Civil Snag
Civil Snag
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
Cleaning, leveling, watering and compaction are required on the application of sealant, application of protective coating. Foundation paint is
7 S+0
disturbed plattform surface. cracked and got removed. This paint must be removed fully and apply
new coating in all the four legs.
Access road Sand removal, grading & compaction on road surface are required. More damages and sattlement on the road.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
Cleaning, leveling, watering and compaction are required on the application of sealant, application of protective coating. Foundation paint is
8 S+3
disturbed plattform surface. cracked and got removed. This paint must be removed fully and apply
new coating in all the four legs.
Access road Sand removal, grading & compaction on road surface are required. More damages and sattlement on the road.