Professional Documents
Culture Documents
Module
Module
Module
03
Quality in Electric Power
Supply—Part II: Indices
and Cost of Power Quality
Justification for Capital
Costs
COST OF OUTAGE
An outage will result in a loss of production and of goods whether in process
or in a finished form as also in a stored stage. It will result in loss of
production partial or complete in some cases. Thus a partly poured casting
will have to be scraped if an outage occurs during pouring.
It will result in loss of wages and other earnings and so on.
BASIS FOR OUTAGE COSTS
These losses will vary from case to case. They will have to be quantified and
brought under a comparable reference base;
1. Loss of a dairy or meat product in an outage of a few seconds will be
negligible. An outage lasting 8 hours could destroy the product (Failure of
cold storage). A common period for collecting the loss data has to be set.
Bases of 20 minutes and of 4 hours seem to be commonly accepted.
2. A customer with a large connected load will incur more losses per outage
of a given period than a customer with a relatively lower connected load.
Figures based on losses kW of customers peak load can become comparable.
These are generally accepted.
3. Similarly a process consuming more energy (kW-Hrs or MW-Hrs) may
report more losses than one using less energy. Losses based on MW-Hr base
can be compared justifiably.
METHODS OF CALCULATING LOSSES
Three methods have been generally accepted for calculating losses:
1. Direct method—ascertaining costs of damages from the party who has
suffered these. Some parties might exaggerate their losses. Average value
may be relied upon.
2. Cost of stand-by equipment maintained by the user to avoid outage losses
may be reduced to a base of his kW's or KVVH and accepted as the cost of
an outage.
3. Rate of decrease method—a customer may be ready to accept an outage
say during a peak hour if he is adequately compensated with a reduction in
d. Reliability indices
A power system in a region may have frequent and prolonged outages.
Industries here will tend to migrate to other regions. On the other hand
another utility has invested adequately and can claim uninterrupted services.
A regulatory commission may decide favorably when this utility asks for an
increase in tariffs as a price for extending a more reliable supply.
How do we define the quality of a service?
Various reliability indices have been evolved. These help to evaluate the
power quality of a utility. These indices have not been accepted universally.
They qualify outages.
The following types of reliability indices are in vogue: (Ref. No. 37)
SAIFI=
system average interruption duration index: (SAIDI)
SAIDI=
customer average interruption frequency index: (CAIFI)
CAIFI=
CAIDI=
ASAI=
The typical values reported in USA are as follows
SAIFI: average 4 customers year,
SAIDI: values varied between 55 minutes to 197 minutes, and
ASAI: lowest- 98.98%, highest- 99.9989%.
Table (1) Costs of Outages Reported for a Canadian Farm Canadian Dollars (Ref. 4
No. 11 @IEEE2000Wacker)
Table (2) Costs of Outages—Offices and Commercial buildings US $ (Ref. No. 32-
2000 Gates)
Table (3) Outages Cost for Large Industrial and Commercial Customers in Nepal
© 2000, IEEE (Pandey, Ref. No. 35)
COST ELEMENT
Production time in hours lost. Work stoppage %.
Table (5) Low Voltage System Classification and Distortion Limits, © 2000, IEEE
Value for An for other than 480 volt systems should be multiplied by V/480
Table (6) Voltage Distortion Limits, © 2000, IEEE (IEEE Std 519, Ref. No. 4)
Table (7) Current Distortion Limits for Genera! Distribution Systems. (120 volts-
through 69000 volts) Maximum Harmonic Current Distortion in Percent of IL
Individual Harmonic Order (Odd Harmonics), © 2000, IEEE (IEEE Std 519, Ref.
No. 4)
COSTING OF HARMONICS
Mr. Emanuel (Ref. No. 14) has done some costing of harmonics on the
utility side. The increase in losses in transformer windings as well as in
feeder conductors was calculated from the skin effect factor for harmonics.
The calculations cover a period of 30 years. They pertain to a transformer
and a feeder. Allowance has been made for yearly increases in a 60 Hz load
along with its reactive load. Similar allowances have been made for
harmonic reactor power and harmonic losses. He has arrived at the following
interesting conclusions:
1. Without capacitors, the harmonic losses remain almost negligible.
2. Capacitors for p.f. improvement tune up harmonics and increase harmonic
losses considerably. However they reduce the 60 Hz losses very
substantially.
3. When capacitors are coupled with series inductances, harmonic losses are
considerably reduced.
4. When active filters are used, the harmonic losses are almost negligible.
For this, the cost of active of filters must be very low.
Table (8) Cumulative Costs of Losses from Year 20 to Year 30, © 2000, IEEE
(Emanuel, Ref. No. 14)
Case 1 : No capacitors. Harmonic losses are 2.5% of 60 Hz losses
Quality in Electric Power Supply—Indices and Cost
Case 2 : Capacitors installed. Harmonic losses increase by 3.78 times.
Actual increase: $564,650.
The 'K' factor can be divided into K Peak and Off-peak to obtain loading
conditions corresponding to peak loads and to off-peak load respectively.
To cite an example, a transformer is loaded to 97.7% when its K was 1.08,
that is, at its rated peak load current. With the actual harmonics measured, it
would be overloaded by 8%. Obviously its operation at 97.7% of its rated
value, has overloaded it.
In almost all the countries, a customer dumping harmonics in a network is
warned and then threatened with disconnection. It so happens that a
customer producing harmonics is the first casualty of the harmonics he
produces. He generally takes care of his harmonics, through suitable filters
suppressors.
'K1 Factor for Capacitors
As per IEC-871-1 and IS:2834 now revised to 15:13925, a capacitor can be
overloaded up to 135% of its rated value, including overloading due to
References
1. Standard for dry type, general purpose power transformers. Underwriters
Laboratories Inc. Standard No. 1561 and 1562 of 1992.
2. "IEEE recommended practices for, establishing transformer capability
when supplying non-sinusoidal load currents". Standard C-57-110, 1986.
3. "Demand and load analysis. Marginal costs and tariff's analysis". Task
report for MSEB SRC International USA, 1995.
4. "IEEE recommended practice and requirements for harmonic control in
electrical power systems". IEEE Stud 519-1992.
5. Modified proposal for revision of tariffs, submitted by Maha-rashtra State
Electricity Board to Maharashtra Electricity Regulatory Commission, 6th
Mar., 2000, pp. 523.
6. Crier, publication no 251, "Guide for limiting voltage harmonics" July,
1996.
7. Economic cost of electricity supply interruptions. US and foreign
experience. A. P. Shanghais. Energy economics, July, 1982, pp. ISO-1998.
8. Interruption costs - methodology and results - A. Canadian residential
survey, Wicker T-PAS, Oct., 1983, pp. 33S5-3392.. A capacitor can stand
this test. However, as explained earlier, its life will be reduced.
The 'K' factor for capacitors has not been investigated.
9. Interruption costs - methodology and results - A Canadian commercial
and small industries survey, Wicker, T-PAS, Feb., 1984, pp. 437-444.
10. Costs of electrical losses. Calculation method, Bodice, T-PWRS, May,
1989, pp. 586-593.
11. Farm costs resulting from random electric supply interruptions. Survey
results, Wackier, T-PWRS, May, 1989, pp. 472-478.
12. US experience with innovative peak load management and pricing
strategies, A. P. Shanghai’s, TERI Conference, 90, Tata McGraw-Hill, p 33.
13. Compressive bibliography on reliability worth and electrical service
consumer interruption costs, Tomlinson, T-PWRS, Nov., • 1991, pp. 1508-
1514.'