Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 18

Mott MacDonald Ltd.

List of balance and snag work (Civil) Contract # N4264


Ras Al Khaimah Site office Page 1 of 18 Lot 2A: 400kV OHL between Dhaid RAK
Tower # Tower Type Platform Pile Cap
Balance work: Cleaning of stub & pilecap, repairing of damages on concrete,
1 DE-6 No platform, General cleaning required
application of sealent, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
2 S+6 No platform, General cleaning required
application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. More damages and sattlement on the road.
Platform was disturbed by foundation, erection and stringing work. Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
3 S+3
Surface cleaning, leveling and compaction are required application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. More damages and sattlement on the road.
Pile sides need filling. Cleaning, leveling, watering and compaction Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
4 S+3
are required on the disturbed plattform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. More damages and sattlement on the road.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
5 S+0
disturbed plattform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. More damages and sattlement on the road.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
6 S+0
disturbed plattform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. More damages and sattlement on the road.

Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
Cleaning, leveling, watering and compaction are required on the application of sealant, application of protective coating. Foundation paint is
7 S+0
disturbed plattform surface. cracked and got removed. This paint must be removed fully and apply
new coating in all the four legs.

Access road Sand removal, grading & compaction on road surface are required. More damages and sattlement on the road.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
Cleaning, leveling, watering and compaction are required on the application of sealant, application of protective coating. Foundation paint is
8 S+3
disturbed plattform surface. cracked and got removed. This paint must be removed fully and apply
new coating in all the four legs.
Access road Sand removal, grading & compaction on road surface are required. More damages and sattlement on the road.

Contractor Consultant Client

KEC International Ltd Mott MacDonald TRANSCO


Mott MacDonald Ltd. List of balance and snag work (Civil) Contract # N4264
Ras Al Khaimah Site office Page 2 of 18 Lot 2A: 400kV OHL between Dhaid RAK
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
9 S+3
disturbed plattform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. More damages and sattlement on the road.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
10 S+0
disturbed plattform surface. One corner damaged by vehicle. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
Cleaning, leveling, watering and compaction are required on the
11 S+4 application of sealant, application of protective coating. Leg 'A' exposed 95
disturbed plattform surface.
cm, need filling to make it 75 cm.
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
11A
disturbed plattform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
11B
disturbed plattform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
12 AT+0
disturbed plattform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. More damages and sattlement on the road.
Sand cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
13 S+0
disturbed plattform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
14 S+3
disturbed plattform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
15 S+3
disturbed plattform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
16 S+3
disturbed platform surface. application of sealant, application of protective coating

Contractor Consultant Client

KEC International Ltd Mott MacDonald TRANSCO


Mott MacDonald Ltd. List of balance and snag work (Civil) Contract # N4264
Ras Al Khaimah Site office Page 3 of 18 Lot 2A: 400kV OHL between Dhaid RAK
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
17 S+2
disturbed platform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
18 AT+6
disturbed platform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair. Less width to be corrected.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
19 S+6
disturbed platform surface. application of sealant, application of protective coating.
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair. Less width to be corrected.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
Cleaning, leveling, watering and compaction are required on the
20 AT+6 application of sealant, application of protective coating. Leg 'C' exposed 40
disturbed platform surface.
cm, need to maintain 75 cm as per standard.
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
21 S-6
disturbed platform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Less width to be corrected.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
Cleaning, leveling, watering and compaction are required on the
22 S+0 application of sealant, application of protective coating. Leg 'A' exposed 45
disturbed platform surface.
cm, need to maintain 75 cm as per standard.
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair. Less width to be corrected.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
Cleaning, leveling, watering and compaction are required on the
23 S+6 application of sealant, application of protective coating. Leg 'A', 'B' and 'C'
disturbed platform surface.
less exposed need to maintain 75 cm as per standard.
Access road Sand removal, grading & compaction on road surface are required. Less width to be corrected.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
Cleaning, leveling, watering and compaction are required on the
24 S+0 application of sealant, application of protective coating. Leg 'D' exposed 40
disturbed platform surface.
cm, need to maintain 75 cm as per standard.
Access road Sand removal, grading & compaction on road surface are required. Less width to be corrected.

Contractor Consultant Client

KEC International Ltd Mott MacDonald TRANSCO


Mott MacDonald Ltd. List of balance and snag work (Civil) Contract # N4264
Ras Al Khaimah Site office Page 4 of 18 Lot 2A: 400kV OHL between Dhaid RAK
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
Cleaning, leveling, watering and compaction are required on the
25 S+3 application of sealant, application of protective coating. Leg 'D' exposed 40
disturbed platform surface.
cm, need to maintain 75 cm as per standard.
Access road Sand removal, grading & compaction on road surface are required. Less width to be corrected.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
Cleaning, leveling, watering and compaction are required on the
26 S+6 application of sealant, application of protective coating. Leg 'C' and 'D'
disturbed platform surface.
exposed 40 cm, need to maintain 75 cm as per standard.
Access road Sand removal, grading & compaction on road surface are required.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
Cleaning, leveling, watering and compaction are required on the
27 S-3 application of sealant, application of protective coating. Leg 'D' exposed 40
disturbed platform surface.
cm, need to maintain 75 cm as per standard.
Access road Sand removal, grading & compaction on road surface are required. More damages and sattlement on the road.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
28 S+6
disturbed platform surface. Filling required in the pile sides. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
29 S-6
disturbed platform surface. Filling required in the pile sides. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
30 S+0
disturbed platform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair. Less width to be corrected.
Balance work: Cleaning of stub & pile cap, repairing of concrete damages,
Cleaning, leveling, watering and compaction are required on the
31 S+6 application of sealant and protective coating. Leg 'B' 100 cm & leg 'D' 45cm
disturbed platform surface.
exposed, need to make 75 cmm as per standard.
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
32 S+2
disturbed platform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
33 AT+3 Cleaning & leveling are required on the disturbed platform surface.
application of sealant, application of protective coating

Contractor Consultant Client

KEC International Ltd Mott MacDonald TRANSCO


Mott MacDonald Ltd. List of balance and snag work (Civil) Contract # N4264
Ras Al Khaimah Site office Page 5 of 18 Lot 2A: 400kV OHL between Dhaid RAK
Access road Sand removal, grading & compaction on road surface are required.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
34 S+0 Only cleaning required.
application of sealant, application of protective coating
Access road Leveling & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
35 S+2
disturbed platform surface. application of sealant, application of protective coating
Access road Leveling & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
36 S+2
disturbed platform surface. application of sealant, application of protective coating
Access road Leveling & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
37 AT+0
disturbed platform surface. application of sealant, application of protective coating
Access road Leveling & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
38 S+0
disturbed platform surface. application of sealant, application of protective coating
Access road Leveling & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
39 S+2
disturbed platform surface. application of sealant, application of protective coating
Access road Small cleaning required on the surface.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
40 S+2
disturbed platform surface. application of sealant, application of protective coating
Access road Leveling & compaction on road surface are required.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
41 S+3 Cleaning is required on the platform surface.
application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
42 S+3 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road

Contractor Consultant Client

KEC International Ltd Mott MacDonald TRANSCO


Mott MacDonald Ltd. List of balance and snag work (Civil) Contract # N4264
Ras Al Khaimah Site office Page 6 of 18 Lot 2A: 400kV OHL between Dhaid RAK
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
43 S+3 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
44 S+0
disturbed platform surface. application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
45 S+6 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
46 S+6 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
47 S+6 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
48 BAT/90+6 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
49 BAT/90+6 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
50 S+0 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
51 S+0 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
52 S+0
disturbed platform surface. application of sealant, application of protective coating

Contractor Consultant Client

KEC International Ltd Mott MacDonald TRANSCO


Mott MacDonald Ltd. List of balance and snag work (Civil) Contract # N4264
Ras Al Khaimah Site office Page 7 of 18 Lot 2A: 400kV OHL between Dhaid RAK
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
53 S+3 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
54 S+3 No platform, General cleaning required application of sealant, application of protective coating. Leg 'D' exposed 45
cm, need to maintain 75 cm as per standard.
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
55 S+3 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
56 S+3 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
57 S+2 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
58 S+0
disturbed platform surface. application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
59 S+2 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
60 S+2 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
61 AT+0 No platform, General cleaning required
application of sealant, application of protective coating
Access road Leveling on road surface is required.

Contractor Consultant Client

KEC International Ltd Mott MacDonald TRANSCO


Mott MacDonald Ltd. List of balance and snag work (Civil) Contract # N4264
Ras Al Khaimah Site office Page 8 of 18 Lot 2A: 400kV OHL between Dhaid RAK
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
62 S+0 Cleaning & leveling are required on the disturbed platform surface.
application of sealant, application of protective coating
Access road Leveling on road surface is required.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
63 S+6 Cleaning & leveling are required on the disturbed platform surface.
application of sealant, application of protective coating
Access road Leveling on road surface is required.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
64 S+6 Cleaning & leveling are required on the disturbed platform surface.
application of sealant, application of protective coating
Access road Leveling on road surface is required.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
65 S+6 Cleaning & leveling are required on the disturbed platform surface.
application of sealant, application of protective coating
Access road Leveling on road surface is required.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
66 S+6 Cleaning & leveling are required on the disturbed platform surface.
application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
67 S+2
disturbed platform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
Cleaning, leveling, watering and compaction are required on the
68 BAT+3 application of sealantand protective coating. Leg 'C' 45 cm and leg 'D' 50' cm
disturbed platform surface.
exposed need to maintain 75 cm as per standard.
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
69 S+0
disturbed platform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
70 S+0
disturbed platform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
71 AT-6
disturbed platform surface. Platform size to be corrected. application of sealant, application of protective coating

Contractor Consultant Client

KEC International Ltd Mott MacDonald TRANSCO


Mott MacDonald Ltd. List of balance and snag work (Civil) Contract # N4264
Ras Al Khaimah Site office Page 9 of 18 Lot 2A: 400kV OHL between Dhaid RAK
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
72 S+6
disturbed platform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
73 S+6
disturbed platform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
74 S-6
disturbed platform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
75 S-4
disturbed platform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair. Less width to be corrected.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
76 S+3
disturbed platform. Erosion started in one side,need protection. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
77 S+6
disturbed platform. Erosion started in one side,need protection. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
78 S+6
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
79 S+0
disturbed platform surface and pile sides.. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
80 S-6
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating
Access road Leveling on road surface is required.

Contractor Consultant Client

KEC International Ltd Mott MacDonald TRANSCO


Mott MacDonald Ltd. List of balance and snag work (Civil) Contract # N4264
Ras Al Khaimah Site office Page 10 of 18 Lot 2A: 400kV OHL between Dhaid RAK
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
81 S+0
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
82 S-4
disturbed platform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
83 S-3
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
84 S+6
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
85 BAT/90+6
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
86 BAT/90+0
disturbed platform surface. Severe damage need repair. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
87 S+6
disturbed platform surface. application of sealant, application of protective coating
Access road Cleaning and leveling on road surface is required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
88 S+6
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
89 S+3
disturbed platform surface pile sides. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
90 S-6
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating

Contractor Consultant Client

KEC International Ltd Mott MacDonald TRANSCO


Mott MacDonald Ltd. List of balance and snag work (Civil) Contract # N4264
Ras Al Khaimah Site office Page 11 of 18 Lot 2A: 400kV OHL between Dhaid RAK
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
91 S+6
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
92 S-3
disturbed platform. Rain cut need repair. Size is smaller application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
93 S+3
disturbed platform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
Cleaning, leveling, watering and compaction are required on the
94 AT-6 application of sealant, application of protective coating. Small cracks on pile
disturbed platform surface.
cap (leg B, C & D) need repair properly.
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
95 S+4
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
96 S+6
disturbed platform surface. Big slope in one side. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
97 S+0
disturbed platform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair. Less width to be corrected.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
98 S+0
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair. Less width to be corrected.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
99 S+0
disturbed platform surface. Big rain cut need repair. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair. Less width to be corrected.

Contractor Consultant Client

KEC International Ltd Mott MacDonald TRANSCO


Mott MacDonald Ltd. List of balance and snag work (Civil) Contract # N4264
Ras Al Khaimah Site office Page 12 of 18 Lot 2A: 400kV OHL between Dhaid RAK
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
100 S+0
disturbed platform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
Cleaning, leveling, watering and compaction are required on the
101 S-4 application of sealant, application of protective coating. Leg 'C' & 'D' only 45
disturbed platform surface.
cm exposed, 75 cm tobe maintain as per standard.
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
Cleaning, leveling, watering and compaction are required on the
102 S-6 application of sealant, application of protective coating. Leg 'B' 95 cm
disturbed platform surface.
exposed, 75 cm to be maintained as per standard.
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
103 S+0
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
104 S+6
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
105 S+6
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
106 S+6
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
107 AT+0
disturbed platform surface. (Inside fence) application of sealant, application of protective coating
Access road No access road
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
108 S+0
disturbed platform surface. application of sealant, application of protective coating
Access road No access road

Contractor Consultant Client

KEC International Ltd Mott MacDonald TRANSCO


Mott MacDonald Ltd. List of balance and snag work (Civil) Contract # N4264
Ras Al Khaimah Site office Page 13 of 18 Lot 2A: 400kV OHL between Dhaid RAK
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
109 S-6
disturbed platform surface. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
110 S-6
disturbed platform surface. application of sealant, application of protective coating
Access road Levelling & compaction on road surface are required.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
Cleaning, leveling, watering and compaction are required on the
111 S-6 application of sealant, application of protective coating.one leg exposed more
disturbed platform surface.
than 75 cm.
Access road Levelling & compaction on road surface are required. Less width, to be corrected.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
112 S-3
disturbed platform surface. application of sealant, application of protective coating
Access road Levelling & compaction on road surface are required. Less width, to be corrected.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
113 DE-6
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
Cleaning, leveling, watering and compaction are required on the
Gan-II T-GAN(UC) application of sealant, application of protective coating. Some pile cap top
disturbed platform surface.
was damaged by rain need to be repaired properly.
Access road Levelling & compaction on road surface are required. Less width, to be corrected.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
Gan-III T-GAN(UC)
disturbed platform surface. application of sealant, application of protective coating
Access road surface leveling required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
114 BAT/90+6
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating
Access road No access road
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
115 AT+6
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating
Access road Levelling & compaction on road surface are required. (closed by fence.)

Contractor Consultant Client

KEC International Ltd Mott MacDonald TRANSCO


Mott MacDonald Ltd. List of balance and snag work (Civil) Contract # N4264
Ras Al Khaimah Site office Page 14 of 18 Lot 2A: 400kV OHL between Dhaid RAK
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
116 S+6
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating
Access road surface leveling required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
117 S+6
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating
Access road Sand removal, grading & compaction on road surface are required. Rain cut in several places, need repair.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
118 S-3
disturbed platform surface. application of sealant, application of protective coating
Access road Levelling & compaction on road surface are required. Less width, to be corrected.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
119 S-6
disturbed platform surface. Rain cut need repair. application of sealant, application of protective coating
Access road Levelling & compaction on road surface are required. Less width, to be corrected.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
120 S+6
disturbed platform surface. Size to be corrected. application of sealant, application of protective coating
Access road Leveling on road surface is required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
121 S+3
disturbed platform surface. application of sealant, application of protective coating
Access road Leveling on road surface is required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
122 S+6
disturbed platform surface. application of sealant, application of protective coating
Access road Leveling on road surface is required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
123 S+0
disturbed platform surface. application of sealant, application of protective coating
Access road Leveling on road surface is required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
124 S-6
disturbed platform surface. application of sealant, application of protective coating
Access road Leveling on road surface is required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
125 S-3
disturbed platform surface. application of sealant, application of protective coating

Contractor Consultant Client

KEC International Ltd Mott MacDonald TRANSCO


Mott MacDonald Ltd. List of balance and snag work (Civil) Contract # N4264
Ras Al Khaimah Site office Page 15 of 18 Lot 2A: 400kV OHL between Dhaid RAK
Access road Leveling on road surface is required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
126 BAT+0
disturbed platform surface. application of sealant, application of protective coating
Access road No access road
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
127 S+0
disturbed platform surface. application of sealant, application of protective coating
Access road Leveling on road surface is required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
128 S+0
disturbed platform surface. application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
129 S+0 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road
No platform, General cleaning required. Pile sides need filling and Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
130 BAT/90+0
compaction. application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
131 S+6 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
132 S+6 No platform, General cleaning required
application of sealant, application of protective coating
Access road Partial road, Width need to be rectified. Road is closed by fence.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
133 S+6 No platform, General cleaning required
application of sealant, application of protective coating
Access road Cleaning and leveling on road surface are required. (Closed by fence)
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
134 S+6
disturbed platform surface. application of sealant, application of protective coating
Access road Cleaning and leveling on road surface are required. (Closed by fences)

Contractor Consultant Client

KEC International Ltd Mott MacDonald TRANSCO


Mott MacDonald Ltd. List of balance and snag work (Civil) Contract # N4264
Ras Al Khaimah Site office Page 16 of 18 Lot 2A: 400kV OHL between Dhaid RAK
No platform, General cleaning required. Pile sides need filling and Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
135 AT+6
compaction. application of sealant, application of protective coating
Access road Leveling on road surface is required. (Closed by fence)
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
136 S+3
disturbed platform surface. application of sealant, application of protective coating
Access road No access road
No platform, General cleaning required. Pile sides need filling and Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
137 BAT+0
compaction. application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
138 S+6 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
139 S+6
disturbed platform surface. (Inside date farm) application of sealant, application of protective coating
Access road Leveling on road surface is required. (Closed by fence)
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
140 S+6
disturbed platform surface. application of sealant, application of protective coating
Access road No access road
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
141 S+6
disturbed platform surface. application of sealant, application of protective coating
Access road No access road
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
142 S+4
disturbed platform surface. application of sealant, application of protective coating
Access road No access road
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
143 S+2
disturbed platform surface. application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
144 BAT+6 No platform, General cleaning required
application of sealant, application of protective coating

Contractor Consultant Client

KEC International Ltd Mott MacDonald TRANSCO


Mott MacDonald Ltd. List of balance and snag work (Civil) Contract # N4264
Ras Al Khaimah Site office Page 17 of 18 Lot 2A: 400kV OHL between Dhaid RAK
Access road Leveling on road surface is required. (Partial road, closed by fence)
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
145 S+6
disturbed platform surface. application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
146 S+0 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
147 S+0
disturbed platform surface. (Inside date farm) application of sealant, application of protective coating
Access road Cleaning and leveling on road surface are required. (Partial road closed by fence)
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
148 S+6
disturbed platform surface. application of sealant, application of protective coating
Access road No access road
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
149 BAT+6
disturbed platform surface and sattled Pile sides. application of sealant, application of protective coating
Access road Cleaning and leveling on road surface are required.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
150 S+6
disturbed platform surface. (closed by fence) application of sealant, application of protective coating
Access road Partial road, Width need to be rectified.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
151 S+3 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
152 AT+6 No platform, General cleaning required
application of sealant, application of protective coating
Access road No access road
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
153 AT+6 No platform, General cleaning required
application of sealant, application of protective coating
Access road Cleaning and leveling on road surface are required. (Partial road closed by fence)

Contractor Consultant Client

KEC International Ltd Mott MacDonald TRANSCO


Mott MacDonald Ltd. List of balance and snag work (Civil) Contract # N4264
Ras Al Khaimah Site office Page 18 of 18 Lot 2A: 400kV OHL between Dhaid RAK
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
154 AT+2
disturbed platform surface. application of sealant, application of protective coating
Access road Cleaning and leveling on road surface are required. (Partial road closed by fence)
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
155 S-6
disturbed plattform surface. application of sealant, application of protective coating
Access road Cleaning and leveling on road surface are required. Road sattled un duley need to be repaired.
Cleaning, leveling, watering and compaction are required on the Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
156 BAT90/DE-6
disturbed plattform surface. application of sealant, application of protective coating
Access road Cleaning and leveling on road surface are required.
Balance work: Cleaning of stub & pile cap, repairing of damages on concrete,
GANTRY Inside substation, No platform
application of sealant, application of protective coating

Contractor Consultant Client

KEC International Ltd Mott MacDonald TRANSCO

You might also like