Jaurigues Audit Report Midterm

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 57

College of Engineering

BS Mechanical Engineering

ME 302 - ME Elective 2

ENERGY AUDIT REPORT OF PERFERIO


JAURIGUE’S RESIDENCE

LAGUNA UNIVERSITY
Laguna Sports Complex, Bubukal Santa Cruz, 4009, Laguna

In Partial Fulfillment of the Requirements for the Degree


Bachelor of Science in Mechanical Engineering (BSME)

Submitted by:
Ferma, Idmarck
Rebong, Pauline Joy
Piamonte, Joseph Michael
Robles, Kenneth
Salcedo, Jonard

Submitted to:
Engr. Gaious Joe L. Bautista, RME

October 2022
Table of Contents

1. INTRODUCTION ........................................................................................................ 1
1.1 Objectives................................................................................................................. .1

I
College of Engineering
II

BS Mechanical Engineering

2. INTERPRETATION ...........................................................................................…….. 1
3. SUMMARY OF RECOMMENDATIONS........................................................................2
3.1 Description of building ..........................................................................................…..3
3.2 Findings................................................................................................................……5
4. HISTORICAL DATA ANALYSIS ..........................................................................….... 8
4.1 Energy Balance ..............................................................................................…….... 8
APPENDIX C Inventory of all appliances………………….………………………………...9
APPENDIX D Inventory for Door(s)/Window(s)/Room(s)
………………………………………………………………….11
APPENDIX E Computation of Power Consumption Monthly …………………………….12
APPENDIX F Additional Photos / Documentation ………………………………………….13

II
College of Engineering
1

BS Mechanical Engineering

1. INTRODUCTION
1.1 Objectives
The Energy Audit was defined to meet the following objectives:
• Find out what can be done to lower energy use across the board and, if money is
available, what system improvements are feasible.
• Carry out a quick walk-through audit or observation of the energy consumption of the
electrical equipment at the Perferio Jaurigue’s Residence building.
• Identify and evaluate potential tactics for enhancing the buildings'/wards'
environmental performance and offer remedies.

2 . INTERPRETATION
In this report, unless the contrary intention appears;
Energy conservation refers to actions done to decrease and consume as little energy as possible
through adjusting energy consumption behavior, for example. When not in use, turn off lights.
Energy efficiency is defined as utilizing less energy to produce the same service/output, for example.
Changing out inefficient light bulbs for efficient ones.
Faulty meaning that the equipment is not operating properly or was not installed appropriately.
Potential savings refer to the actual decrease in operating expenditures resulting from better energy
efficiency created by an energy conservation or efficiency activity.
Retrofitting is the process of improving the energy efficiency of an existing system.
Tariff refers to the amount of money charged by the supplier (utility) for the usage of electrical
energy per kWh.

3. SUMMARY OF RECOMMENDATIONS
The following are some suggestions based on general observations made across the Perferio
Jaurigue's Residence building.

The recommendations are classifed, with A being the most urgent, requiring immediate action (first
or second week of receiving this report). B might be 1 to 2 months after obtaining this report, whereas
C is dependent on funding availability.

1
College of Engineering
2

BS Mechanical Engineering

Table: Recommendations

Recommendations
Category A Category B Category C
Faulty air conditioners are Dispose of any broken Put energy saving measures
found inside the residence equipment inside the structure. into action, isolate or
(they may be operating, but no disconnect vampire loads
cold air is being expelled), while not in use.
isolate or disconnect them, or
get the air conditioners
serviced once every three
months.
Remove the air conditioner if In places, where air Create internal energy-
the room is truly not properly conditioning is not necessary, saving and efficiency
sealed. use fans. measures for the building.
Replace obsolete outdoor air Techniques for reducing Any incandescent light bulb
conditioners with more energy use include efficiency should be replaced as
efficient ones and conservation initiatives. necessary across the whole
structure. Reduce the number
of lights in each area or get rid
of any that are unnecessary.

3.1 Description of Building

The Perferio Jaurigue's Residence Building is located in Brgy.Sto. Domingo, Calauan,Laguna as


shown on Figure 1a: Perferio Jaurigue's Residence.

Observation: Perferio Jaurigue's Residence Building is constructed in a modern style. The wiring and
electrical outlets were nicely structured, and the electrical system was decent and well-located so that
appliances could be used effectively.
Suggestion: When not in use, please plugged off the appliances to avoid high consumption of power.

(Figure 1: Perferio Jaurigue's Residence in Brgy. Sto. Domingo, Calauan, Laguna)

Suggestion: The appliances should turn off when not needed, that may result to high cost of electrical
consumption.

2
College of Engineering
3

BS Mechanical Engineering

Fig 1: Perferio Jaurigue's Residence building, Brgy. Calauan, Laguna

3.2 FINDINGS

3
College of Engineering
4

BS Mechanical Engineering

3.2.1 Vampire Load/ Ghost Load


Issues/ Observations
- Although they are not performing any useful tasks, appliances in standby mode are
using energy.
- Both defective light fixtures with intact bulbs and defective light fixtures with intact
bulbs are used include vampire loads as well.
- All electrical equipment and appliances cords and wires knotting can affect the electronics
performance.
Recommendations
- When not in use, electrical devices should be unplugged.
- Faulty lights ought to be taken out.
- Ensure that the cords and wires are always dry, spotless, and free of knots.

3.2.2 Lighting
The most frequent load in both indoor and outdoor spaces is lighting. Below are a few
the following features and flaws were found:

i. Findings of lightnings
Issues/Observation
- There are too many lights connected to one switch.
- Based on our observations, there are too many unnecessary lights in a room that
consumpt too much energy.
Recommendations
- To better manage illumination, reduce the number of lights per switch.
- Decrease the quantity of lights in each space.
- When not in use, turn off the lights.

3.2.3 Air Conditioning


i. Air Conditioning Management

4
College of Engineering
5

BS Mechanical Engineering

Issues/Observation
- When entering and leaving the room where the air conditioner is, person in the room leave
the door open.
- The airconditioner's brand and model are inconsistent (not inverter type), which
makes maintenance expensive.
- The doors and windows they used in an air- conditioning room is highly advisable.
Recommendations
- When entering or leaving an air-conditioned room, always shut the door.
- Turn off while not in use, but don't lower the temperature, and keep it on.
- In the event that the air conditioner is not running, try to get some fresh air outside
entirely to reduce the price of electricity.
- At least two or three maintenance visits should be made to every installed air conditioner.
- When possible, switch to an electric fan.

5
College of Engineering
6

BS Mechanical Engineering

4. Historical Data Analysis


4.1 Energy Balance
Latest Power Consumption Data for the Perferio Jaurigue’s Building ( July - October Billing)

MONTH POWER CONSUMPTION MONTHLY BILL


(kWh/Month)

JULY 383kWh P4,259.34

AUGUST 312kWh P3,253.67

SEPTEMBER 289kWh P2,639.74

OCTOBER

TOTAL 993kWh P10,152.73

6
College of Engineering
7

BS Mechanical Engineering

APPENDIX C - INVENTORY OF ALL APPLIANCES

APPLIANCES QUANTITY DESCRIPT RATED USAGE PER USAGE


ION POWER DAY DAYS PER
MONTH

AIRCON 2 Markes 930 W 9 Hrs 30 days


Window
Type aircon

ELECTRIC 2 2 hanabishi 50 W 10 Hrs 30 days


FAN stand fan

REFRIGERAT 1 Kelvinator 145 W 24 Hrs 30 days


OR

T.V 1 Sharp LED 85 W 3 - 4 Hrs 30 days


TV

LIGHT BULBS 6 3 Omni LED 6W 10 hrs 30 days


lights
1 Firefly
LED
2 Akari LED
lights

RICE 1 Standard 300 W 1 hrs 30 days


COOKER Rice Cooker

Exhaust fan 1 15 W 5 hrs 30 days

LED Ceiling 2 18 W 10 HRS 30 Days


light (round)

Turbo 1 1200 W

7
College of Engineering
8

BS Mechanical Engineering

Appendix D - Inventories for Door(s), Window(s) and Room Dimensions


Day 1
BEDROOM 1
DOOR = 1
WINDOW - 0 (Bedroom 1 have no window(s)
ROOM Dimension -
Side 1 = 2.5 x 2.60 = 6.50 m^2

8
College of Engineering
9

BS Mechanical Engineering

Side 2 = 2.5 x 2.60 = 6.50 m^2


Side 3 = 1.77 x 2.60 = 4.602 m^2
Side 4 = 1.77 x 2.60 = 4.602 m^2
Roof = 2.5 x 1.77 = 4.425 m^2
Floor = 2.5 x 1.77 = 4.425 m^2
SARI-SARI STORE
DOOR - 1
WINDOW ( converted into store)
DIMENSION
Side 1 = 2.35 x 1.5 = 3.525 m^2
Side 2 = 2.35 x 1.5 = 3.525 m^2
Side 3 = 2.0 x 1.5 = 3 m^2
Side 4 = 2.0 x 1.5 = 3 m^2
Roof = 2.35 x 2.0 = 4.7 m^2
Floor = 2.35 x 2.0 = 4.7 m^2
SALA
DOOR - 1
WINDOW - 1
DIMENSION
Side 1 = 2.65 x 2.5 = 6.625 m^2
Side 2 = 2.65 x 2.5 = 6.625 m^2
Side 3 = 2.45 x 2.5 = 6.125 m^2
Side 4 = 2.45 x 2.5 = 6.125 m^2
Roof = 2.65 x 2.45 = 6.4925 m^2
Floor = 2.65 x 2.45 = 6.4925 m^2
DINING / KITCHEN
DOOR -

9
College of Engineering
10

BS Mechanical Engineering

WINDOW -
DIMENSION/AREA
Side 1 = 3.25 x 2.60 = 8.45 m^2
Side 2 = 3.25 x 2.60 = 8.45 m^2
Side 3 = 2.55 x 2.60 = 6.63 m^2
Side 4 = 2.55 x 2.60 = 6.63 m^2
Roof = 3.25 x 2.55 = 8.2875 m^2
Floor = 3.25 x 2.55 = 8.2875 m^2
A. Transmission Load

BEDROOM 1
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 26.629 m^2 x (32C - 21C) x 24 ÷ 1000
Q = 3.866 kWh/Day
Floor
Q = 0.55 x 8.2875 m^2 x ( 32C - 21C) x 24 ÷ 1000
Q = 1.2033 kWh/Day
Total daily transmission heat gain = 3.866 + 1.2033 = 5.0693 kWh/Day

Internal heat load – People


Q = people x time x heat / 1000
Q = 3 x 9 x 150 / 1000
Q = 4.05 kWh/Day
Internal heat load – Lighting
Q= lamps x time x wattage / 1000
Q = 6 x 10 x 6 / 1000
Q = 0.36 kWh/Day

10
College of Engineering
11

BS Mechanical Engineering

Equipment load – fan motors


Q = fans x time x wattage / 1000
Q = 2 x 15 x 65 / 1000
Q = 1.95 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 10 x 17.5 x 1.2 x (32C - 20) / 3600
Q = 0.7 kWh/ Day
Total cooling load
Transmission load: 5.0693 kWh/Day
Internal load: 4.41 kWh/Day
Equipment load: 1.95 kWh/Day
Infiltration load: 0.7 kWh/ Day
TOTAL = 12.1293 kWh/Day
SARI-SARI STORE
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 17.75 x ( 32 - 20 ) x 24 / 1000
Q = 2.8116 kWh/Day
Floor
Q = 0.55 x 4.7 x ( 32 -20 ) x 24 / 1000
Q = 0.7445 kWh/Day
Total daily transmission heat gain = 2.8166 + 0.7445 = 3.5611 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 3 x 9 x 150 / 1000
Q = 4.05 kWh/Day

11
College of Engineering
12

BS Mechanical Engineering

Internal heat load – Lighting


Q= lamps x time x wattage / 1000
Q = 6 x 10 x 6 / 1000
Q = 0.36 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 15 x 65 / 1000
Q = 1.95 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 10 x 17.5 x 1.2 x (32C - 20) / 3600
Q = 0.7 kWh/ Day
Total cooling load
Transmission load: 3.5611 kWh/Day
Internal load: 4.41 kWh/Day
Equipment load: 1.95 kWh/Day
Infiltration load: 0.7 kWh/ Day
TOTAL = 10.6211 kWh/Day
SALA
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 31.9925 x ( 32 - 20 ) x 24 /1000
Q = 5.0676 kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 6.4925 x ( 32 - 20 ) x 24 / 1000
Q = 1.028 kWh/Day

12
College of Engineering
13

BS Mechanical Engineering

Total daily transmission heat gain = 5.0676 + 1.028 = 6.0956 kWh/Day


Internal heat load – People
Q = people x time x heat / 1000
Q = 3 x 9 x 150 / 1000
Q = 4.05 kWh/Day
Internal heat load – Lighting
Q= lamps x time x wattage / 1000
Q = 6 x 10 x 6 / 1000
Q = 0.36 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 15 x 65 / 1000
Q = 1.95 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 10 x 17.5 x 1.2 x (32C - 20) / 3600
Q = 0.7 kWh/ Day
Total cooling load
Transmission load: 6.0956 kWh/Day
Internal load: 4.41 kWh/Day
Equipment load: 1.95 kWh/Day
Infiltration load: 0.7 kWh/ Day
TOTAL = 12.8556 kWh/Day
KITCHEN
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 38.4475 x ( 32- 20) x 24 / 1000

13
College of Engineering
14

BS Mechanical Engineering

Q = 6.090 kWh/Day
Floor
Q = 0.55 x 8.2875 x ( 32 - 20 ) x 24 / 1000
Q = 1.312 kWh/Day
Total daily transmission heat gain = 6.090 + 1.312 = 7.402 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 3 x 9 x 150 / 1000
Q = 4.05 kWh/Day
Internal heat load – Lighting
Q= lamps x time x wattage / 1000
Q = 6 x 10 x 6 / 1000
Q = 0.36 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 15 x 65 / 1000
Q = 1.95 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 10 x 17.5 x 1.2 x (32C - 20) / 3600
Q = 0.7 kWh/ Day
Total cooling load
Transmission load: 7.402 kWh/Day
Internal load: 4.41 kWh/Day
Equipment load: 1.95 kWh/Day
Infiltration load: 0.7 kWh/ Day
TOTAL = 14.462 kWh/Day

14
College of Engineering
15

BS Mechanical Engineering

DAY 2
BEDROOM
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 26.625 x ( 30 - 19 ) x 24 / 1000
Q = 3.8659 kWh/Day
Floor
Q = 0.55 x 4.425 x ( 30 - 19 ) x 24 / 1000
Q = 0.6425 kWh/Day
Total daily transmission heat gain = 3.8659 + 0.6425 = 4.5084 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 4 x 8 x 200 / 1000
Q = 6.4 kWh/Day
Internal heat load – Lighting
Q= lamps x time x wattage / 1000
Q = 6 x 8 x 6 / 1000
Q = 0.288 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 8 x 65 / 1000
Q = 1.04 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 10 x 15 x 1.2 x ( 30 - 19 ) / 1000
Q = 1.98 kWh/Day
Total cooling load

15
College of Engineering
16

BS Mechanical Engineering

Transmission load: 4.5084 kWh/Day


Internal load : 6.688 kWh/Day
Equipment load : 1.04 kWh/Day
Infiltration load : 1.98 kWh/Day
TOTAL : 14.2164 kWh/Day
SARI-SARI STORE
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 17.75 x ( 30 - 19 ) x 24 / 1000
Q = 2.5773 kWh/Day
Floor
Q = 0.55 x 4.7 x ( 30 -19 ) x 24 / 1000
Q = 0.68244 kWh/Day
Total daily transmission heat gain = 2.5773 + 0.68244 = 3.2597 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 1 x 8 x 200 / 1000
Q = 1.6 kWh/Day
Internal heat load – Lighting
Q= lamps x time x wattage / 1000
Q = 6 x 8 x 6 / 1000
Q = 0.288 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 8 x 65 / 1000
Q = 1.04 kWh/Day
Infiltration load

16
College of Engineering
17

BS Mechanical Engineering

Q = changes x volume x energy x (Temp out – Temp in ) / 3600


Q = 10 x 15 x 1.2 x ( 30 - 19 ) / 1000
Q = 1.98 kWh/Day
Total cooling load
Transmission load : 3.2397 kWh/Day
Internal load : 1.888 kWh/Day
Equipment load : 1.04 kWh/Day
Infiltration load : 1.98 kWh/Day
TOTAL : 8.1677 kWh/Day
SALA
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 31.9925 x ( 30 - 19 ) x 24 / 1000
Q = 4.645 kWh/Day
Floor
Q = 0.55 x 6.4925 x ( 30 - 19) x 24 /1000
Q = 0.9427 kWh/Day
Total daily transmission heat gain = 4.645 + 0.9427 =
Internal heat load – People
Q = people x time x heat / 1000
Q = 1 x 8 x 200 / 1000
Q = 1.6 kWh/Day
Internal heat load – Lighting
Q= lamps x time x wattage / 1000
Q = 6 x 8 x 6 / 1000
Q = 0.288 kWh/Day
Equipment load – fan motors

17
College of Engineering
18

BS Mechanical Engineering

Q = fans x time x wattage / 1000


Q = 2 x 8 x 65 / 1000
Q = 1.04 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 10 x 15 x 1.2 x ( 30 - 19 ) / 1000
Q = 1.98 kWh/Day
Total cooling load
Transmission load : 5.5877 kWh/Day
Internal load : 1.888 kWh/Day
Equipment load : 1.04 kWh/Day
Infiltration load : 1.98 kWh/Day
TOTAL : 10.4957 kWh/Day
KITCHEN
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 38.4475 x ( 30 - 19 ) x 24 / 1000
Q = 5.825 kWh/Day
Floor
Q = 0.55 x 8.2875 x ( 30-19) x 24 / 1000
Q = 1.2033 kWh/Day
Total daily transmission heat gain = 5.825 + 1.2033 = 7.028 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 4 x 8 x 200 / 1000
Q = 6.4 kWh/Day
Internal heat load – Lighting

18
College of Engineering
19

BS Mechanical Engineering

Q= lamps x time x wattage / 1000


Q = 6 x 8 x 6 / 1000
Q = 0.288 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 8 x 65 / 1000
Q = 1.04 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 10 x 15 x 1.2 x ( 30 - 19 ) / 1000
Q = 1.98 kWh/Day
Total cooling load
Transmission load = 7.028 kWh/Day
Internal load = 6.688 kWh/Day
Equipment load = 1.04 kWh/Day
Infiltration load = 1.98 kWh/Day
TOTAL = 16.726 kWh/Day
DAY 3
BEDROOM
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 26.629 x ( 33 - 21 ) x 24 / 1000
Q = 4.2180 kWh/Day
Floor
Q = 0.55x 4.425 x ( 33 - 21 ) x 24 / 1000
Q = 0.701 kWh/Day
Total daily transmission heat gain = 4.2180 + 0.701 = 4.919 kWh/Day

19
College of Engineering
20

BS Mechanical Engineering

Internal heat load – People


Q = people x time x heat / 1000
Q = 3 x 8 x 200 / 1000
Q = 4.8 kWh/Day
Internal heat load – Lighting
Q= lamps x time x wattage / 1000
Q = 6 x 8 x 6 / 1000
Q = 0.288 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 8 x 65 / 1000
Q = 1.04 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 10 x 16 x 1.3 x ( 33-21) / 3600
Q = 0.693 kWh/Day
Total cooling load
Transmission load : 4.919 kWh/Day
Internal load : 5.088 kWh/Day
Equipment load : 1.04 kWh/Day
Infiltration load : 0.693 kWh/Day
TOTAL : 11.74 kWh/Day
SARI-SARI STORE
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 3 x 17.75 x ( 33-21) x 24 / 1000
Q = 15.336 kWh/Day

20
College of Engineering
21

BS Mechanical Engineering

Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 4.7 x (33-21) x 24 / 1000
Q = 4.061 kWh/Day
Total daily transmission heat gain = 15.336 + 4.061 = 19.3968 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 3 x 8 250 / 1000
Q = 6 kWh/Day
Internal heat load – Lighting
Q= lamps x time x wattage / 1000
Q = 6 x 10 x 6 / 1000
Q = 0.36 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 8 x 65 / 1000
Q = 1.04 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 10 x 15 x 1.2 x (33-21) / 3600
Q = 0.9kWh/Day
Total cooling load
Transmission load = 19.3968 kWh/Day
Internal load = 6.63 kWh/Day
Equipment load = 1.04 kWh/Day
Infiltration load = 0.9 kWh/Day
TOTAL = 27.9668 kWh/Day

21
College of Engineering
22

BS Mechanical Engineering

SALA
Transmission Load
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 31.9925 x ( 33-21) x 24 / 1000
Q = 5.0676 kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 6.4925 x ( 33-21) x 24 / 1000
Q = 1.0284 kWh/Day
Total daily transmission heat gain = 5.0676 + 1.0284 = 6.0960 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 3 x 8 250 / 1000
Q = 6 kWh/Day
Internal heat load – Lighting
Q= lamps x time x wattage / 1000
Q = 6 x 10 x 6 / 1000
Q = 0.36 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 8 x 65 / 1000
Q = 1.04 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 10 x 15 x 1.2 x (33-21) / 3600
Q = 0.9kWh/Day

22
College of Engineering
23

BS Mechanical Engineering

Total cooling load


Transmission load = 6.0960 kWh/Day
Internal load = 6.63 kWh/Day
Equipment load = 1.04 kWh/Day
Infiltration load = 0.9 kWh/Day
TOTAL = 14.666 kWh/Day
KITCHEN
Transmission Load
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 38.4475 x (33-21) x 24 / 1000
Q + 39.2855 kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 8.2875 x ( 33-21) x 24 / 1000
Q = 9.1255 kWh/Day
Total daily transmission heat gain = 39.2855 + 9.1255 = 48.411 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 3 x 8 250 / 1000
Q = 6 kWh/Day
Internal heat load – Lighting
Q= lamps x time x wattage / 1000
Q = 6 x 10 x 6 / 1000
Q = 0.36 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000

23
College of Engineering
24

BS Mechanical Engineering

Q = 2 x 8 x 65 / 1000
Q = 1.04 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 10 x 15 x 1.2 x (33-21) / 3600
Q = 0.9kWh/Day
Total cooling load
Transmission load = 48.411 kWh/Day
Internal load = 6.63 kWh/Day
Equipment load = 1.04 kWh/Day
Infiltration load = 0.9 kWh/Day
TOTAL = 56.711 kWh/Day
DAY 4
Bedroom
Transmission load
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 26.629 x (33-22) x 24 / 1000
Q = 3.866kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 4.425 x ( 33-22) x 24 / 1000
Q = 0.64251 kWh/Day
Total daily transmission heat gain = 3.866+ 0.64251 = 4.5085 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 2 x 5 x 250 / 1000

24
College of Engineering
25

BS Mechanical Engineering

Q = 2.5 kWh/Day
Internal heat load – Lighting
Q= lamps x time x wattage / 1000
Q = 6 x 5 X 6 / 1000
Q = 0.18 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 5 x 65 / 1000
Q = 0.65 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 10 x 15 x 1.2 x ( 33-22)/ 3600
Q = 0.55 kWh/Day
Total cooling load
Transmission load = 4.5085 kWh/Day
Internal load = 2.68 kWh/Day
Equipment load = 0.65 kWh/Day
Infiltration load = 0.55 kWh/Day
TOTAL = 8.3885 kWh/Day
Sari-Sari Store
Transmission Load
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 17.75 x ( 33-22) x 24 / 1000
Q = 2.5773 kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000

25
College of Engineering
26

BS Mechanical Engineering

Q = 0.55 x 4.7 x ( 33-22) x 24 /1000


Q = 0.682kWh/Day
Total daily transmission heat gain = 2.5773 + 0.682 = 3.2597 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 4 x 11 x 220 / 1000
Q = 9.68 kWh/Day
Internal heat load – Lighting
Q = lamps x time x wattage / 1000
Q = 6 x 11 x 6 / 1000
Q = 0.396 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 11 x 65 / 1000
Q = 1.43 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 10 x 15 x 1.2 x ( 33-22)/ 3600
Q = 0.55 kWh/Day
Total cooling load
Transmission load = 3.2597 kWh/Day
Internal load = 10.076 kWh/Day
Equipment load = 1.43 kWh/Day
Infiltration load = 0.55 kWh/Day
TOTAL = 15.3157 kWh/Day
SALA
Transmission load

26
College of Engineering
27

BS Mechanical Engineering

Walls and Roof


Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 31.9925 x ( 33-22) x 24 / 1000
Q = 4. 6453 kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 6.4925 x ( 33-22) x 24 / 1000
Q = 0.942 kWh/Day
Total daily transmission heat gain = 4.6453 + 0.942 = 5.5880 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 4 x 11 x 220 / 1000
Q = 9.68 kWh/Day
Internal heat load – Lighting
Q = lamps x time x wattage / 1000
Q = 6 x 11 x 6 / 1000
Q = 0.396 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 11 x 65 / 1000
Q = 1.43 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 10 x 15 x 1.2 x ( 33-22)/ 3600
Q = 0.55 kWh/Day
Total Cooling load
Transmission load = 5.5880 kWh/Day

27
College of Engineering
28

BS Mechanical Engineering

Internal load = 10.076 kWh/Day


Equipment load = 1.43 kWh/Day
Infiltration load = 0.55 kWh/Day
TOTAL = 17.644 kWh/Day
KITCHEN
Transmission Load
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 38.4475 x ( 33-22) x 24 / 1000
Q = 5.5825 kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 8.2875 x ( 33-22) x 24 / 1000
Q = 1.2033 kWh/Day
Total daily transmission heat gain = 5.5825 + 1.2033 = 6.785 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 4 x 11 x 220 / 1000
Q = 9.68 kWh/Day
Internal heat load – Lighting
Q = lamps x time x wattage / 1000
Q = 6 x 11 x 6 / 1000
Q = 0.396 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 11 x 65 / 1000
Q = 1.43 kWh/Day

28
College of Engineering
29

BS Mechanical Engineering

Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 10 x 15 x 1.2 x ( 33-22)/ 3600
Q = 0.55 kWh/Day
Total Cooling load
Transmission load =6.785 kWh/Day
Internal load = 10.076 kWh/Day
Equipment load = 1.43 kWh/Day
Infiltration load = 0.55 kWh/Day
TOTAL = 18.841 kWh/Day
DAY 5
BEDROOM
Transmission load
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 26.629 x ( 34-20 ) x 24 /1000
Q = 4.9210 kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 4.425 x ( 34-20) x 24 / 1000
Q = 0.8177 kWh/Day
Total daily transmission heat gain = 5.7387 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 2 x 10 x 200 / 1000
Q = 4 kWh/Day
Internal heat load – Lighting

29
College of Engineering
30

BS Mechanical Engineering

Q = lamps x time x wattage / 1000


Q = 6 x 10 x 6 / 1000
Q = 0.36 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 10 x 65 / 1000
Q = 1.3 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 11 x 16 x 1.3 x ( 34-20 ) /3600
Q = 0.889 kWh/Day
Total Cooling load
Transmission load = 5.7387 kWh/Day
Internal load = 4.36 kWh/Day
Equipment load = 1.3 kWh/Day
Infiltration load = 0.889 kWh/Day
TOTAL = 12.2877 kWh/Day
SARi-SARI STORE
Transmission load
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 17.75 x ( 34-20) x 24 / 1000
Q = 3.2802 kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 4.7 x ( 34-20) x 24 / 1000
Q = 0.8685 kWh/Day

30
College of Engineering
31

BS Mechanical Engineering

Total daily transmission heat gain = 4.1487 kWh/Day


Internal heat load – People
Q = people x time x heat / 1000
Q = 2 x 10 x 200 / 1000
Q = 4 kWh/Day
Internal heat load – Lighting
Q = lamps x time x wattage / 1000
Q = 6 x 10 x 6 / 1000
Q = 0.36 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 10 x 65 / 1000
Q = 1.3 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 11 x 16 x 1.3 x ( 34-20 ) /3600
Q = 0.889 kWh/Day
Total Cooling load
Transmission load = 4.1487 kWh/Day
Internal load = 4.36 kWh/Day
Equipment load = 1.3 kWh/Day
Infiltration load = 0.889 kWh/Day
TOTAL = 10.6977 kWh/Day
SALA
Transmission load
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000

31
College of Engineering
32

BS Mechanical Engineering

Q = 0.55 x 31.9925 x ( 34-20) x 24 / 1000


Q = 5.9122 kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 6.4925 x ( 34-20) x 24 / 1000
Q = 1.1998 kWh/Day
Total daily transmission heat gain = 7.1120 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 2 x 10 x 200 / 1000
Q = 4 kWh/Day
Internal heat load – Lighting
Q = lamps x time x wattage / 1000
Q = 6 x 10 x 6 / 1000
Q = 0.36 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 10 x 65 / 1000
Q = 1.3 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 11 x 16 x 1.3 x ( 34-20 ) /3600
Q = 0.889 kWh/Day
Total Cooling load
Transmission load = 7.1120 kWh/Day
Internal load = 4.36 kWh/Day
Equipment load = 1.3 kWh/Day

32
College of Engineering
33

BS Mechanical Engineering

Infiltration load = 0.889 kWh/Day


TOTAL = 13.661 kWh/Day
KITCHEN
Transmission load
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 38.4475 x (34-20) x 24 / 1000
Q = 7.1050 kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 8.2875 x ( 34-20) x 24 / 1000
Q = 1.5315 kWh/Day
Total daily transmission heat gain = 8.6365 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 2 x 10 x 200 / 1000
Q = 4 kWh/Day
Internal heat load – Lighting
Q = lamps x time x wattage / 1000
Q = 6 x 10 x 6 / 1000
Q = 0.36 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 10 x 65 / 1000
Q = 1.3 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600

33
College of Engineering
34

BS Mechanical Engineering

Q = 11 x 16 x 1.3 x ( 34-20 ) /3600


Q = 0.889 kWh/Day
Total Cooling load
Transmission load = 8.6365 kWh/Day
Internal load = 4.36 kWh/Day
Equipment load = 1.3 kWh/Day
Infiltration load = 0.889 kWh/Day
TOTAL = 15.1875 kWh/Day
DAY 6
BEDROOM
Transmission load
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 26.629 x ( 31-19) x 24 / 1000
Q = 4.218 kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 4.425 x (31-19) x 24 / 1000
Q = 0.7001 kWh/Day
Total daily transmission heat gain = 4.1989 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 3 x 7 x 230 / 1000
Q = 4.83 kWh/Day
Internal heat load – Lighting
Q = lamps x time x wattage / 1000
Q = 6 x 7 x 6 / 1000

34
College of Engineering
35

BS Mechanical Engineering

Q = 0.252 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 7 x 65 /1000
Q = 0.91 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 12 x 16 x 1.5 x ( 31-19) /3600
Q = 192.018kWh/Day
Total Cooling load
Transmission load = 4.9189kWh/Day
Internal load = 5.082 kWh/Day
Equipment load = 0.91 kWh/Day
Infiltration load = 192.018 kWh/Day
TOTAL = 202.92 kWh/Day
SARI-SARI STORE
Transmission load
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 17.75 x ( 31-19) x 24 /1000
Q = 2.8116 kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 4.425 x ( 31-19) x 24 /1000
Q = 0.7009 kWh/Day
Total daily transmission heat gain = 3.5125 kWh/Day
Internal heat load – People

35
College of Engineering
36

BS Mechanical Engineering

Q = people x time x heat / 1000


Q = 3 x 7 x 230 / 1000
Q = 4.83 kWh/Day
Internal heat load – Lighting
Q = lamps x time x wattage / 1000
Q = 6 x 7 x 6 / 1000
Q = 0.252 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 7 x 65 /1000
Q = 0.91 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 12 x 16 x 1.5 x ( 31-19) /3600
Q = 192.018kWh/Day
Total Cooling load
Transmission load = 3.5125kWh/Day
Internal load = 5.082 kWh/Day
Equipment load = 0.91 kWh/Day
Infiltration load = 192.018 kWh/Day
TOTAL = 201.5225 kWh/Day
SALA
Transmission load
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55x 31.9925 x ( 31-19) x 24 /1000
Q = 5.0676 kWh/Day

36
College of Engineering
37

BS Mechanical Engineering

Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q =0.55 x 6.4925 x ( 31-19) x 24 / 1000
Q = 1.0284 kWh/Day
Total daily transmission heat gain = 6.096 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 3 x 7 x 230 / 1000
Q = 4.83 kWh/Day
Internal heat load – Lighting
Q = lamps x time x wattage / 1000
Q = 6 x 7 x 6 / 1000
Q = 0.252 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 7 x 65 /1000
Q = 0.91 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 12 x 16 x 1.5 x ( 31-19) /3600
Q = 192.018kWh/Day
Total Cooling load
Transmission load = 6.096kWh/Day
Internal load = 5.082 kWh/Day
Equipment load = 0.91 kWh/Day
Infiltration load = 192.018 kWh/Day
TOTAL = 204.106 kWh/Day

37
College of Engineering
38

BS Mechanical Engineering

KITCHEN
Transmission load
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 38.4475x (31-19)x 24 /1000
Q = 6.0901 kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 8.2875 x ( 31-19) x 24 / 1000
Q = 1.3127 kWh/Day
Total daily transmission heat gain = 7.4028 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 3 x 7 x 230 / 1000
Q = 4.83 kWh/Day
Internal heat load – Lighting
Q = lamps x time x wattage / 1000
Q = 6 x 7 x 6 / 1000
Q = 0.252 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 7 x 65 /1000
Q = 0.91 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 12 x 16 x 1.5 x ( 31-19) /3600
Q = 192.018kWh/Day

38
College of Engineering
39

BS Mechanical Engineering

Total Cooling load


Transmission load = 7.4028kWh/Day
Internal load = 5.082 kWh/Day
Equipment load = 0.91 kWh/Day
Infiltration load = 192.018 kWh/Day
TOTAL = 205.413 kWh/Day
DAY 7
BEDROOM
Transmission load
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 26.629 x ( 33-18) x 24 / 1000
Q = 5.2725 kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x4.425 x ( 33-18) x 24 / 1000
Q = 0.8761 kWh/Day
Total daily transmission heat gain = 6.1486 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 2 x 7 x 200 /1000
Q = 2.8 kWh/Day
Internal heat load – Lighting
Q = lamps x time x wattage / 1000
Q = 6 x 7 x 6 / 1000
Q= 0.252 kWh/Day
Equipment load – fan motors

39
College of Engineering
40

BS Mechanical Engineering

Q = fans x time x wattage / 1000


Q = 2 x 7 x 65 /1000
Q = 0.91 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 11 x 15 x 1.2 x ( 33-18) /3600
Q = 0.825 kWh/Day
Total Cooling load
Transmission Load = 6.1486 kWh/Day
Internal Load = 3.052 kWh/Day
Equipment load = 0.91 kWh/Day
Infiltration load = 0.825 kWh/Day
TOTAL = 10.9356 kWh/Day
SARI-SARI Store
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 17.75 x ( 33-18 ) x 24 /1000
Q = 3.5145 kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 4.7 x ( 33-18) x 24 / 1000
Q = 0.9306 kWh/Day
Total daily transmission heat gain = 4.4451 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 2 x 7 x 200 /1000
Q = 2.8 kWh/Day

40
College of Engineering
41

BS Mechanical Engineering

Internal heat load – Lighting


Q = lamps x time x wattage / 1000
Q = 6 x 7 x 6 / 1000
Q= 0.252 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 7 x 65 /1000
Q = 0.91 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 11 x 15 x 1.2 x ( 33-18) /3600
Q = 0.825 kWh/Day
Total Cooling load
Transmission Load =4.4451 kWh/Day
Internal Load = 3.052 kWh/Day
Equipment load = 0.91 kWh/Day
Infiltration load = 0.825 kWh/Day
TOTAL = 9.2321 kWh/Day
SALA
Transmission load
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 31.9925 x ( 33-18 ) x 24 / 1000
Q = 6.3345 kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 6.4925 x ( 33-18) x 24 /1000

41
College of Engineering
42

BS Mechanical Engineering

Q = 1.2855 kWh/Day
Total daily transmission heat gain = 7.6200 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 2 x 7 x 200 /1000
Q = 2.8 kWh/Day
Internal heat load – Lighting
Q = lamps x time x wattage / 1000
Q = 6 x 7 x 6 / 1000
Q= 0.252 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 7 x 65 /1000
Q = 0.91 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 11 x 15 x 1.2 x ( 33-18) /3600
Q = 0.825 kWh/Day
Total Cooling load
Transmission Load = 7.6200 kWh/Day
Internal Load = 3.052 kWh/Day
Equipment load = 0.91 kWh/Day
Infiltration load = 0.825 kWh/Day
TOTAL = 12.407 kWh/Day
KITCHEN
Transmission load
Walls and Roof

42
College of Engineering
43

BS Mechanical Engineering

Q = U x A x (Temp out – Temp in) x 24 ÷ 1000


Q = 0.55 x 38.4475 x ( 33-18) x 24 / 1000
Q = 7.6126 kWh/day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 8.2875 x ( 33-18) x 24 / 1000
Q = 1.6409 kWh/Day
Total daily transmission heat gain = 9.2535 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 2 x 7 x 200 /1000
Q = 2.8 kWh/Day
Internal heat load – Lighting
Q = lamps x time x wattage / 1000
Q = 6 x 7 x 6 / 1000
Q= 0.252 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 7 x 65 /1000
Q = 0.91 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 11 x 15 x 1.2 x ( 33-18) /3600
Q = 0.825 kWh/Day
Total Cooling load
Transmission Load = 9.2535 kWh/Day
Internal Load = 3.052 kWh/Day

43
College of Engineering
44

BS Mechanical Engineering

Equipment load = 0.91 kWh/Day


Infiltration load = 0.825 kWh/Day
TOTAL = 14.0405 kWh/Day
DAY 8
BEDROOM
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 26.629 x ( 35-23 ) x 24 / 1000
Q = 4.218 kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 4.425 x ( 35-23) x 24 / 1000
Q = 0.7009 kWh/Day
Total daily transmission heat gain = 4.9189 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 4 x 12 x 250 / 1000
Q = 12 kWh/Day
Internal heat load – Lighting
Q = lamps x time x wattage / 1000
Q = 6 x 12 x 65 / 1000
Q = 4.68 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 12 x 65 / 1000
Q = 1.56 kWh/Day
Infiltration load

44
College of Engineering
45

BS Mechanical Engineering

Q = changes x volume x energy x (Temp out – Temp in ) / 3600


Q = 12 x 15 x 1.2 x ( 35-23) /3600
Q = 0.72 kWh/Day
Total Cooling load
Transmission Load = 4.9189 kWh/Day
Internal load = 16.68 kWh/Day
Equipment load = 1.56 kWh/Day\
Infiltration load = 0.72 kWh/Day
TOTAL = 23.8789 kWh/Day
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 17.75 x ( 35-23) x 24 / 1000
Q = 2.8116 kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 4.7 x ( 35-23) x 24 / 1000
Q = 0.7445 kWh/Day
Total daily transmission heat gain = 3.5561 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 4 x 12 x 250 / 1000
Q = 12 kWh/Day
Internal heat load – Lighting
Q = lamps x time x wattage / 1000
Q = 6 x 12 x 65 / 1000
Q = 4.68 kWh/Day
Equipment load – fan motors

45
College of Engineering
46

BS Mechanical Engineering

Q = fans x time x wattage / 1000


Q = 2 x 12 x 65 / 1000
Q = 1.56 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 12 x 15 x 1.2 x ( 35-23) /3600
Q = 0.72 kWh/Day
Total Cooling load
Transmission Load = 3.5561 kWh/Day
Internal load = 16.68 kWh/Day
Equipment load = 1.56 kWh/Day\
Infiltration load = 0.72 kWh/Day
TOTAL = 22.5161 kWh/Day
SALA
Transmission load
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 31.9925 x ( 35-23) x 24 / 1000
Q = 5.076 kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 6.925 x ( 35-23) x 24 / 1000
Q = 1.096 kWh/Day
Total daily transmission heat gain = 6.1645 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 4 x 12 x 250 / 1000

46
College of Engineering
47

BS Mechanical Engineering

Q = 12 kWh/Day
Internal heat load – Lighting
Q = lamps x time x wattage / 1000
Q = 6 x 12 x 65 / 1000
Q = 4.68 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 12 x 65 / 1000
Q = 1.56 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 12 x 15 x 1.2 x ( 35-23) /3600
Q = 0.72 kWh/Day
Total Cooling load
Transmission Load = 6.1645 kWh/Day
Internal load = 16.68 kWh/Day
Equipment load = 1.56 kWh/Day\
Infiltration load = 0.72 kWh/Day
TOTAL = 25.1245 kWh/Day
KITCHEN
Transmission Load
Walls and Roof
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000
Q = 0.55 x 38.4475 x ( 35-23) x 24 /1000
Q = 6.0900 kWh/Day
Floor
Q = U x A x (Temp out – Temp in) x 24 ÷ 1000

47
College of Engineering
48

BS Mechanical Engineering

Q = 0.55 x 8.2875 x ( 35-23) x 24 / 1000


Q = 1.3127 kWh/Day
Total daily transmission heat gain = 7.4027 kWh/Day
Internal heat load – People
Q = people x time x heat / 1000
Q = 4 x 12 x 250 / 1000
Q = 12 kWh/Day
Internal heat load – Lighting
Q = lamps x time x wattage / 1000
Q = 6 x 12 x 65 / 1000
Q = 4.68 kWh/Day
Equipment load – fan motors
Q = fans x time x wattage / 1000
Q = 2 x 12 x 65 / 1000
Q = 1.56 kWh/Day
Infiltration load
Q = changes x volume x energy x (Temp out – Temp in ) / 3600
Q = 12 x 15 x 1.2 x ( 35-23) /3600
Q = 0.72 kWh/Day
Total Cooling load
Transmission Load =7.4027 kWh/Day
Internal load = 16.68 kWh/Day
Equipment load = 1.56 kWh/Day\
Infiltration load = 0.72 kWh/Day
TOTAL = 26.3627 kWh/Day

APPENDIX E - COMPUTATION OF POWER CONSUMPTION MONTHLY

48
College of Engineering
49

BS Mechanical Engineering

Daily Consumption = 12.4 kWh/day (JULY)


Consumption of Electricity per month = (12.4 kWh/day)(31days) = 384.4 kWh
Rates per month = 11.12 pesos per kWh
Monthly Bill amount = (12.4 kWh/day) (11.12 pesos per kWh) (31days) = 4274.528
Pesos

Daily Consumption = 10.4 kWh/day (AUGUST)


Consumption of Electricity per month = (10.4 kWh/day)(30days) = 312 kWh
Rates per month = 10.43 pesos per kWh
Monthly Bill amount = (10.4 kWh/day) (10.43 pesos per kWh) (30days) = 3254.16
Pesos

Daily Consumption = 10.4 kWh/day (SEPTEMBER)


Consumption of Electricity per month = (9.32 kWh/day)(31days) = 288.92kWh
Rates per month = 10.27 pesos per kWh
Monthly Bill amount = (9.32 kWh/day) (10.27 pesos per kWh) (31days) = 2638.0184
Pesos

APPENDIX F - ADDITIONAL PHOTOS / DOCUMENTATION

49
College of Engineering
50

BS Mechanical Engineering

October 1

50
College of Engineering
51

BS Mechanical Engineering

51
College of Engineering
52

BS Mechanical Engineering

October 2

52
College of Engineering
53

BS Mechanical Engineering

October 4

October 7

October 9

53
College of Engineering
54

BS Mechanical Engineering

Octoberer 12

54
College of Engineering
55

BS Mechanical Engineering

October 14

October 15

55