Risk
Explanation: A secondary risk is caused by applying the strategy to minimize
the effect of the primary risk. For example, you dig a trench to stop people
crossing it, but there is also a chance that someone may fall into it.
74. What should be your goal while negotiating with the seller?
(a) Press for lower price
(b) Press for early completion
(c) To arrive at a fair deal
(d) Give him extra benefits
75. How will you deal with the stakeholders with High Interest but Low Power?
(a) Keep them informed
(b) Monitor them
(c) Manage them closely
(d) Try to satisfy them
Explanation: You will deal with stakeholders as follows: high power and low
interest category stakeholders will be kept satisfied, high power and high
interest category stakeholders will be managed closely, low power and low
interest category stakeholders will only be monitored and high interest and low
power category stakeholders will be kept informed.
76. Which of the following is not an example of Enterprise Environmental
Factor?
(a) Rules and Regulations
(b) Organization Culture
(c) Procedures
(d) Market condition
Explanation: Enterprise Environmental Factors are conditions that influence
the project. These factors are not within the control of the project team and
they have to work within it. Enterprise Environmental Factors are not always
helpful to the project team; sometimes they may harm you as well.
Rules & Regulations, Organization Culture, and Market Conditions are
examples of Enterprise Environmental Factors.
Procedure is an example of Organizational Process Assets.
90. What does the Cost Performance Index (CPI) say about the project?
(a) It says whether you are ahead of or behind schedule
(b) It says whether you are overspending or under-spending
(c) It says whether your process is under control or not
(d) Specifies the control limits of the process
91. A contract cannot be a legal document until:
(a) Signed by the project manager
(b) Signed by the buyer
(c) Signed by the seller
(d) Signed by all parties
92. A project has more than one critical path. What does this mean to you?
(a) Risk increases – more path, more to monitor
(b) Risk decreases
(c) The duration of the project reduces
(d) The project may cost less
93. If an un-identified risk occurs:
(a) You will use the management reserve to manage it
(b) You will use the contingency reserve to manage it
(c) You will not take any action
(d) You will log it into the risk registers
Explanation: Management Reserve is used to manage un-identified risks.
94. Who contributes, develops and updates the Lessons Learned document?
(a) Client
(b) Project Management Team
(c) Functional Manager
(d) Management
Explanation: The whole project management team, including the project manager, contributes
to and helps maintain the lessons learned document.
95. You are developing the project management plan for your project. What
will be your main emphasis during this process?
(a) Hide it from team members until it is completed
(b) To take input from team members
(c) Not to inform management until it is ready
(d) Hide it from everyone
96. You have added a few extra features to the product with the intention to
make the client happy. This activity is known as:
(a) Buffer
(b) Scope Creep
(c) Gold Plating
(d) None of the above
Explanation: Gold Plating is a phenomenon where you add some extra
features to the product in order to make the client happy. Gold Plating may
increase the cost and risks.
97. Which one is an example of Crashing?
(a) Starting a few activities simultaneously
(b) Adding more resources
(c) Reducing resources
(d) Increasing the duration of project
98. TCPI = 1.5, what does it mean?
(a) You are doing well
(b) You are in bad condition
(c) You are going as planned
(d) None of the above
Explanation: If the TCPI is more than one, it means you need to work with better cost
performance.
100. Which one of the following is not true about the change request?
(a) It happens usually in the execution phase of the project
(b) Usually requested by the client
(c) Usually requested by the project management team
(d) It is always an informal verbal request
Explanation: Change request must always be a formal request. You cannot process a change
request based on any informal request.
101. Due to a miscommunication with the client, some features are added to
the product. This process is known as:
(a) Gold Plating
(b) Scope Creep
(c) Scope Management
(d) Buffer
Explanation: The uncontrolled addition to the scope is known as Scope Creep. Scope Creep
indicates that you do not have adequate control over your project.
104. You have identified a large number of risks during your risk identification
process. What will be your next step?
(a) You will prioritize them using the Qualitative Risk Analysis process
(b) Go for the Quantitative Risk Analysis
(c) Assign the risk owner to each risk
(d) Calculate the contingency reserve
105. Which of the following represents the correct order of project
management phases?
(a) Initiating, Planning, Executing, Monitoring & Controlling, Closing
(b) Initiating, Executing, Planning, Monitoring & Controlling, Closing
(c) Initiating, Planning, Monitoring & Controlling, Executing, Closing
(d) Planning, Initiating, Executing, Monitoring & Controlling, Closing
106. The role of the Develop Project Management Plan process is to:
(a) Create a Schedule for the Project
(b) Monitor Schedule
(c) Integrate all Subsidiary Plans
(d) Develop Cost Baseline
Explanation: The role of Develop Project Management Plan process is to
integrate all subsidiary plans; e.g. scope management plan, schedule
management plan, cost management plan, etc.
107. In risk management, you have many strategies to manage risks. Which
strategy will you not use with the negative risks?
(a) Mitigate
(b) Exploit
(c) Transfer
(d) Avoid
Explanation: Exploit risk response strategy is used with positive risks.
108. Which document is created by breaking the project scope into smaller
and manageable elements?
(a) Scope Baseline
(b) WBS
(c) OBS
(d) None of the above
109. Rearranging resources to optimize their utilization is known as:
(a) Crashing
(b) Fast Tracking
(c) Resource Leveling
(d) Schedule Compression
110. Which of the following statements is true about the Point of Total
Assumption?
(a) Above PTA, seller bears the cost
(b) Above PTA, buyer bears the cost
(c) Below PTA, buyer bears the full cost
(d) Below PTA, seller bears the 50% of cost
Explanation: Under the FPIF, you set a ceiling price; once this ceiling price is
passed, the seller bears all the cost. This point is known as Point of Total
Assumption.
111. Pareto Chart helps you find:
(a) Minor sources creating the majority of problems
(b) Majority of causes creating the minority of problems
(c) Cause of variation
(d) Cause of deviation
Explanation: Pareto Chart helps you identify the minor number of sources
causing most of the troubles
112. What is a Workaround?
(a) A response to unplanned threat
(b) A response to identified threat
(c) A response to low-priority risk
(d) None of the above
Explanation: When an unidentified risk occurs, you will take prompt action to
handle it. This activity is called a workaround.
113. While inspecting, you find a defective component and you repaired it.
This act is known as:
(a) Preventive Action
(b) Corrective Action
(c) Defect Repair
(d) None of Above
Explanation: Defect Repair is a process where you correct a defective
component. Preventive Action is an action that is taken to avoid any
anticipated future defects that may appear in the component. Corrective
Action is a future response to the defect repair process or the correction, so
that the cause of error or non-conformity will not occur again.
114. You are managing a project with a budget of 500,000 USD, and 250,000
USD has been spent. Upon review, you observe that only 40% of the work
has been completed; though, your schedule says that you should have
completed 50% of the work. What is the Actual Cost?
(a) 500,000 USD
(b) 200,000 USD
(c) 300,000 USD
(d) 250,000 USD
115. You are reviewing the control chart and observe that there are seven
points in a row that are below the mean. What does it mean?
(a) The mean should be re-adjusted
(b) Investigate the cause of it
(c) Re-draw in control limit
(d) It is common, nothing to worry about
Explanation: A process is considered to be out of control if seven
consecutive plot points are either above or below the mean.
116. The client inspects the deliverables with you, and finds that it meets the
acceptance criteria. He signed off and formally approves the deliverables.
Which process is this?
(a) Control Quality
(b) Control Scope
(c) Validate Scope
(d) Close Project
Explanation: Accepted Deliverables is the output of the Validate Scope
process.
117. Which is an example of Triple Constraint?
(a) Scope, Human Resource, Time
(b) Quality, Scope, Human Resource
(c) Cost, Human Resource, Time
(d) Scope, Cost, Time
Explanation: Scope, Cost and Time are considered Triple Constraints.
118. In which phase will the risks be at the lowest level?
(a) Initiating
(b) Planning
(c) Execution
(d) Closing
Explanation: Risk will be at its highest point at the Initiating Process group
and at the minimum at the Closing Process group.
119. Which Conflict Resolution Technique leads to consensus and
commitment?
(a) Withdraw
(b) Accommodate
(c) Compromise
(d) Collaborative
Explanation: Collaborative approach incorporates viewpoints of all parties involved in the
conflict.
131. During which phase of the project will risks be the highest?
(a) Initiating
(b) Planning
(c) Execution
(d) Closing
Explanation: During the Initiating phase the risks are highest and they decrease as the project
progresses
132. For your project, you have identified your project stakeholders,
developed strategy and now you are in the execution phase. In which project
phases do you identify the project stakeholders?
(a) Initiating and Planning and Execution
(b) Initiating and Planning
(c) Initiating, Planning, and Monitoring & Controlling
(d) All phases
Explanation: Stakeholder identification is an iterative process. You will identify stakeholders
throughout the project.
133. You are developing the project charter, with management, for a new
project. You are going to be the project manager. Who will sign the project
charter?
(a) Project Manager
(b) Operational Manager
(c) Functional Manager
(d) Someone from top management
134. What may happen if your project has more than one critical path?
(a) It will cost more
(b) The project completion date may be extended
(c) The quality may be reduced
(d) Risks will increase
135. Which of the following diagram looks like a fish skeleton?
(a) Ishikawa Diagram
(b) Tornado Diagram
(c) Decision Tree
(d) None of the above
136. For all your needs you have to go to the functional manager; moreover,
you do not have control over the budget. In what kind of organization are you
working?
(a) Projectized
(b) Weak Matrix
(c) Strong Matrix
(d) Balanced Matrix
137. Your management has asked you to provide them with the rough order
estimate for a project on an urgent basis. In this case, which of the following
techniques will you use?
(a) Parametric
(b) Bottom Up
(c) Rough order
(d) Analogous
138. Which is not an example of organizational process assets?
(a) Processes
(b) Procedures
(c) Lessons learned
(d) Political conditions
139. Your project is late and to bring it back on track you are adding extra
resources to some activities and giving overtime to your team members. This
is an example of:
(a) Critical Chain
(b) Fast Tracking
(c) Crashing
(d) Resource Leveling
140. In a balanced matrix organization, who has authority over the budget?
(a) Project Manager
(b) Functional Manager
(c) Both
(d) None of the Above
141. Which document authorizes the existence of the project?
(a) Scope Statement
(b) Project Plan
(c) Project Charter
(d) Stakeholder’s Register
142. he successor activity cannot be finished until the predecessor activity
starts. This is an example of which kind of relationship:
(a) Finish to Start (FS)
(b) Finish to Finish (FF)
(c) Start To Start (SS)
(d) Start to Finish (SF)
143. Which of the following graphs shows the major of problems due to a
minority of causes?
(a) Scatter Diagram
(b) GANTT Chart
(c) Pareto Diagram
(d) Bar Chart
144. Regarding the project expeditor and the project coordinator, which of the
following statements is correct?
(a) The coordinator has more power than the expeditor
(b) The expeditor has more power than the coordinator
(c) Both have equal power
(d) None of the above
Explanation: In a weak matrix organization, the project manager can work as either a
project coordinator or an expeditor. The expeditor has no authority or power to make
any decision while the coordinator has a little power to make decisions.
145. Your project is delayed by 45 days and the client has threatened that he
will impose a heavy penalty if you do not complete the project on time.
Therefore, to bring the project back on schedule you hire some equipment
and bring more team members to work with you. This is an example of:
(a) Resource Leveling
(b) Resource Optimization
(c) Crashing
(d) Fast Tracking
146. Which of the following risks remain even after applying the risk response
of an identified risk?
(a) Primary Risk
(b) Secondary Risk
(c) Remaining Risk
(d) Residual Risk
147. You have been given a task to accurately calculate the cost of a project.
Which of the following techniques will you use to get the most accurate cost of
the project?
(a) Parametric
(b) Analogous
(c) Bottom Up
(d) Top Down
148. Tom is a low-power stakeholder in your project, He is very interested and
enthusiastic about your project. He wants you to complete the project
successfully. How will you manage him?
(a) Keep informed
(b) Monitor
(c) Keep satisfied
(d) Manage closely
149. Who should be involved in identifying the project risks?
(a) Project team members
(b) Sponsors and upper management
(c) All relevant project stakeholders
(d) Project manager and top management
150. There is a risk which has a 7% chance of happening, and if it occurs it
will cost you 2,500 USD. What is the EMV of this event?
(a) -175 USD
(b) 2,325 USD
(c) 2,675 USD
(d) 175 USD
EMV = Impact * Probability
= (-2,500)*.07
= -175
151. During the procurement phase, you are analyzing whether you should
outsource a particular task or do it on your own with your team. Which
process are you currently in?
(a) Plan Procurement Management
(b) Conduct Procurement
(c) Control Procurement
(d) Decide Procurement
152. A company has to make a choice between two projects, because the
available resources in money and kind are not sufficient to run both at the same
time. Each project would take 9 months and would cost $250,000.
The first project is a process optimization which would result in a cost reduction
of $120,000 per year. This benefit would be achieved immediately after the end
of the project.
The second project would be the development of a new product which could
produce the following net profits after the end of the project:
1. year: $ 15,000
2. year: $ 125,000
3. year: $ 220,000
Assumed is a discount rate of 5% per year. Looking at the present values of the
benefits of these projects in the first 3 years, what is true for their monetary
attractiveness?
The measurements made at the end of the process yielded the following results:
Which of the following is usually not an element of the project charter and can
therefore removed from the document?
d.High-level risks
a.Scope Statement
d.Requested Change
8.
a. Make sure that all exit criteria of the consecutive phase have been met to
ensure the flow of communications in a team situation which is more complex by
a factor of 2.
b. Make sure that all entry criteria of the previous phase have been met by
planning and performing a phase gate meeting to assess technical aptness.
c. Make sure that all exit criteria of the previous phase have been met by
planning and performing a phase gate meeting to assess technical performance.
10. A project manager has been asked to support an internal project request by
developing a business case.
11.
You found the following earned value analysis information for a project that was
recently closed-out:
a.The project has been cancelled while it was executed. At that time the
project was behind schedule and on budget.
b.The project's deliverables have all been finished. The project came in
behind schedule but on budget.
c.The project's deliverables have all been finished. The project came in
ahead of schedule but on budget.
d.The project's deliverables have all been finished. The project came in on
schedule but over budget.
12.
a.Quality audit
b.Deliverable inspection
15. With your team you are using judgment from subject matter experts early
during initiation to discuss perceived project risks. There is a number of experts
from different disciplines available. You want to create a conversational setting to
allow them to discuss their different views on the project and its risks.
Which of the following techniques can ensure best that the different perceptions
and opinions are contributing to the expert discussion?
a.Peer review
b.SWOT analysis
c.Focus group
a.$1,300,000
b.$1,500,000
c.$80,000
d.$1,125,000
She discovers that two members assigned to the project have charged time
without performing any work for the project customer. Upon further
investigation, she determines that this occurred because there have been no
other project assignments open for these employees and that her company
wanted to keep their time billed to a customer. The customer is unaware of these
facts.
a.Try to find some productive work for these staff members in the project
and leave them on the team.
b.The best thing is to do nothing. The customer will not realize the problem
anyway.
d.Take the two people off the team immediately and arrange for the
refund of the excess charges to the customer.
18. Start dates in the following network logic diagram are defined as early
morning, finish dates are evening.
19. Your project is executed with a globally spread virtual team. The project
progress has been found to be too slow. Which measure is most likely to
immediately help team members act as a team and speed up the project?
The procurement documents will probably have to support what main intention?
a.Describing the needs of the project in sufficient detail to enable vendors
to make suitable proposals based on each one's specific strengths
c.Helping to clarify the approved project scope statement and giving guidelines to
break it down into the WBS and the WBS dictionary of the project
d.Developing the risk management plan and the risk reports from those risk
management reviews which have been made so far eith the vendors
a.Requirements engineering
b.Communication planning
d.Network diagramming
22. You are assigned as the project manager to a project which is executed for
a customer under FP contract. Your customer informed you this morning that
they insist on certain "refinements" of the project scope. They consider them
clearly part of the contractual price and require implementation without extra
costs or delays.
You agree that the requested actions will be beneficial to the project, but believe
that they constitute a major change increasing the project scope. What should
you do next?
b.Perform earned value analysis to assess the current status of the project
and get all the numbers you need to communicate the case to the change control
board which then will have to make the best decision regarding the customer
request.
c.Check the contract, the project charter, the scope statement and other
documents related to the project and the legal relationship. Implement ADR
(alternative dispute resolution) procedures if the conflict cannot be resolved
otherwise.
d.Talk to the project sales department and find a joint solution with them
how to best reject the request considering the commercial and strategic value of
the customer to the organization you are working for.
23. A prime contractor in a customer project under CPFF contract has run into
unexpected technical problems through no fault of their own. Fixing these
problems will require a lot of additional work to be done.
The company made a decision to book more staff and equipment from their
subcontractors in order to increase productivity and adhere to the agreed
timeline. The overhead work for the project is reimbursed by the customer with
the fixed fee and will remain unchanged. The customer agreed to this decision.
a.The contractor‘s indirect costs will increase and the customer‘s payment
for them will increase, too.
b.The contractor‘s indirect costs will increase, but the customer‘s payment
for them will not increase.
c.The contractor‘s indirect costs will not increase, but the customer‘s
payment for them will.
d.Both the contractor's indirect costs and the customer‘s payment for
them will not increase.
24. A project management team is evaluating the causes that might contribute
to unsatisfactory performance and quality. They are discussing the influence of
common causes (also called random causes) and special causes.
Which of the following statements should they use as a guidance to identify the
types of causes of the problems found?
a.Special causes are generally easier to predict and cope with than common
causes.
a.Projects should never be executed without a valid, updated and working project
management plan.
b.The consistency of the various plans is secondary because it is only the results
that matter.
d.Poor planning and insufficient updating of project management plans are rather
uncommon as reasons for cost and time overruns.
26. Together with your project management team in a project to build a state-
of-the-art power station, you want to perform active risk acceptance in your
project.
Assuming ±3 sigma precision level for each estimate, what is the calculated
standard deviation of the allover path?
d.You can not derive the path standard deviation from the information
given.
b.The limits of the six sigma area on either side of a control chart to plot
measured values; data found outside the area are out of specification and can
lead to rejection of an entire batch.
30. The scope baseline is used to ídentify variance on the scope during the
project. It consists of what?
a.Scope statement, WBS with work packages and planning packages, WBS
dictionary
a.36 days
b.37 days
c.39 days
d.42 day
32. Which tools and techniques are used in the processes Create WBS and
Define activities?
c.Brainstorming
a.Theft, embezzlement
b.Fraud
c.Corruption
d.Bribery
a.a
b.a, b, c, d
c.b, c, d
d.b, c
c.Variables sampling means that the result is classified into one of the 3
categories:
d.Inspection is often mainly done to keep errors out of the hands of the
customer as an activity of process control.
35. Which statement describes best why you should document assumptions?
a.Prevention costs
b.Maintenance cost
c.Appraisal costs
d.Failure costs
37. You have recently been assigned as a project manager to a new B-O-T
(build, operate, transfer) capital project. Your company will invest in public
infrastructure today, then make profit from operating the infrastructure over 30
years, after which it is handed over to the government.
Reviewing the initial documentation you found out that the business case has
been calculated with a very small margin during operations of the infrastructure.
What should you do?
a.As you are not responsible for lifecycle costing, you don't have to worry
about operation profits. Focus on project costs from initiation through handover.
d.Develop a plan to immediately leave the company, when the first signs
occur that it may not survive the questionnable business case and go insolvent.
39. You are project manager in a global project with a team consisting of
people from various countries. What can you try to prevent misunderstandings
due to cross-cultural differences?
a.Use all communication methods available that are suitable for the team
and follow up in writing when communicating verbally. Remember that cultural
and individual diversity may help project teams solving unforeseen problems
during the course of the project.
b.When you are about to form a team for your project, keep in mind that
some cultures are developed, others are more primitive. Some have values, some
not. You should consequently avoid choosing members from countries with
cultures that are not similar to your own.
c.Cultural dilemmas can prevent any project from being successful. They
should therefore be smoothed or suppressed so as to make sure that they cannot
disrupt project work. Your effort should concentrate on communication that can
help reach that goal.
41. A change request in a project has been rejected some weeks ago.
Yesterday, the project manager found out that it nevertheless has been
implemented by team members, who had originally requested the change and
therefore knew of it, but not of the rejection.
b.Verify scope
b.A warning sign that a previously identified risk might be occurring or has
occurred
You and your project team received a note this morning informing you that the
software delivery will be delayed by 2 weeks.
What is the term commonly used for the resources inside the directory?
a.Unassigned staff
b.Project team
c.Resource pool
d.Program team
45. What does the acronym RACI commonly stand for in project management?
d.Remove physical ánd legal constraints and replace hard logic with soft
logic.
47. Liquidated damages (LDs) are contractually agreed payments in order to...
d...make a bid or proposal binding for the offerer while the customer has
time to select among various bidders.
48. Together with your team, you are writing a risk management plan. In the
team, discussions are occurring what should be covered by the plan and what not.
Finally, the team found out that _______ should NOT be covered by a risk
management plan?
49. You are assigned as the project manager to a project which had a one-time
cost variance in the past caused by unexpected rework which has meanwhile
been finished. You expect future costs of the project as was originally planned
You perform earned value analysis and get the following results:
BAC is 500,000.
What is right?
a.EAC = 550,000
b.EAC = 525,000
c.EAC = 500,000
d.EAC = 425,000
50. An estimation has been made for a construction project that the
construction of a residential home will cost a certain amount per square foot of
living area.
b.Bottom-up estimating
c.Top-down estimating
d.Parametric estimating
a.A change request that helps improving the project and its product,
service, or result and could be generally discussed in a friendly style.
b.A direction by the buyer or an action taken by the seller that either
party may post hoc consider an undocumented change.
54. What is true for modern project management? Project managers need...
55. You are the project manager in an engineering project and have recently
signed a contract with a software vendor for the development of a complicated
control solution as a contractor of your project.
The software will be used to control machinery equipment which your project
team is currently developing. The contract is a lump-sum contract. The contractor
has a cost target based on estimates, which seem rather low to you. Which of the
following statements is NOT true for this situation?
a.It is the contractor's risk in this type of contract that their profit may
vanish if costs have been underestimated.
b.This form of contract should only be chosen when all requirements on the
contractor's product are well-understood by all parties involved.
c.In a fixed-price contract, change requests can require adaptations to
price, schedule and other contractual items for the changes to be applied.
d.It is likely that your organization may have to assume any unexpected
additional costs for the software development that occur.
a.Quality audit
b.Inspection
c.Quality testing
d.Reject screening
a.It allows a project manager to easily identify the breakdown level of the
item in the resource structure.
d.It defines ethical behavior in the project and the responsibilities to the
customer and the profession.
58. You are the manager of your company's project management office. The
company is running many concurrent projects; most of them share a resource
pool of technical staff. Understanding how resources are utilized across projects
has been found essential to overall project performance, including cost
effectiveness and profitability.
This morning you received a message that the resource pool members will be
unable to perform as planned for the next months because the overall work load
has grown too high and while delays are adding up, the morale of the staff is
going down.
c.Do nothing related to the described problem unless you are explicitly
requested by the organizations upper management. Supporting decision making
on the level on which project portfolio management is done, is not the project
management office's business.
59. You have been criticized that certain specifications in your scope statement
do not pass the test for SMART objectives. What are SMART objectives?
Which additional documents may help you clarify work requirements in this
situation?
After budget approval, an additional and unexpected cost item has been
identified, which made the project more expensive some weeks ago. The item has
meanwhile been paid by the project, and it is expected that for the remaining
duration of the project, costs will be as budgeted.
In this case, which is the best formula to calculate EaC (Estimate at Completion)?
a.EaC = BaC - CV
c.EaC = AC + BtC / CV
62. During a company event, you had the opportunity to talk to a colleague
project manager. He told you that in his current project actual costs are 15%
under cumulated costs budgeted for today.
What do you think?
b.The project will probably be completed with total costs remaining under
budget until the end.
c.A significant cost increase during the further course of the project will
probably bring the costs back to baseline level.
d.Original cost forecasting and budgeting for the project must have been
poor to allow this variance.
63. What is the meaning of Jerry B. Harvey's concept called the "Journey to
Abilene"?
a.Project managers should visit their customers far more often than what is
usual in order to avoid misunderstandings and bad emotions.
c.Group decisions can have the paradox outcome, that a decision is jointly
made or approved that is not desired by any of the group members.
64. Which of the following statements describes best the relationship between
project phases and the project life cycle?
a.The project life cycle includes the time when the project is performed and
the expected product lifespan after that.
2. Project charter,
2. Scope statement,
3. Project charter,
1. Feasibility study
3. Contract,
3. Project charter
5. Scope baseline.
c.A metaphoric description of the short term uncertainties that are present
in every project.
d.The graph that describes the typical growth of earned value during the
course of the project.
b.Ensuring that proposed and approved changes to configuration items are fully
analyzed.
c.Ensuring that proposed and approved changes to configuration items are
fully documented.
69. Which statement describes best the meaning of the term cost baseline?
70. Which is NOT true in regard of RoI (return on investment) calculation for a
project?
a.It defines the cumulated net income from an investment at a given point
in time or during a defined period.
b.It includes investment, direct and indirect costs and may include
allowances for capital cost, depreciation, risk of loss, and/or inflation.
d.It is the time when cumulated net income is equal to the investment.
The sponsor considers to shift some resources from the first project to the second
to accelerate the second project, which is currently behind schedule.
What is the most likely outcome of such a measure?
c.Project A will become slower. According to Brooks's law, Project B will also lose
pace.
72. Which of the following statements describes best the relationship of quality
and grade?
73. A project management team intends to develop a lifecycle for its new
software development project on a continuum between the extremes of highly
agile and highly predictive methods. What is a typical signal that the lifecycle
chosen is located between the two extremes?
74. You have been asked to calculate the internal rate of return (IRR) of a
project? What will you assess?
a.The time period needed to pay back the investment from a project when
future income is discounted.
c.The rate of negative risk that can be accepted for a project without
turning the expected net present value negative.
75. You have just created the following network logic diagram to describe the
planned flow of activities for your project which will start tomorrow:
Which potential inconsistency in the diagram should you solve right now to
ensure that the activities and the milestones "Start" and "A-F finished" are
correctly linked?
c.You cannot calculate a critical path when lags and/or leads are calculated
in percent.
76. A project management team identified negative risks (threats) that cannot
be responded to by avoidance or mitigation. An alternative risk response would
be active acceptance. What would the team do to implement that?
b.Monitor risks.
Which management principle is applied by the project manager and the team?
a.Self-organizing teams
b.Norming teams
c.Micro-managed teams
d.Competing teams
a.Autocratic leadership
b.Benevolent leadership
c.Responsible leadership
d.Servant leadership
c.Project charter
a.It is the seller’s responsibility to ensure that the procurement meets the
specific needs of the project.
c.Local culture and laws may have influence upon the enforceability of a
contract.
83. When does a project manager perform the integrated change control
process to make sure the effects of change requests are under control?
a.Complexity risk
b.Ambiguity risk
c.Variability risk
d.Event-related risk
85. A project was planned to take 5 months. The team is currently 3 months
into it and has completed half of the work.
Applying Earned schedule technique, what are the performance data of the
project?
a.Activity attributes
b.Increment
c.Iteration
d.Product backlog
88. A project management team has identified a large number of risks during
its risk identification sessions. It noticed that it would not have the time and
resources to quantitatively analyze all of them. The team also agreed that not all
of these risks would justify the effort necessary to digg deeply into them.
89. A project management team has identified, analyzed and prioritized a great
number of individual project risks and also some overall risks. The team discusses
strategies to respond to them.
What is true for strategies that can be used for individual risks?
c.Only responses for threats can also be used for overall risk.
dOnly responses for opportunities can also be used for overall risk.
90. A project management team has identified, analyzed, prioritized risks and
developed risk responses.
b.Action should be taken to respond to individual risks only. Overall risk can
be escalated.
91. A project has been given into the hands of a contractor and will be
performed against payments by the customer.
During contract development, it has been agreed that the buyer’s procurement
statement of work (SOW) would become an appendix to the contract (CSOW),
turning it into a part of the agreement.
From the contractor’s perspective, which should be among the next steps to
initiate and plan the customer project?
a.The contractor can mostly disregard the SOW, because the language in
the contract’s main document is the binding one for the project.
c.The contractor should regard the requirements laid down in the CSOW as
the only binding ones and focus solely on meeting them during the project.
A question turns up, which risks should be assumed by contractors and which
should remain the responsibility of the customer.
b.Risks should generally remain with the customer to reduce the costs of
outsourcing for the project.
c.Each risk should be accurately allocated to the respective party that is
most capable of managing it.
93. A project management team has identified a large number of sellers who
seem capable to be taken as contractors into the project supply network and
allocated to work items.
a.If they can influence the project, yes. The team should engage them as
stakeholders.
95. A project management team has decided to use an assumptions log for
lower-level tasks and activities in a project to refurbish and modernize an old
business building that should be rented out for upmarket customers.
The actual project work will mostly be done by contractors, and the task of the
project team will be mainly contract development and management and the
coordination of the contractors regarding technical and schedule matters.
In addition to assumptions, what other content may the team capture in the
assumptions log?
a.Project contractors
b.Summary risks
c.Technical risks
d.Constraints
96. A project manager and the project management team have identified a
number of stakeholders for a project to develop and implement a new software
solution that would come with far-reaching changes inside the organization. They
listed them up in a stakeholder register.
97. A project manager is discussing with the project management office the
implementation of risk audits in the project.
a.A risk audit gives the opportunity to verify the completeness of the risk
register and risk report.
b.A risk audit gives the opportunity to validate the existence of a risk
management plan.
c.A risk audit gives the opportunity to consider the effectiveness of the risk
management response strategy.
d.A risk audit gives the opportunity to consider the effectiveness of the
entire risk management process.
a.Project contract
b.Internal agreement
c.Memorandum of understanding
d.Gentlemen agreement
99. A company is writing a job advert to look for a project manager to lead and
direct an urban development project. The mission of the project is to implement a
bold architectural vision. It will be the project manager’s task to ensure that
project work is accomplished through the project’s team members and other
stakeholders.
a.Legal skills.
b.Technical skills.
c.Interpersonal skills.
d.Engineering skills.
When a project manager has been assigned to the project, what should be the
first step to get chartered for the project?