Professional Documents
Culture Documents
9 Major Steps Are Required in Developing A Schedule
9 Major Steps Are Required in Developing A Schedule
1. List task
List task means listing the tasks or task list which shows the individual activities that need
to be performed to complete work packages and respectively the overall project scope. In
the end, project schedule includes the ordered and organized project activities. Therefore,
task list is a critical input for develop schedule process.
For example: For a normal working person, task list will be as follows-
TIME TASK
4:30 am Wake up
4:45 am Exercise
5:00 am Bathing
5:30 am Dress Up
6:00 am Breakfast
6:30 am Office
1:30 pm Lunch
8:30 pm Dinner
BUILDING A HOUSE
BUYING
FENCING STRUCTURE
MATERIAL TEAM
DISSOLUTION
RECRUITING PAINTING
LABOUR
- Site preparation: It’ll all start with the site cleaning. The nearby area should be ready
for all upcoming activities. It will take some time. After that, we need to secure
fencing in order to carry out all the internal work.
- Buying resources: The next stage of our construction work breakdown structure
example includes cost prediction, purchasing the necessary materials and construction
equipment, and recruiting labour.
- Construction: This is one of the most important steps in the process of building the
house, as it relates to building a foundation and various structures. Painting works are
also included into this part of the WBS.
- Cleaning: After all construction work, we will need to remove scrap and unnecessary
building materials.
- Deliverable: Our work breakdown structure for construction project will end with the
release of the house and the dissolution of the team.
3. Identify Milestones
For Example: Milestones of a project named building a house are discussed below:
MILESTONES
PROJECT APPROVAL 30 OCT 2022
It means assigning responsible people for the project development and each person will
have to perform their specific role and responsibility.
NAME ROLE
APPROVAL OF COSTRUCTION
CONTRACTOR
PROJECT
REMOVING CLEANING
SCRAP
END
Estimating task efforts means estimating the efforts which are needed to perform in the
project development tasks. Different tasks in project development requires different efforts.
This leads to know the duration of different tasks and their execution dates in project
management. Estimate task duration is the technique for evaluating the number of work
periods required to finish individual activities with estimated resources. The key advantage of
this procedure is that it projects the amount of time that every task will take to complete,
which is a significant input to the development schedule process. Subsequently, as activity
resources are determined, the resources estimate the activity durations for project completion
timelines.