CE-210043 - HC Dew Point Conditioning Unit - Technical Offer - Rev 0
CE-210043 - HC Dew Point Conditioning Unit - Technical Offer - Rev 0
RFQ Reference: ITT No. ASPL/2021/DRM/003 (Tender for EPC/BOO of Duarmara Gas Processing Facility)
Project: Duarmara Phase I- Onshore Development Project Surface Facility Development
Client: Antelopus Energy Private Limited
Location: India
Dear Sir,
Crescent Engineering FZE are pleased to offer this quotation for Duarmara Phase I- Onshore Development
Project in accordance with the following design criteria, specifications, terms, pricing and delivery.
Our offer is as defined in this proposal and any attached documents including the “Comments /
Clarifications/ Exceptions” section of this proposal.
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 2
Quotation No.: CE-210043 Rev 0 21th September, 2021
Table of Contents
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 3
Quotation No.: CE-210043 Rev 0 21th September, 2021
FEED
COMPOSITION
The production facility has been designed to process the following gas composition;
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 4
Quotation No.: CE-210043 Rev 0 21th September, 2021
15 n-Octane 0.0145
16 n-Nonane 0.0010
17 n-Decane 0.0016
DESIGN MARGIN
The plant has been designed with the following design margin considered;
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 5
Quotation No.: CE-210043 Rev 0 21th September, 2021
1 No. Inlet Manifold (NPS 3”, SCH XXS) is provided to receive the production fluid from 2 Wells. We have
considered two flow lines (NPS 3”, SCH XXS).
All the flowlines and Manifold is designed for the well shut-in pressure 310.30 Barg (4500 Psig).
CASE 1 2 3 4
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 6
Quotation No.: CE-210043 Rev 0 21th September, 2021
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 7
Quotation No.: CE-210043 Rev 0 21th September, 2021
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 8
Quotation No.: CE-210043 Rev 0 21th September, 2021
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 9
Quotation No.: CE-210043 Rev 0 21th September, 2021
8. BMS (Burner Management System) will be part of PLC to be placed in safe area.
9. Burner Parts
- Fuel Gas/ Diesel Oil Modulating Low NOx ATEX Monobloc burner controlled by a PLC, Ex ( ATEX
zone 1&2 version ), with the following characteristics:
- Fully self-running modulating burner manufactured in steel with air regulation by air flaps.
The following items are incorporated to the burner.
Steel housing manufactured in carbon steel where the fan motor and the air wheel are
included.
Fan operating safety control by air pressure transmitter. Suitable for ATEX area EExd.
Combustion burner head composed by center gas tube, gas lances, flame tube, primary air
front plate.
Ignition by a non-continuous pilot burner.
Sight glass at the back of the burner for visualization of flame.
Flame detection by 1 UV self-checking EExd certified flame scanner.
Internal damper for regulating air flow.
Trafo. included in a S.S. EExe junction box.
1Off ATEX zone 1 & 2 EExd actuator for moving the air flaps.
1 Off EExe ATEX junction box for the connection of the elements.
Automatic system for the oil lance retraction when the burner is operating with gas with
one EExd zone 1 limit switch
1 Off 5/2 EExd solenoid valve for moving the cylinder of the oil lance.
Silencer.
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 10
Quotation No.: CE-210043 Rev 0 21th September, 2021
Mist Eliminator
Vortex Breaker
Insulation No
Additional Design
Considerations EHT No
Mechanical Design:
Tag No – V-100
Type – Horizontal, Three Phase Separator
Vessel Size – 450 mm ID X 8 ft T/T
Design Pressure (Bar g) – 76 /FV
Design Temperature (°C) – -29/ 100 °C
Main Nozzle size – Inlet Nozzle – 4 Inch
Gas Outlet – 4 inch
Level Setting – LSLL – 150 mm
LAL – 250 mm
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 11
Quotation No.: CE-210043 Rev 0 21th September, 2021
NLL – 350 mm
LAH – 450 mm
LSHH – 550 mm
Internals will be – Crescent Standard Tangential Baffle type inlet device
6 inch Thk Demister Pad
Material Specification:
Shell – SA 516 Gr 70 N/ SA 106 Gr B
Head – CS
Nozzle Pipes – A 106 Gr B
Nozzle Flanges – A 105 N
Corrosion Allowance – 3 mm
Insulation – None
Design Code – ASME SEC VIII Div 1.
U Stamp – Yes
Saddle / Base Plate etc – A 36 OR SA 516 Gr 70N
Name Plate – SS 316
Bolts – SA 193 Gr B7
Nuts – SA-194 Grade 2H
Internal MOC – SA 516 Gr 70 (Welded)
SS 316 (Removable)
Material Certification – Pressure Part – EN 10204, type 3.1
Non Pressure Part – EN 10204, type 2.2
External Painting – 3 Coat Epoxy
Internal Painting – NA
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 12
Quotation No.: CE-210043 Rev 0 21th September, 2021
CASE 1 2 3 4
Insulation No
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 13
Quotation No.: CE-210043 Rev 0 21th September, 2021
Mechanical Design:
Tag No – E-101
Type – Air Cooled Heat Exchanger
Duty – 180 Kw
Design Pressure (Bar g) – 76 Bar g
Design Temperature (°C) – -29/ 100 °C
Main Nozzle size – Inlet Nozzle – 4 Inch
Header – CS
Pipe Coil – CS
Construction Details:
Fin – L Fins, Aluminum Alloy Fin 1100.
Header Box – Plug type, SA 516 Gr 70.
Tubes – 25.4 mm OD X 2.11 mm Thk X 5.3 mm long, SA 179.
Motor – 3.7 KW.
VFD compatible motors, TEFC, 50 Hz, 400 V, Ex’d’, Zone-2,
IIA/IIB, T3, IP55, MOC-Cast iron, MakeWEG, Brook
Crompton, Leroy Somer, Marrelli Motors or equivalent.
Vibration Switch – Murphy VS-2
Tube to Tube sheet Joint – Expanded With groove.
Bug Screen – NIL
Louvers – NIL
Motor Maintenance Platform – NIL
Painting – Structure hot dip galvanized and Header box shall be
painted only.
Mechanical Design:
Mechanical design of pressure parts of the air cooled heat exchangers shall be in accordance with job
specifications, ASME Sec.-VIII, Div.-I edition 2019 using PVELITE.
Structural Design:
Structural design of the air cooled heat exchanger support structure shall be performed using STAADPRO
software.
Fans:
The fans will be of COFIMCO make with Aluminum blades and manually adjustable pitch and forced draft
type. All air coolers will have sound pressure level < 85 dbA at 1 m from unit periphery.
All Pressure parts materials shall be procured in accordance with EN 10204 3.1 certification. All Non
pressure parts will be with 3.1/2.2 material certification as per availability.
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 14
Quotation No.: CE-210043 Rev 0 21th September, 2021
CASE 1 2 3 4
Insulation No
Additional Design
Considerations
Mechanical Design:
Tag No – E-102
Type – Shell and Plate Heat Exchanger
Duty – 131 Kw
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 15
Quotation No.: CE-210043 Rev 0 21th September, 2021
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 16
Quotation No.: CE-210043 Rev 0 21th September, 2021
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 17
Quotation No.: CE-210043 Rev 0 21th September, 2021
3.6 LT SEPARATOR
Mist Eliminator
Vortex Breaker
Insulation No
Additional Design
Considerations EHT No
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 18
Quotation No.: CE-210043 Rev 0 21th September, 2021
LT Separator V-101
Mechanical Design:
Tag No – V-101
Type – Three Phase Separator
Vessel Size – 450 mm ID X 8 ft T/T
Design Pressure (Bar g) – 40 /FV
Design Temperature (°C) – -29/ 50 °C
Main Nozzle size – Inlet Nozzle – 4 Inch
Gas Outlet – 4 inch
Level Setting – LSLL – 150 mm
LAL – 250 mm
NLL – 350 mm
LAH – 450 mm
LSHH – 550 mm
Internals will be – Crescent Standard Tangential Baffle type inlet device
6 inch Thk Demister Pad
Material Specification:
Shell – SA 516 Gr 70 N/ SA 106 Gr B
Head – CS
Nozzle Pipes – A 106 Gr B
Nozzle Flanges – A 105 N
Corrosion Allowance – 3 mm
Insulation – None
Design Code – ASME SEC VIII Div 1.
U Stamp – Yes
Saddle / Base Plate etc – A 36 OR SA 516 Gr 70N
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 19
Quotation No.: CE-210043 Rev 0 21th September, 2021
Mechanical Design:
Tag No – E-103
Type – Electric Heater
Heater Duty – 73 kW
Heater Size – TBA
Design Pressure (Bar g) – 10 /FV
Design Temperature (°C) – -29/ 50 °C
Main Nozzle size – Inlet Nozzle – 2 Inch
Outlet Nozzle – 2 inch
Material Specification:
Shell – SA 516 Gr 70 N/ SA 106 Gr B
Head – CS
Nozzle Pipes – A 106 Gr B
Nozzle Flanges – A 105 N
Corrosion Allowance – 3 mm
Insulation – None
Design Code – ASME SEC VIII Div 1.
U Stamp – Yes
Saddle / Base Plate etc – A 36 OR SA 516 Gr 70N
Name Plate – SS 316
Bolts – SA 193 Gr B7
Nuts – SA-194 Grade 2H
Internal MOC – SA 516 Gr 70 (Welded)
SS 316 (Removable)
Material Certification – Pressure Part – EN 10204, type 3.1
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 20
Quotation No.: CE-210043 Rev 0 21th September, 2021
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 21
Quotation No.: CE-210043 Rev 0 21th September, 2021
Mechanical Design:
Tag No – V-103
Type – Two Phase Separator
Vessel Size – 375 mm ID X 7 ft T/T
Design Pressure (Bar g) – 10 /FV
Design Temperature (°C) – -29/ 90 °C
Main Nozzle size – Inlet Nozzle – 1.5 Inch
Gas Outlet – 1.5 inch
Level Setting – LSLL – 150 mm
LAL – 250 mm
NLL – 350 mm
LAH – 450 mm
LSHH – 550 mm
Internals will be – Crescent Standard Tangential Baffle type inlet device
6 inch Thk Demister Pad
Material Specification:
Shell – SA 516 Gr 70 N/ SA 106 Gr B
Head – CS
Nozzle Pipes – A 106 Gr B
Nozzle Flanges – A 105 N
Corrosion Allowance – 3 mm
Insulation – None
Design Code – ASME SEC VIII Div 1.
U Stamp – Yes
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 22
Quotation No.: CE-210043 Rev 0 21th September, 2021
Mechanical Design:
Tag No – V-102
Type – Horizontal Vessel
Vessel Size – 375 mm ID X 7 ft T/T
Design Pressure (Bar g) – Atm
Design Temperature (°C) – -29/ 90 °C
Main Nozzle size – Inlet Nozzle – 1.5 Inch
Outlet Nozzle – 1.5 inch
Level Setting – LSLL – 150 mm
LAL – 250 mm
NLL – 350 mm
LAH – 450 mm
LSHH – 550 mm
Internals will be – Crescent Standard Tangential Baffle type inlet device
6 inch Thk Demister Pad
Material Specification:
Shell – SA 516 Gr 70 N/ SA 106 Gr B
Head – CS
Nozzle Pipes – A 106 Gr B
Nozzle Flanges – A 105 N
Corrosion Allowance – 3 mm
Insulation – None
Design Code – ASME SEC VIII Div 1.
U Stamp – Yes
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 23
Quotation No.: CE-210043 Rev 0 21th September, 2021
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 24
Quotation No.: CE-210043 Rev 0 21th September, 2021
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 25
Quotation No.: CE-210043 Rev 0 21th September, 2021
Performance Curve:
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 26
Quotation No.: CE-210043 Rev 0 21th September, 2021
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 27
Quotation No.: CE-210043 Rev 0 21th September, 2021
Casing Visual
Shaft Visual
Impellers Visual
Shaft Seal/ Balance piston Visual
Bearing Housing Visual
NDT Nozzle Welds Visual
NDT Butt Welds Visual
NDT Filler Welds Visual
All tests available will be performed according to ASNT-TC-1A with class II or III Operator.
PMI test shall be performed for all alloyed / stainless steel, if requested.
Official ITP for pumps will be prepared after the order.
Quoted test and certifications required are:
The following items are excluded related to pumps from the scope of supply, but could be quoted as
option:
1. Every drainage / cooling / flushing from the pump to the plant, if required
2. First fill in of lubricant
3. Welding Map, WPQR and WPS for Welds components and parts
4. Every cost of Third Part Inspection (TPI)
5. Every Non Destruction Examination (NDE): Magnetic Test (MT), Penetrant Test (PT), Radiographic
Test (RT) on every castings
6. Every Non Destruction Examination (NDE): Magnetic Test (MT), Penetrant Test (PT), Radiographic
Test (RT) on every welds both casing and base-plate
7. Witnessed 4 Hours Performance Test, NPSH Test and Hydrostatic Test
8. Special Painting Cycle
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 28
Quotation No.: CE-210043 Rev 0 21th September, 2021
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 29
Quotation No.: CE-210043 Rev 0 21th September, 2021
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 30
Quotation No.: CE-210043 Rev 0 21th September, 2021
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 31
Quotation No.: CE-210043 Rev 0 21th September, 2021
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 32
Quotation No.: CE-210043 Rev 0 21th September, 2021
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 33
Quotation No.: CE-210043 Rev 0 21th September, 2021
RVP Analyzer
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 34
Quotation No.: CE-210043 Rev 0 21th September, 2021
UTILITY PACKAGE
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 35
Quotation No.: CE-210043 Rev 0 21th September, 2021
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 36
Quotation No.: CE-210043 Rev 0 21th September, 2021
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 37
Quotation No.: CE-210043 Rev 0 21th September, 2021
Design Basis ;
B) The Minimum Dew Point of water at dryer outlet is (-)40 °C at atmospheric Pressure.
C) Instrument Air & Utility Air Receiver is sized with 5 mintues residance time between normal and
Maximum Supply Pressure.
The Instrument and Utility Air System is used to provide the air for Control valves, Shutdown valves, on/off
valves and maintenance of Vessel. Instrument/ Utility air systems are designed to cater all the
requirements. Instrument/ Utility air System consists of ;
Atmospheric air is compressed through the IA/UA Compressor Package to the required pressure. IA/UA
Compressor is designed to deliver the _____ Nm³/hr air capacity(2x100%-1 is in operation and 1 for
operational Standby). The IA dryer package should be heatless type and 20% of the dried air from the dryer
outlet is used for dryer bed regeneration. Utility air receiver and IA Dryer package receives inlet from IA/UA
compressor package discharge header. Utility Air Receiver distributes the Utility air to Utility air consumers.
Instrument Air dryer is used to remove water vapour and to achieve the dew point of (-)40 ° at atmospheric
pressure from compressed air to use as instrument air. The process of air compression concentrates
atmospheric contaminants, including water vapour. This raise the dew point of the compressed air relative
to free atmospheric air and leads to condensation within pipes as the compressed air cools downstream of
the compressor. Excessive water in compressed air, either in the liquid or vapour phase, can cause a variety
of operational problems for users of compressed air. These include freezing of outdoor air lines; corrosion
of equipment;fouling of processes and products. After drying the air , it is sent to the instrument air
receiver. Instrument air is distributed to the consumers from the instrument air receiver.
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 38
Quotation No.: CE-210043 Rev 0 21th September, 2021
The IA/UA compressor sarts automatically once the utility air receiver pressure reaches the low level. The
IA/UA Compressor is programmed with auto start/Stop function .
Material of construction :
Type : Vertical
Dimension : xxxxxxx
Type : Vertical
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 39
Quotation No.: CE-210043 Rev 0 21th September, 2021
Dimension : xxxxxxxxx
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 40
Quotation No.: CE-210043 Rev 0 21th September, 2021
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 41
Quotation No.: CE-210043 Rev 0 21th September, 2021
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 42
Quotation No.: CE-210043 Rev 0 21th September, 2021
PLC Panel:
The proposed PLC system shall be used for control and monitor of Dew Point Unit and suitable for Safe
Area.
The proposed system is of PLC based system (Siemens make) PLC with simplex IO s.
We have considered a sheet steel enclosure IP55 rated suitable to be placed in safe area.
A 7” HMI has been proposed to control and monitor the system. HMI shall be mounted SS316 Enclosure.
The proposed HMI will be communicating with the PLC via Ethernet based network.
PLC control system comprises of the following main items:
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 43
Quotation No.: CE-210043 Rev 0 21th September, 2021
We have considered 400A Auto Transfer Switch (ATS) controlled Change Over system for 400 Volts, 3 PH,
50 Hz incoming supply from 2 no’s diesel generator in Power Distribution and ATS Panel with Motor
Control Center.
Following starters for 3 phase pump motors and Air cooler have considered in the MCC section.
The same panel will be equipped with single phase feeder for lighting distribution, PLC power and
container utility. Single phase voltage shall be derived internally using power transformers which shall be
installed inside the distribution section.
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 44
Quotation No.: CE-210043 Rev 0 21th September, 2021
Engineering, Fabrication, Testing and Supply of Power Distribution and ATS Panel with Motor Control
Center built in sheet steel, RAL 7035, IP42 safe area enclosure suitable to install in container completed
with following sections:
400A Auto Transfer Switch (ATS) controlled Change Over system for 400 Volts, 3 PH, 50 Hz incoming supply
from 2 no’s Diesel generator completed with following:
- 2 X 400A 3P MCCB with motor mechanism
- Electrical and Mechanical Interlock
- 1 X ATS Controller
- Open Closed Indication lamps for incomers
- Ammeter with ASS for both incoming supply
- Voltmeter with VSS for both incoming supply
2. Motor Control center with 2 X 3.7kW & 2 X 5.5KW DOL Starter:
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 45
Quotation No.: CE-210043 Rev 0 21th September, 2021
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 46
Quotation No.: CE-210043 Rev 0 21th September, 2021
The pressure instruments in fuel gas line are hooked up with manual ball valve. Stainless steel pneumatic
tubing and process impulse lines, within the skid edge, are included.
Electrical wiring will be run on cable trays between instruments and skid edge Junction Box.
All the wetted parts for the instruments shall be minimum of SS 316.
No Intrinsically safe instruments are accounted in our scope of supply.
We have not accounted for any DBB for Instrument isolation, Diaphragm seal for the pressure instruments
in our scope.
Cables, Cable Glands and others:
- We have considered UAE made Cable trays with HDG Material, flame retardant
cables, Nickel plated brass cable gland, SS316 tubing and fitting
- All instruments shall directly terminate to skid edge JB. Analog (Both AI and AO) signals shall be
terminated in One Junction box. Similarly, All digital signals shall be terminated in another JB
- We have not considered any specific AVL for E&I bulk materials. But standard materials shall be
used.
- We considered FLUKE-789 and multi meters, and DC power supply for the continuity and valve
stroke test. Requirement of additional instruments like Hart communicator shall be chargeable.
- We have considered supply of consumable items for the termination of cables at instrument side as
well as panel side and is listed below
1. Ferrules
2. Sleeves
3. Lugs
4. Teflon sheet
5. PVC coated SS Cable Ties
6. Cable tags
- The following test are considered in our scope
Megger Test
Continuity test
Functional testing of instruments
Interconnecting Cabling:
We have considered the following for the Off Skid Cabling till the Control Room
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 47
Quotation No.: CE-210043 Rev 0 21th September, 2021
Lighting:
We have considered Exd certified lighting fixture with two (2) Nos in each skid.
Approx 18 Watts Flourescent Light Fixtures provided suitable for Zone 2.
Lighting cable in each skid shall be installed as loop in loop out method. No Separate Lighting junction box
considered in skid.
Light shall be operated from container
Control Room:
20 ft Container for the Control room is provided. This cabin is designed and built for operation in Safe area.
PLC Panel and Power Distribution and ATS Panel with Motor Control Center are placed in the Control.
This will be provided with Work Station with following:
1. 1 Table
2. 3 Chairs
3. Air Condition
External Dimensions of Container: 6058mm Length x 2438mm Width x 2896mm Height
FLOORING:
Floor is covered with Insulated Rubber Floor Matting (1000 V) fixed above 9 mm FC screwed above existing
container floor of 28mm marine ply which is fixed to the bottom structures of the container.
Bottom cable entry provision for the LV panels will be provided with structural support on the container
floor
ROOF & WALL CLADDING:
Composed of Insulated composite panels as per the following specification;
Outer Skin (Exposed to container wall): 0.5 mm thick GI sheet pre painted , low ribbed.
Insulation: Fire rated Class-B2 PIR 38 to 40Kg/M³ Density.
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 48
Quotation No.: CE-210043 Rev 0 21th September, 2021
Inner Skin: 0.5 mm thick GI sheet pre painted polyester coated RAL 9002(Off White) white colour of low
ribbed.
Overall thickness: Walls & Roof 50 mm.
AIR CONDITION:
Split type AC unit with Cooling & Heating temperature will be provided with external frame for compressor
unit.
Capacity: 2.5 Ton, Qty : 1 no’s .Per container
ELECTRICALS:
All the electrical fittings & wiring system will be exposed on the walls. GI trunkings and conduits will be
used as trunk lines for internal wiring.
Container will have separate DB and Power inlet with following items
- The Distribution Board shall be 415VAC, 3Ph, 4 wires + E, 50Hz, wall mounted, IP42 minimum,
- Twin Sockets
- Double Fluorescent internal Lights
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 49
Quotation No.: CE-210043 Rev 0 21th September, 2021
No: of
Item
Description Unit Total Qty Engineers Remarks
No:
Assigned
Client to provide
Supervision for Erection , Pre
necessary Manpower
1 Commissioning , Start – up & Man-days 20 1
during the Erection ,
Commissioning activities
Commissioning activities
Client to advise the
2 Training at Site Man-days 5 1 Total Strength for
Training
To be arranged by Client
near to Site , If far from
4 Lodging and Boarding 2 site then client to
provide daily
transportation till site
Not Included / To be
5 Working on Holidays
discussed
We will also consider provision for remote monitoring of the complete Asset by connecting it to
cloud. This will allow gaining insight to improve complete asset maintenance and operational
efficiency.
These data can be monitored by experts and provide operational level advises. All data will be
continuously logged throughout the year and hourly, weekly or monthly trends can be generated
for further analysis.
Furthermore, there will be also provision for receiving critical alerts via Microsoft teams, Mail and
SMS during critical events or process upsets.
A remote support engineer, to monitor and control these operations and assist the field engineers
whenever required.
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 50
Quotation No.: CE-210043 Rev 0 21th September, 2021
- For Shell & End plates (Insulated) for bath heater - SA 2.5 Blasted
2 Coats Epoxy – 150 Microns
Total Dry Film Thickness – 150 Microns
- For Expansion Tank, Process Inlet / Outlet Header ( Uninsulated) for bath heater
3 Coats –Epoxy – 200 Microns
Total Dry Film Thickness – 200 Microns
- For Stack (Uninsulated operating at 100 to 537 deg C) As per Crescent Recommendations for bath
heater
Primer Coat – Inorganic Zinc rich primer- 50 Microns
Mid Coat – Silicone Aluminium – 25 Microns
Final Coat – Silicone Aluminium – 25 Microns
Color – Aluminium
- For Inlet Separator , ACHE, Gas/ Gas Exchanger, Flow meter Skid ,MP Flash Drum, API Gravity
Separator and its associated Piping - SA 2.5 Blasted
3 Coats – Epoxy – 150 Microns
- Mechanically cleaned of mill scale, slag and fabrication debris. There is no Internal coating required
for the vessel in this Project.
Insulation:
- Inlet Separator , ACHE, Gas/ Gas Exchanger, Flow meter Skid ,MP Flash Drum, API Gravity Separator
and its associated Piping
Not Provided
- LT Separator and piping till the Gas Gas Exchanger
Type – Cold Insulation (Cold Conservation)
Insulation Material – Cellular Glass/ Fibre Glass/ Equivalent
Insulation Thickness – Piping - 3inch and above – 2.5 inch to 3 inch
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 51
Quotation No.: CE-210043 Rev 0 21th September, 2021
Miscellaneous
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 52
Quotation No.: CE-210043 Rev 0 21th September, 2021
- Shipment Preparation:
Fragile instruments and controls are removed and boxed for protection in shipment. All vessel
openings are provided with protective covers. Stack and expansion tank may be removed for
shipping
No Nitrogen purging or special Vapor phase corrosion inhibitors considered for packing during
shipment.
Best preservation/storage practices and storage requirements and any additional scope
requirements, shall be mutually determined at the appropriate time. This will be with price adder if
any.
Exclusion
- TO BE ADDED
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 53
Quotation No.: CE-210043 Rev 0 21th September, 2021
1. Considering the large heat duty requirement we have proposed the heater to be designed for 2x 50%
Configuration.
Our design is based on Natural draft Indirect gas fired bath heater; each with the process duty
requirement of about 13 MM Btu/HR.
2. Since Site location details are not provided we have considered Elevation as 500 Mtrs.
3. RFQ Datasheet refer for process gas M.W. as 17.18 ; however based on the provided gas composition
M.W is calculated to be 16.4; we have considered Process gas Molecular weight as 16.4 for the heater
design. Client to confirm.
4. Client to advise the fuel gas composition and feed conditions as this information is required to finalise
the fuel gas train. Currently we have considered 2 inch line size for both common and individual fuel
train lines. Fuel gas line size to be confirmed later.
5. Client to clarify if there is any minimum Stack height and emission requirement to meet the local
regulations on this project.
6. The Process Coil is designed and manufactured based on Seamless pipe of 6 inch Sch 80 A 333 Gr 6
Materials; if welded type piping materials is required then we have to go with 6 inch Sch 120 and this
will change the heater design due to higher pressure drop.
7. We have not accounted for any heat tracing mainly on the fuel gas line; client to confirm if required; we
can provide with additional price.
8. Please note that typically the Shell is designed to Atmospheric Pressure +Static head and is a Non Code
Design.
Crescent Engineering proposed process coils/connections will be designed and built in accordance to
ASME Sec VIII Div 1.
Heater Shell and Expansion tank will be Non-code, designed for atmospheric pressure; they are not
designed to ASME Code.
Fuel Train piping will be per ASME B31.3 Process Piping.
9. MOC will be as per the materials specified above and client Specification; Crescent will not take any
responsibility for the selection of MOC and thereby guarantee for any design life required on this
project.
We have considered material certification as per BS EN 10204 as below
Plate material (pressure part) : Type 3.1
Gasket & Fasteners : Type 2.2
Non-Pressure parts/ Structure : Type 2.1
10. There will be Level gauge provided on the expansion tank and level transmitter / switch on the Shell to
monitor the level in the bath heater and to safe guard the heater.
Water make up in the heater will not be a continuous operation.
11. Water bath temperature is monitored by Temperature transmitter which sends a signal to package PLC.
Temperature transmitter to be installed at the outlet Header measures the temperature of the process
gas at the Outlet of heater.
The Temperature control valve on the fuel gas line controls the fuel input at main gas line and this in
turn maintains the temperatures at water bath and gas outlet. This is achieved via the Low select logic
between Bath temperature controller and Process outlet temperature controller Low select logic.
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 54
Quotation No.: CE-210043 Rev 0 21th September, 2021
The lowest PID controller output shall be selected between two TICs and shall control the TCV
accordingly. Both the controllers shall be reverse acting PID controllers and the controller output shall
increase when the temperature falls below the respective set points.
12. The Fuel gas line for each burner (fire box) with main line and pilot line; Main Line will be provided with
Direct Acting pressure regulator followed by PSV , Pressure gauge, Pressure transmitter or Switch for
low low alarm, two (2) pneumatic Operated Shutdown valve and a vent line in between SDV are with
solenoid valve and then control valve on main burner line.
Pilot line will be tubing with Direct Acting Pressure regulator followed by Solenoid valve and Pressure
gauge.
The fuel gas train will be provided with all necessary isolation valves; and instruments.
NFPA 87 is the one which is applicable for Indirect fired heater and we comply with its requirements.
The MOC for the isolation valves on fuel gas train will be with CS Body and SS Trim; other wetted part of
the instruments will be SS.
Fuel Gas Piping will be with Piping Class A01B.
13. MOC will be as per the materials specified above and client Specification; Crescent will not take any
responsibility for the selection of MOC and thereby guarantee for any design life required on this
project.
14. The bath heater will be provided with Inlet / Outlet Header; we are not offering Inlet / Outlet piping
with any inlet Outlet Isolation valves. This to be taken care by client. Our battery limit will be
terminated till the Inlet /Outlet header.
Inlet Header will be provided with Pressure gauge and temperature gauge.
Outlet header will be provided with Pressure gauge and temperature transmitter.
15. One (1”) test port is provided on stack for emission monitoring. We are not offering any monitoring
system (CEMS) with the offer.
16. Insulation is provided for Heater Shell and End Plates. Expansion Tank and Process headers are not
insulated.
17. We have not accounted for any intrinsically safe instruments in our package.
18. Crescent Engineering sizing calculations are proprietary and will be not provided. We shall submit the
heater datasheet during project execution.
19. We have accounted for 3D modelling for the bath heater in our current offer.
Client to confirm if we are required to participate for any Hazop Meeting; currently we have included
attending HAZOP in UAE or by video conference only. We have not included any travel to visit client’s
office in Turkey.
20. We understand that there is No Restriction to country of Origin for the materials.
Considering the quantity for the bought out items; the Materials/ Equipment’s offered shall be
manufactured and supplied from suppliers approved by Crescent Internal approved manufacturers who
got a good track record with us.
We can provide the Credentials of the Manufacturers prior to Award if required by client.
There are no AVL issued with the RFQ; If issued we shall review and comply with price impact.
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 55
Quotation No.: CE-210043 Rev 0 21th September, 2021
21. We are not considering HIC Tested Plates or the plates tested for HIC for the bath heater shell. The
pipes, flanges and fitting offered are not with any or complying with any HIC testing requirements.
Radiography if any will be carried out using Gamma source. We have not accounted for any ultrasonic
test in this project.
22. Manual valve offered on the Shell are with Carbon steel body and SS Trim; considering the sizes
required for this project all the manual valves will be Socket welded or threaded for 2” and below.
Inspection /testing requirement considered for the manual Valves are with 100% Visual and PMI only;
Being low pressure valves ; we have not accounted for any RT, MPT, and DPT for the valves. Client to
provide if any specific NDE test to be carried out for the valves required in the fuel gas line.
We have not accounted for any DBB Valves for Instruments isolation in the fuel gas line and for the
instruments directly mounted on the Bath heater Shell.
23. All fuel train piping >= 2” nominal pipe size shall have flanged type connections wherever it is practical,
otherwise NPT and/or welded connections will be used as selected by Crescent. Piping < 2” nominal
pipe size shall be NPT and/or welded as selected by Crescent.
24. Shell is leak tested with liquid fill for any leaks at static head only. Fire tube leak test is performed by
inserting it into the shell during the shell leak test and checking for any water entrainment into the fire
tube (visual inspection only). All other tests will be per Crescent standards. Test procedures will be
submitted for information only.
25. P&ID, GA drawing and all other documents will be per Crescent format i.e., tagging / numbering
philosophy will be in Crescent standard format. They can be provided in other formats if required by
customer.
26. Post order, submittal documents will be P&ID, GA Drawing. GA Drawing does not include any internal(s)
details. All other documents & drawings (including fabrication drawings) will not be provided as a part
of Crescent offering in this proposal.
27. Crescent will be released to purchase long lead materials (shell plate, burner, coil and others) prior to
client’s final drawing approval. If otherwise, delays will occur.
28. No taxes, permits, licenses or inspection fees are included in the price quoted except for those items
applicable to the design and manufacture (and shipment, if applicable) of this equipment. No sales or
use taxes are included.
29. VDRL (Vendor Document Release List) and ITP (Inspection Test Plan) are offered as our Crescent
standard. If different documentation is required, it will need to be discussed and agreed upon prior to
Award.
30. Crescent standard terms, conditions, warranties & guarantees as described below shall apply.
31. All files/documentation submitted as part of the transmittal process may not be text searchable,
especially some of the vendor documents/parts.
PRICING
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 56
Quotation No.: CE-210043 Rev 0 21th September, 2021
Total Price
Item No: Description
USD
2 Process design & Performance Guarantee Test Run for the package for ---- Included
3 Documentation Included
4 Packing Included
VALIDITY
The quoted prices are fixed and firm for the contract delivery period subject to acceptance within thirty
(30) days from date of the proposal.
Due to the current variability in materials prices, this quotation is based on current material prices which
are in effect at time of order. In the event Crescent is the successful bidder we must verify prices prior to
accepting any orders.
PAYMENT TERMS
Net thirty (30) days from date of invoice and payment terms per the following schedule:
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 57
Quotation No.: CE-210043 Rev 0 21th September, 2021
Additional 5% VAT will be applicable on total invoice value. Currently VAT is not included in above price and
to be discussed prior to Award.
General Notes:
1. One (1) set of the operations manual will be provided within two weeks from the date of shipment.
2. Crescent shall provide relevant drawings or documents for the project, excluding proprietary
drawings and documents.
3. All drawings submitted for approval to buyer/buyers appointed representative must be returned to
Crescent as approved, approved with Changes, or with some other affirmative indication of
approval to proceed with release for fabrication.
CONSTRUCTION SCHEDULE
Process Documents like PFD /P&IDs will be submitted two (2) to Four (4) weeks after acceptance of order
(AOA).
The unit will be ready for shipment in 24 Weeks after receipt of approved PFD and P&ID’s.
To meet the delivery schedule, we are not expecting any Document approval cycle is required to comply
other than PFD & P&ID.
We can discuss and improve the delivery time once firm ordering date is in place.
Drawing and fabrication schedules are based on engineering and shop loads as well as material availability
at the time of quotation. These schedules could change; we therefore reserve the right to review this
portion of our proposal prior to order placement, and revise if necessary.
QUALITY ASSURANCE
Crescent and all affiliated companies performing any of the work as part of this project are certified ISO
9001 and operate a full Quality Assurance/Quality Control program in accordance with the requirements of
the ASME Code.
Crescent Engineering Director of Quality has full responsibility for implementation and control of total
project/product quality. The Quality and/or Code manuals are available at all times on site at
manufacturer’s facility for client's review purposes.
Start-up, pre-commissioning and commissioning and Training are not included in the base price. If
requested the service of a start-up engineer to assist on installation or start-up will be provided at the rate
in effect at time of need. This will include travel time. Living and travel expenses will be billed for the
actual expenses incurred.
SHIPMENT PREPARATION
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 58
Quotation No.: CE-210043 Rev 0 21th September, 2021
The equipment would be made available for shipping, uncrated, with all openings plugged or covered to
prevent the ingress of moisture or foreign material.
Instruments and accessories, which are liable to damage during transit, will be dismantled, tagged and
packed in a crate(s). Re-assembly of such items on site would be by others.
Pricing does not include taxes, export packing, duties, or freight unless otherwise noted. Freight and
packing can be included by Crescent on a pre-pay and add basis at a cost plus 10% handling fee. Should the
outlined scope of supply change, pricing is subject to change as well.
LIMIT OF LIABILITY
In no event shall either party be liable to the other for any indirect or consequential damage of any nature
or kind arising from this contract unless such consequential loss, liability, damage or claim was caused by
the negligence or recklessness or willful misconduct of suppliers or any servants or agents of supplier or any
partner affiliates or subsidiaries. Companies or sub-contractor suppliers shall not be liable for any
consequential loss in respect of loss of use, loss of profits, or loss of production.
ASSIGNMENT
Any transaction resulting from this quotation shall not be assignable by either party without the prior
written consent of the other party hereto, except that any transaction may be assigned without such
consent to the successor of either party acquiring all or substantially all of the business and assets of such
party.
POLITICAL RISK
Notwithstanding anything to the contrary herein, this order is not cancelable by buyer, its client, or the
ultimate end user due to force majeure, EXCEPT acts of God. Should buyer, its client, or the ultimate end
user wish to cancel this order for any situation other than acts of God, said cancellation shall be considered
to be "Cancellation for Convenience" and seller shall be paid for all costs incurred by it to the date of
cancellation and all reasonable costs incurred in effecting the cancellation.
FORCE MAJEURE
Any delay in or failure to perform by a party, other than the payment of money, shall not constitute a
default that exposes it to liability for breach if and to the extent the delay or failure to perform is caused by
an occurrence beyond the reasonable control of the party, including, but not limited to, an act of God or
the public enemy; expropriation or confiscation of facilities; compliance with any order or requirement or
any governmental authority; act of war, rebellion or sabotage or damage resulting therefrom; fire, flood,
explosion or accident; riots or strikes or other concerted acts of workmen; inability after diligent effort to
obtain necessary licenses or permits; the delay or inability of Crescent to secure products, parts, materials,
fuel, supplies, equipment or power at reasonable prices or in sufficient amount through usual sources of
supply; or any other cause, whether or not of the same class or kind as those specifically above named,
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 59
Quotation No.: CE-210043 Rev 0 21th September, 2021
which is not within the control of the party and which, by the exercise of reasonable diligence, the party is
unable to prevent or remedy (force majeure).
In the event of force majeure, the party claiming force majeure shall furnish the other party with written
notice or by telephone immediately confirmed in writing, setting forth the full particulars of the force
majeure claimed, as soon as possible after the occurrence of the force majeure, and the obligations of that
party, so far as they are affected by such force majeure, shall be suspended during the continuance of any
inability so caused, but for no longer. The party relying upon such force majeure shall use due diligence
and all reasonable efforts, including, but not limited to, reasonable expenditure of money, to overcome the
cause of force majeure. If a force majeure event exceeds 45 days, either party may cancel this order
subject to the Cancellation Schedule below.
ACCEPTANCE
Before releasing equipment for shipment, a signed statement of acceptance is required of customer. A
complete check out and functional test of components are to be witnessed by customer prior to signing this
release. Upon equipment arrival at job site a visual inspection is required prior to signing the bill of lading
submitted by carrier. Any damages to the equipment or its components are to be filed with the carrier, and
Crescent is to be notified. Such inspection without objection or failure to inspect within five (5) days after
equipment delivery shall constitute acceptance thereof as being in conformity with the order and
purchaser waives any damages not reported.
MECHANICAL WARRANTY
Crescent warrants new products of its manufacture to be free from defective workmanship and material
for a period of twelve (12) months from the date of equipment start-up or eighteen (18) months from the
date of transmittal of notice of readiness for shipment to customer, whichever period expires first,
provided customer subjects the equipment only to the operating conditions specified by customer when
the order is placed and in accordance with Crescent's written operating instruction, if any.
Crescent does not warrant components manufactured by others, but shall exert good faith effort to assign
such components manufacturer's guarantee to customer. In the event of a breach of this warranty,
Crescent's obligation is limited to replacement of the defective equipment, Ex Works fabrication plant.
No allowance will be granted for repairs or alterations made by customer without option, either to repair
the defective part or furnish a replacement without written consent. Equipment performance guarantees, if
any are limited to those specifically enumerated in the quotation.
Crescent makes no warranty with respect to service work, to parts requiring replacement due to wear and
tear, to used equipment, or to painting/coating/lining. There are no other warranties, except for the
warranty expressly stated above, and none shall be implied by law, including those of merchantability and
fitness for a particular purpose.
PROCESS WARRANTY
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 60
Quotation No.: CE-210043 Rev 0 21th September, 2021
Crescent warrants the equipment shall perform as described in the “Process Design Basis” for a period of
twelve (12) months from the date of equipment start-up or eighteen (18) months from the date of delivery,
whichever expires first, provided the inlet fluid composition, capacity, conditions and properties form such
“Process Design Conditions” are provided by the client or others. This Warranty is valid only if the
equipment is operated according to the operating conditions specified by customer when the order is
placed and in accordance with Crescent’s written operating instruction, if any.
Crescent makes no representation as to the accuracy of the client inlet data, nor any client-supplied design,
equipment or use data. Our Process Warranty exclusively covers only those system components specifically
designed or specified by us to control the process outputs/parameters. As such, this Process Warranty
specifically excludes mechanical, electrical, control, instruments, accessories, pneumatic devices, internals,
components and/or systems that are designed, selected and specified by others.
Crescent does not warrant components manufactured by others, but shall exert good faith effort to assign
such components manufacturer's guarantee to customer.
There are no other warranties, except for those expressly stated herein, and none shall be implied by law,
including those of merchantability and fitness for a particular purpose.
CANCELLATION SCHEDULE
The cancellation or termination of this project after customer's authorization to proceed, shall result in the
customer's paying all costs, expenses, losses and damages sustained by Crescent in connection with such
cancellation or termination, including administrative and engineering expense and loss of anticipated
profits. This charge shall be less any credit received for returned materials, but shall include all re-stocking,
freight and handling charges.
INSURANCE
The Prices quoted include insurance of the equipment up to "Pass of the Title".
INSPECTION
CHANGE ORDER
Once an order is received and additions or deletions are required, a lump sum, net price, plus or minus, and
revised delivery date, if applicable, will be submitted to the customer's office for approval.
The engineering change order will include:
* Project engineering and related changes
* Drafting changes and related costs
* Material costs
* Freight deliveries and/or restocking costs
P.O. Box 117030, Dubai, United Arab Emirates, Tel. +971 4 817 3333 Fax. +971 4 880 2000 www.crescent-me.com
Page 61
Quotation No.: CE-210043 Rev 0 21th September, 2021
* Administration charges
* Project delivery revisions
SPARE PARTS
2 years Spare parts price to be provided during Detail Engineering once we finalize the sub vendors. We
have found it is not possible to provide accurate spare parts list and costs until agreement is reached on
what specific equipment, valves, instruments, and controls are to be supplied.
Thank you for the opportunity to provide this quotation. If you have any questions or need additional
information, please feel free to contact us.
Regards,
Julian Hill
General Manager
Crescent Engineering FZE
Attachment
1. Process Flow Diagram
2. P&ID
3. Block Diagram for I&C