BENCH AT GWALIOR
W.P. NO. /2022
Versus
RESPONDENTS : The State of M.P. & Ors.
LIST OF EVENTS
Date Description Annexure
Petitioner is aggrieved by the action on the part P/1 to P/4
of respondents while not releasing the payment,
despite of fact that work is successfully
completed and work completion certificate issued
way back on 12.10.2020. The only reason
assigned for non-making payment, remaining
bills of the petitioner is of non-availability of
funds, which reason cannot sustain in view of
Article 14 of the Constitution of India. Once the
petitioner has worked with the respondents, the
amount is not disputed, the respondents have no
authority under the law to stop the payment of
the remaining bills of the petitioner.
Versus
RESPONDENTS : The State of M.P. & Ors.
INDEX
DOCUMENTS
1. Writ Petition
2. Affidavit
3. List of Documents
4. Copy of work order P/1
5. Copy of work completion certificate P/2
6. Copy of bill P/3
7. Copy of representation P/4
8. Power
(D.S. Raghuvanshi)
Advocate
IN THE HIGH COURT OF MADHYA PRADESH
BENCH AT GWALIOR
W.P. NO. /2022
Versus
RESPONDENTS : The State of M.P. & Ors.
LIST OF DOCUMENTS
Versus
CONSTITUTION OF INDIA
Declaration :
Decision etc:
ORDER:
EXPLANATION THEREFOR:
under:
Annexure P/3.
Constitution of India.
5.9 That, for the reasons aforesaid, the present petition is
(6) GROUNDSURGED:
Constitution of India.
course of arguments.
granted.
justice.
(10)CAVEAT :
(D.S. Raghuvanshi)
Advocate
Versus
RESPONDENTS : The State of M.P. & Ors.
AFFIDAVIT