Material Requisition: I-RM-3A36.05-1519-29B-PZ9-004 Uo-Bs 1 7 Búzios 5 Field Development Búzios 5
Material Requisition: I-RM-3A36.05-1519-29B-PZ9-004 Uo-Bs 1 7 Búzios 5 Field Development Búzios 5
:
MATERIAL REQUISITION I-RM-3A36.05-1519-29B-PZ9-004
CLIENT: SHEET:
UO-BS 1 of
7
JOB:
BÚZIOS 5 FIELD DEVELOPMENT
AREA:
BÚZIOS 5
TITLE:
CONTRACT: 4600639715
INDEX OF REVISIONS
EXECUTION Yonathan(UPOV)
CHECK Cintia(Y534)
APPROVAL M.Dias(BEIW)
INFORMATION IN THIS DOCUMENT IS PROPERTY OF PETROBRAS, BEING PROHIBITED OUTSIDE OF THEIR PURPOSE
FORM OWNED TO PETROBRAS N-381 REV. L
PÚBLICA
No. REV.
MATERIAL REQUISITION I-RM-3A36.05-1519-29B-PZ9-004 0
SHEET
2 of
7
TITLE:
CONTENTS
1 SCOPE .......................................................................................................................... 3
2 REFERENCES .............................................................................................................. 3
3 SCOPE OF SUPPLY ..................................................................................................... 3
4 FIT-UP TEST ................................................................................................................. 7
PÚBLICA
No. REV.
MATERIAL REQUISITION I-RM-3A36.05-1519-29B-PZ9-004 0
SHEET
3 of
7
TITLE:
1 SCOPE
1.1 This MATERIAL REQUISITION defines the specific requirements for the design,
manufacture, test and supply of subsea umbilical systems. All general requirements
shall be according to the CONTRACT MATERIAL REQUISITION
2 REFERENCES
2.1 References here presented prevail over those previously presented in reference [1].
Table 2-I
Ref. Standard/Code Rev./Ed. Title/Description
[1] I-RM-3000.00-1519-29B-PZ9-010 0 Contract Material Requisition
[2] LI-3000.00-1519-29B-PZ9-008 C Terminações padronizadas de umbilicais
[3] I-DE-3A36.05-1500-941-P9U-004 D Subsea Layout
[4] I-ET-3A36.00-1000-941-PPC-001 E Metocean data
[5] I-ET-3A26.00-1500-960-PPC-001 D Fatigue data for Santos Basin
[6] ET-3000.00-6600-941-PMU-001 AG Principais características - frota PLSV
[7] 0479-SF20-80R1-0004-001 B Host facility motion data
[8] seriesLF_roll_MV32 Séries Temporais de Roll
[9] Proposta Segunda Ordem RA Movimento de Roll de Segunda Ordem
para Buzios 5
[10] I-ET-3A36.05-1200-940-PR4-003 0 Host facility mooring/offset data
[11] I-DE-3A36.00-1500-941-PLR-067 N Host facility general balcony drawing
[12] 0479-CDS20-30DL-8521-001 1 Host facility drawings
[13] 0479-MI20-3004-8521-001 Maximum top loads
[14] I-DE-3010.00-1300-279-PPC-085 0 Bend stiffener cap for bell mouth
[15] TBD Riser configuration data
[16] RL-3A36.05-1500-941-PIP-002 0 Soil data
3 SCOPE OF SUPPLY
3.1 MATERIALS
3.1.1 Materials scope of supply according to subsea layouts and Table 3-I. Components
interfaces/terminations according to reference [2].
3.1.2 When not requested by PETROBRAS the use of umbilical joints shall be
highlighted and justified by SUPPLIER and approved by PETROBRAS.
Table 3-I
PÚBLICA
No. REV.
MATERIAL REQUISITION I-RM-3A36.05-1519-29B-PZ9-004 0
SHEET
4 of
7
TITLE:
1 1
EDB - 1
Umbilical Umbilical
System EDB - 2 System
Umbilical Umbilical
System System
3.1.4 Schematic of internal circuits of end-line UTAs of I-MOD5-01 and I-MOD5-03 shall
be as follow:
PÚBLICA
No. REV.
MATERIAL REQUISITION I-RM-3A36.05-1519-29B-PZ9-004 0
SHEET
5 of
7
TITLE:
UTA To well 2
EDB - 1
Umbilical
EDB - 2 System
UTA To well 2
Umbilical
System
1 2
Alternative A
From FPSO UTA To PLEM
Umbilical Umbilical
System EDB
Umbilical systems electric cables and System
electric terminations
3
3 Pair of electric connectors for 1x2x4mm2 cable / JIC-8
PÚBLICA
No. REV.
MATERIAL REQUISITION I-RM-3A36.05-1519-29B-PZ9-004 0
SHEET
6 of
7
TITLE:
1 2 3
Alternative B
From FPSO UTA To PLEM
Umbilical Umbilical
System System
Umbilical systems electric cables and
electric terminations
EDB
1 Pair of electric connectors for 1x2x2,5mm2 cable / JIC-8
To ESDV
EDB – Electric distribution box
Umbilical Umbilical
System System
3.1.6 The anchoring collars shall be supplied with shackles according to Table 3-II.
Shackles shall be bolt type with safety pin.
Table 3-II
Anchoring collar
Shackles compatibility
load class
Shackles supplied shall be dimensionally compatible with 50/55
Till 80 tonnes tonnes ABNT NBR 13545:2012 Grau 8S curved shackle
Shackles supplied shall be dimensionally compatible with 120
Above 80 tonnes tonnes ABNT NBR 13545:2012 Grau 8S curved shackle
3.1.7 If rigid joint/bend restrictor for top end termination/bend stiffener use fuse cables
of pull-in kit, a set of cables shall be supplied for handling and a set of cables shall
be supplied for pull-in.
3.1.8 The materials not assembled on umbilical shall be delivered in closed boxes, not
be loose in box, be corrosion protected (coated with lubricant, oil, wax, varnish…),
have all threads lubricated and protected and be packed (tape, plastic…).
PÚBLICA
No. REV.
MATERIAL REQUISITION I-RM-3A36.05-1519-29B-PZ9-004 0
SHEET
7 of
7
TITLE:
3.2.1 The Table 3-III presents particular analyses required for this supply.
Table 3-III
Analysis Required
Interference analysis YES
Abandonment analyses for riser umbilicals with
NO
buoyancy systems
Free-hanging catenary analysis to evaluate
viability of eliminating buoyance systems in
NO
riser umbilicals (this is an additional analysis to
the lazy-wave design analysis)
3.3 DOCUMENTATION
4 FIT-UP TEST
4.1 Fit-up tests are required between umbilical and subsea equipment that are
PETROBRAS scope of supply. SUPPLIER shall provide an umbilical dummy
termination and a representative for the tests.