Download as pdf or txt
Download as pdf or txt
You are on page 1of 29

SECTION G: MATERIAL

REQUIREMENTS PLANNING
Section G Introduction

Section G Learning Objectives


▪ MRP translates independent demand into time-phased
dependent demand for components (priority plans)
▪ Inputs: bill of material (BOM), inventory status, planning
data
▪ Capacity requirements planning checks
▪ Single- and multilevel BOMs, planning bills, where-used,
and pegging
▪ Parent-child relationships, explosions, and offsetting
▪ MRP grid, gross and net requirements, planned order
releases and receipts, scheduled receipts
▪ Expediting, de-expediting, changes

Section G ■ 2 © 2020 APICS Confidential and Proprietary


Section G Introduction

Manufacturing Planning and Control

Section G ■ 3 © 2020 APICS Confidential and Proprietary


Topic 1: The MRP Environment

Objectives of MRP

Planning Control

▪ Precise material ▪ Adapt to changing priorities


requirements ▪ Demand changes, supply
▪ What, how much, and when issues, errors
▪ What to get from inventory ▪ Update multiple details
▪ What to order, when to ▪ Planners able to expedite,
order, when to schedule de-expedite, add, cancel, or
delivery change planned orders

Section G ■ 4 © 2020 APICS Confidential and Proprietary


Topic 1: The MRP Environment

Inputs, Process, and Outputs


Input Description Source
MPS Quantities, due dates as planned and Master schedule
scheduled orders
Bills of material Quantity of each uniquely identified part Product structure file
(BOMs) to make one item
Planning factors Static inventory data: Inventory records: item
• Lot size master file
• Lead time
• Yield/scrap factors
• Safety stock level
Inventory status Dynamic inventory data for Inventory records:
components/items (on hand, allocated, inventory record file
on order with due date)

Process: time-phased priority plan with proposed release and receipt dates.
Outputs: purchase orders to suppliers (via purchasing) and CRP-validated
manufacturing orders to shop floor.
Section G ■ 5 © 2020 APICS Confidential and Proprietary
Topic 2: Bills of Material

Bill of Material Concepts


Single unit: All parts to
Unique ID: All parts get unique part make exactly one unit of
number. (If form, fit, or function Part Number 100.
changes, part gets new number.)

Scope: If it isn’t listed, it isn’t used (but some Quantities


MRO supplies might be used but not listed). Unit of
Section G ■ 6 © 2020 APICS Confidential and Proprietary measure
Topic 2: Bills of Material

Independent vs. Dependent and Parent-Child


Since Part Number 100 is a unit for individual sale...

*Also called parent-component relationship

Section G ■ 7 © 2020 APICS Confidential and Proprietary


Topic 2: Bills of Material

How BOMs Are Used in Organizations


▪ Engineering
– Part of specifications for new or improved products
– For example, chemical formula BOMs
– Engineering change control and start/stop dates for new
BOMs or components
▪ Customer service and service parts
– Right replacement part
– Customer options (ATO): custom BOM maybe with costs
▪ Finance
– Direct materials costing, direct labor estimates, overhead
allocation

Section G ■ 8 © 2020 APICS Confidential and Proprietary


Topic 2: Bills of Material

Single-Level BOMs
▪ Data in only one place, available for multiple products.
▪ Each part can have its own single-level BOM.
(Part 202 is a child of Part 100.)

Children (components) of Part 202


Section G ■ 9 © 2020 APICS Confidential and Proprietary
Topic 2: Bills of Material

Multilevel BOMs: Indented and Summarized Bills

Can expand

Can’t expand
Section G ■ 10 © 2020 APICS Confidential and Proprietary more (purchased)
Topic 2: Bills of Material

Multilevel BOMs: Indented and Summarized Bills


Series of single-
level bills
▪ All final children
(no levels below)
are purchased.
▪ Shows logical
order of assembly
from bottom up.

Section G ■ 11 © 2020 APICS Confidential and Proprietary


Topic 2: Bills of Material

Planning Bills of Material


▪ Simplify planning: Can’t know what to ATO
▪ Historical average of demand for options

Section G ■ 12 © 2020 APICS Confidential and Proprietary


Topic 2: Bills of Material

Where-Used and Pegging Data


▪ Where-used: Full list of parents using that child
– Impact of engineering change
▪ Pegging: Just parents with gross requirements
– Due dates and quantities of parent MPS orders
– Supply chain issues, material prices

Section G ■ 13 © 2020 APICS Confidential and Proprietary


Topic 3: MRP Logic

MRP Logic Available at


beginning of Time bucket
period shown
On item master record:
• Lead time: 2 weeks Week
Part Number 202
• Lot size: 100 units
From MPS (before inventory)
Released orders (committed)
Inventory balance into future
After inventory and receipts
Due date (still just plans)
When to order or make
Lead time offset

Production is scheduled only when there is demand.


Section G ■ 14 © 2020 APICS Confidential and Proprietary
Topic 3: MRP Logic

MRP Record (Exercise)


Lead time: 1 week
Pegging (week 2): 30 for product X
40 for product Y
Lot size: as required
Week
Part A
1 2 3 4
Gross requirements 70 60 50
Scheduled receipts 50
Projected available 20
Net requirement
Planned order receipt
Planned order release
Section G ■ 15 © 2020 APICS Confidential and Proprietary
Topic 3: MRP Logic

Bill-of-Material Explosion (Exploding)


Parent A B D F
Child B (2) E (2) F (2) C (1)
Child C (4) G (3) E (2)
Child D (2) H (1) G (4)

Section G ■ 16 © 2020 APICS Confidential and Proprietary


Topic 3: MRP Logic

Bill of Material Product Tree Exercise


Parent A B C E
Component B (2) E (2) G (2) G (4)
C (4) F (1) F (3)
D (3) H (2)

Given the parents and components, construct a product


tree. Figures in brackets show the quantities per item.

Section G ■ 17 © 2020 APICS Confidential and Proprietary


Topic 3: MRP Logic

Lead-Time Offset (Offsetting)

Section G ■ 19 © 2020 APICS Confidential and Proprietary


Topic 3: MRP Logic

Offsetting Planned Order Releases from Receipts

Section G ■ 20 © 2020 APICS Confidential and Proprietary


Topic 3: MRP Logic

POR Exercise 1
Quantity per parent What is the cumulative
in all cases = 1 lead time for item B?

Item Week
number Planned order 1 2 3 4 5
Receipt 50
B Release 50
Receipt
C Release
Receipt 50
D Release 50
Receipt
E Release
Receipt
F Release
Wk = Week; LT = lead time
Section G ■ 21 © 2020 APICS Confidential and Proprietary
Topic 3: MRP Logic

POR Exercise 2
Quantity per parent
in all cases = 1

Item Week
number Planned order 1 2 3 4 5
Receipt 200
X Release
Receipt
Y Release
Receipt
Z Release
Receipt
W Release
Receipt
V Release
Wk = Week; LT = lead time
Section G ■ 22 © 2020 APICS Confidential and Proprietary
Topic 3: MRP Logic

Projected Available
Projected Available = Prior Projected
Available + Scheduled Receipts + Planned
Order Receipts − Gross Requirements

Part C,
Week 3:
7+0+0
−4=3

Part E,
Week 2:
4+5+0
−0=9

Section G ■ 23 © 2020 APICS Confidential and Proprietary


Topic 3: MRP Logic
Gross to Net Requirements

Net Requirements =
Gross Requirements − Scheduled Receipts − Prior Projected
Available

Part C, Week 5:
4−0−3=1

Part G, Week 3:
16 − 0 − 13 = 3

Section G ■ 24 © 2020 APICS Confidential and Proprietary


Topic 3: MRP Logic

Completed MRP
Lot size rule =
5 units

Part E, Week 4,
projected available:
1+0+5−4=2

Part G, Week 4, net


requirements:
6−0−2=4

Section G ■ 25 © 2020 APICS Confidential and Proprietary


Topic 3: MRP Logic

Bucketless MRP and CRP


Bucketless MRP Capacity requirements
planning
▪ List actual dates for actions ▪ Detailed capacity check at
and omit periods of no activity MRP level
▪ More common in practice

Section G ■ 26 © 2020 APICS Confidential and Proprietary


Topic 3: MRP Logic

MRP in Lean
▪ MRP is inherently push; lean is pull, uses kanban.
▪ Lean may have push components and use MRP for items
with longer lead times than customer lead times.
▪ Daily (sometimes weekly) time buckets.
▪ Very low or zero inventory.
▪ Lot-for-lot: very low lot sizes.
▪ Gross requirement and production may be in same period.
▪ Simplify and flatten BOMs (e.g., since cellular effectively
creates one big work center).

Section G ■ 27 © 2020 APICS Confidential and Proprietary


Topic 4: Using and Managing the Priority Plan

MRP Planning Software

Automated Planner prompts (usually)

▪ Exploding, offsetting, and ▪ Action messages


gross to net – Planned order releases in
action bucket
▪ Checking on hand, on order,
– Autorelease risk (“computer
allocated inventory did it” not valid excuse)
▪ Generating scheduled receipts ▪ Exception messages
and allocating components – Release, add, cancel
▪ Replanning (planner initiates, – Insufficient quantity or
system recalculates due receipt date: expediting
dates) – Slack time: de-expediting
Section G ■ 28 © 2020 APICS Confidential and Proprietary
Topic 4: Using and Managing the Priority Plan

Order Control
▪ Releasing is decision point: commit money or time.
▪ Release in action bucket: deletes planned order/receipt, replaces with
scheduled receipt.
▪ Firm planned order to reduce system nervousness.

Released (open) order

Planned order Firm planned order


Section G ■ 29 © 2020 APICS Confidential and Proprietary
Topic 4: Using and Managing the Priority Plan

Maintaining Priorities and Replanning


▪ Maintaining priorities
▪ Internal events
(expediting/de-expediting)
is first option, replanning – Lower yield or scrap
(new due dates) is fallback. factors
▪ External events – Early or late completions
– Customer order changes (standard vs. actual time)
– Supplier shortages – Capacity or resource
– Wrong quantities or constraints
damage – Inventory record errors
– Late deliveries

Section G ■ 30 © 2020 APICS Confidential and Proprietary

You might also like