SPP Document 201 ---------Architectural research entails the conduct

of primary and secondary researches and


SCOPE OF PRE-DESIGN SERVICES assembled facts used as basis for conclusion.
1-12.
------------The analysis covers the context of the
site as well as that
of its surrounding environment and the
development controls that apply to the site and
its environs.

------------This analytical problem-seeking


-------When a Client calls upon the Architect to process will lead to the statement and
give oral or written advice and direction, to identification of both horizontal and vertical
attend conferences, to make evaluations and requirements in offering a solution.
appraisals regarding a contemplated project and
similar activities -----------The Architect determines the adequate
size and appropriate configuration and
--------cover a broad line of architectural services assemblage for a proposed project in
ranging from initial problem identification to consideration of the use, allocation and interface
activities that would allow the Architect to initially of spaces for given activities.
conceptualize an array of architectural and allied
solutions. ------------It incorporates a space program with
characterizations of the envisioned spaces such
-------the Architect renders valuable inputs as ambiance, cost range, etc.
whether or not the Client pursues the project.
------------is done mainly through primary data
----------These preliminary studies involve the gathering such as interviews, consultations,
procurement, analysis and use of secondary interfaces, focus group discussions (FGDs),
information gathered for the project to aid the space planning surveys, space audits, etc. and
Client in early decision-making subsequent analyses i.e. spatial layouts with
. stacking concepts, particularly for multi-storey
----------Detailed analysis of the project based on structures.
pre-feasibility studies will determine the viability
of a proposed development. ------------An analysis of the space requirements
of the project based on organizational structure
---------They represent the Architect’s and functional set-up pinpoints linkages and
initial assessment of a project’s soundness, interaction of spaces. The formulation of the
allowing the Client to promptly explore available/ space program will serve as the basis for the
readily identifiable directions / options. development of the architectural plan / design.
------------The studies will set the project against
present and future trends to ------------This technique is applied in the cost
forecast how it will perform over time. This management process to minimize the negative
effect of simplified operations associated with
requires primary data gathering and analysis.
many cost-reduction programs.
------------This entails the formulation of site
criteria, assistance to the Client in site ------------the Architect states the project terms of
evaluation as well as analysis to determine the reference (ToR) including the concept,
most appropriate site/s for a proposed project or objectives and other necessary requirements to
building program. bid out architectural services (whether public or
private).
------------The detailed analysis of the site
involves the identification of a site’s ------------is to achieve an unimpaired program at
development potentials through the proper minimum cost. Thus, a plan, design or
utilization of land system that has been successfully value-
managed will still satisfy the same performance
criteria as the costlier alternatives.
------------Projects may require promotional has spent on his work.
activities in order to develop and generate
financial support and acceptance from governing ------------This method of compensation is
agencies or from the general public frequently used where there is continuing
relationship involving
-----------the Architect can act as the agent of the a series of projects.
Owner by producing and coordinating the
additional activities necessary to complete the ------------This method may be applied to
services. In all such activities, the Architect must government projects since they entail more
maintain his professional status as the paper work and time-consuming efforts.
representative of the Owner.
-------------It establishes a fixed sum over and
After the initial meeting / conversation / above the reimbursement for the
correspondence with the Client, the Architect Architect’s technical time and overhead. An
must submit his proposal for pre-design agreement on the general scope of the work is
services, stating the following: necessary in order to set an equitable fee.
1-4.
--------------a Client may request an Architect to
do work which will require his personal time
such as attending project-related meetings,
----------It is possible for Architects (as natural conferences or trips, conducting ocular
persons) working in a single firm to specialize in inspection of possible project sites, conferring
a variety of ways. Many Architects and firms with others regarding prospective investments or
(juridical persons) specialize without losing the ventures and the like
generalist approach of the Architect or firm.
----------------The SPP provides for more than one
-----------Another common practice is method of compensation on a project. Each
consultation between an Architect and a firm of project should be examined to determine the
other disciplines, under the extended terms of most appropriate and equitable method of
the Owner-Architect Agreement. compensation.

METHOD OF COMPENSATION SPP 202


1-5
-----------The Architect’s work starts at the
inception of the project when the Owner outlines
his requirements to the Architect. The work
covers the various aspects of the project, from
analysis and study of the needs and
requirements, to the preparation of the
necessary instruments of service, and finally to
-----------The Architect’s compensation is based the supervision during project implementation. It
on the Architect’s / architectural firm’s talents, ends only when the general contractor or builder
skill, experience, imagination, and on the type turns over the completed project to the
and level of professional services provided. Owner.

-------------This cost-based method of ---------------This phase involves the definition of


compensation is applicable only to non-creative the requirements of the project by the Owner.
work such as accounting, secretarial, research, The Architect in turn informs the Owner of the
data gathering, preparation of reports and the technical requirements of the project and the
like. concomitant professional fees.

-------------This ---------------In regular practice, the Architect acts


method of compensation is based on technical as the Owner’s/ Client's/ Proponent’s Adviser
hours spent and does not account for creative and/or Representative. He translates the
work since the value of creative design cannot Owner's needs and requirements to spaces and
be measured by the length of time the designer forms in the best manner of professional service.
construction, forms for invitation and instruction
------------the Architect consults with the Owner to to bidders, forms for bidders’
ascertain the conceptual framework and related proposals, general / specific conditions of
requirements of the project and confirms such contract, etc
requirements with him, gathers relevant
information and data leading to the definition of -----------submits to the Owner seven (7) sets of
the requirements of the project, including the all construction drawings and technical
scope of the Architect’s services, reviews and specifications for purposes of obtaining a
refines the owner’s space requirements and building permit
translates them into an architectural program,
prepares an initial statement of probable -------------updates the SPPCC based on
construction cost. changes in scope, requirements or market
conditions, assists the Owner in filing the
-------------This phase consists of the preparation required documents to secure approval of
of schematic design studies derived from the government
Project Definition Phase, leading to conceptual authorities having jurisdiction over the design of
plans. the Project

-------------evaluates the Owner’s program, --------------assists the Owner from the early
schedule, budget, project site and proposes stage of establishing a list of prospective
methods of project deliveries, prepares the initial Contractors to awarding of the construction
line drawings representing design studies contract.
leading to a recommended solution, including a
general description of the project for approval by --------------makes decisions on all claims of the
the Owner, submits to the Owner a Statement of Owner and Contractors on all matters relating to
the Probable Project Construction Cost the execution and progress of work or the
(SPPCC) based on current cost parameters interpretation of the Contract Documents

-------------Based on approved schematics and --------------prepares change orders, gathers and


conceptual plans, the Architect prepares the turns over to the Owner written guarantees
Design Development documents consisting of required of the Contractor and Sub-Contractors
plans, elevations, sections and other
Drawings, outline specifications to fix and -------------The Architect shall not be required to
illustrate the size and character of the entire make exhaustive or continuous 8-hour on-site
project as to type of materials, type of structural, supervision to check on the quality of the work
electrical, mechanical, sanitary, electronic and involved and shall not be held responsible for
communications systems, diagrammatic layout the Contractor's failure to carry out the
of construction systems, and updated sppcc Construction work in accordance with the
Contract Documents.
-------------prepares the complete Contract
Documents consisting of detailed designs and -------------- Group 1
construction drawings, setting forth in detail the -------------- Group 2
work required for the architectural, -------------- Group 3
structural, electrical, plumbing/ sanitary, -------------- Group 4
mechanical, electronic and communication -------------- Group 5
works prepared by the Architect and the -------------- Group 6
respective professionals involved. -------------- Group 7
-------------- Group 8
------------prepares Technical Specifications -------------- Group 9
describing type and quality of materials, finish, -------------- Group 10
manner of construction and the general
conditions under which the project is to be METHOD OF COMPENSATION
constructed
1-6
-------------prepares the Bid Documents such as
forms for contract letting, documents for
Scope of Services SPP 202 necessary, they are to be recommended by the
1-5 Architect for the Owner’s approval.

------------shall be chargeable to the Owner


whenever the Architect or his duly authorized
representative is required to perform services at
a locality beyond 50.0 kilometers (air, straight
line or radial distance) from his established
-------------The Architect’s compensation is based office as it appears in the Architect’s letterhead
on the Architect’s / architectural firm’s talents,
skill, experience, imagination, and on the type -------------The Owner shall pay the Architect for
and level of professional services provided. additional sets of Contract Documents.

-----------The Architect’s Fee based on the PPC -------------If the Architect renders additional
shall be detailed in the Architect’s Guidelines professional services due to changes ordered by
the Owner after approval of the Architect’s
-----------This method of compensation is based outputs, the Owner shall pay the Architect for
on technical hours spent and does not account extra time, resources/ drafting, or other office
for creative work since the value of creative expenses.
design cannot be measured by the length of
time the designer has spent on his work. ------------If the work of the Architect is
abandoned or suspended in whole or in part, the
-------------This method of compensation is Owner shall pay the Architect for the services
frequently used where there is continuing rendered corresponding to the amount due at
relationship involving a series of Projects. the stage of suspension or abandonment of the
work.
------------It establishes a fixed sum over and
above the reimbursement for the --------------If portions of the building/s are
Architect’s technical time and overhead. An erected at different periods of time, thus
agreement on the general scope of the work is increasing the construction period and
necessary in order to set an equitable fee. Architect’s burden of services, charges
pertaining to services rendered during the
-----------This method may be applied to Construction Phase shall be adjusted
government projects since they entail more proportionately. When the suspension of
paper work and time-consuming efforts. construction exceeds a period of six (6) months,
the fee for the remaining works shall be
OTHER CONDITIONS ON SERVICES doubled.
1-18
---------------When the Owner therefore fails to
implement the plans and documents for
construction as prepared by the Architect, the
----------Other services that may be needed in Architect is entitled to receive as compensation
order to complete the project such as services of the sum corresponding to ninety percent (90%)
acoustic and illumination engineers / specialists, of the Architect’s fee.
mural painters, sculptors, and other service
providers are to be recommended by the -------------If the Owner requires the services of
Architect for the Owner’s approval specialist consultants, they shall be engaged
with the consent of the Architect. The cost of
---------- The Architect’s Fee is based on the their services shall be paid for separately by the
Project Construction Cost. Where the Architect Owner and shall not be deducted from the
has to render additional services, additional Architect’s fee.
compensation shall be required.
--------------Any SPPCC or any Cost Estimate
-----------Should a scale model, 3D models submitted by the Architect can attain only a
and/or walk-thru presentation of the architect’s certain degree of
design be
accuracy. As the Architect has no control over that shall be placed at the project site during the
the cost of labor and materials, or the many progress of construction shall be approved by
factors that go into competitive bidding, he does the Architect as to size, design and contents.
not assume any professional responsibility for After the completion of the project, the Owner or
such cost estimates, unless glaring errors or his building lessee shall consult the Architect for
discrepancies are clearly evident. the design, size of all signboards, letterings,
directories and display boards that will be placed
----------Should the Owner require the Architect on the exterior or public areas attached to the
to design movable or fixed pieces of cabinets building project in order to safeguard the
and other architectural interior (AI) elements, Owner’s interest. Nothing should be installed
site development plan (SDP) components, inside or outside of the building that would
urban design elements, and other items of compromise its safety and aesthetics.
similar nature, the Owner shall pay the Architect
in addition to the Architect’s fee. --------------means the cost of the completed
building to the Owner, including the structure,
-----------Upon recommendation of the Architect plumbing/sanitary and electrical fixtures,
and with the approval of the Owner, full-time mechanical equipment, elevators, escalators,
construction supervisors as will be deemed air-conditioning system, fire protection system,
necessary shall be engaged and paid by the alarm and clock system, communications and
Owner. If no Project / Construction Manager is electronic system, elements attached to the
present, the full-time construction supervisor building and all items indicated in the plans,
shall be under the technical control and designs, drawings and specifications prepared
supervision of the Architect and shall make by the Architect and his consultants.
periodic reports to the Owner and to the
Architect regarding the progress and quality of ---------------The PCC does not include any of the
the work done. fees for the Architect, the Engineer, the
Specialist Consultants or the salaries of the
----------------The Architect’s Fee is a net amount. construction inspectors.
Any tax (exclusive of income tax) that the
national and/or local government/s may impose ----------------include cost of the construction as
on the Architect as a consequence of the well as all professional fees,
services performed for the project shall be paid permits, clearances and utilities and cost of
by the Owner. acquiring the project site / lot, cost of money,
etc.
--------------During the progress of work, the
Owner shall furnish the Architect a copy of the SPP Document 203
records of expenses being incurred on the
construction. Upon completion of the project, the ------------involves the detailed planning and
Owner shall furnish the Architect a copy of the design of the indoor / enclosed areas of any
summary of all cost of labor, services, materials, proposed building / structure, including retrofit,
equipment, fixtures and all items used at and for renovation, rehabilitation or expansion work
the completion of the construction. which shall cover all architectural and utility
aspects, including the architectural lay-outing of
--------------All designs, drawings, models, all building engineering systems found therein.
specifications and other contract documents and
copies thereof, prepared, duly signed, stamped -------------prescribes space plans, stacking
and sealed and furnished as instruments of diagrams / sections and computations of areas
service, are the intellectual property and for the different activities and spaces to be
documents of the Architect, whether the work for integrated in a building Project.
which they were made is executed or not, and
are not to be reproduced or used on other work ------------lays out and prescribes furniture / built-
except with a written agreement with the ins / equipment for the project and prepares
Architect specifications of AI components including all
floor / wall / ceiling finishes, doors and
-----------All signboards of the General partition systems, hardware, modular or ready-
Contractor, sub-contractors, jobbers and dealers assembled furniture pieces/ systems,
equipment, furnishings, built-ins, fixtures, ----------prepares the drawings and specifications
signages and graphic devices, etc. for lighting design, illumination, fixture
placement, efficiency, energy considerations,
------------assists the Client in conducting bids or etc.
negotiations with General Contractors,
subcontractors and suppliers of building ----------- assists the Owner/ Client in bidding out
materials, furniture, equipment, fixtures, etc. the work or in negotiating with a specialty
subcontractor
------------checks and approves samples of
materials and shop drawings of AI components, ------------checks and approve samples of
reviews and approves billings of AI components, materials and fixtures, assists Owner/ Client to
conducts final inspection and approves installed evaluate the amount due the sub-contractor
AI components and related items
------------means the total cost of all fixtures and
------------involves the detailed planning and accessories, which were either
design to control sound designed, specified or procured by the Specialist
transmission for compatibility with the Architect and/or his Specialist Consultants
architectural design concept. (SCs) for the Owner/ Client, and that were used
or installed in the project.
----------The Architect is the prime professional
commissioned by the Owner/Client to plan and --------------The space planning, architectural lay-
design the building/structure and all its utilities outing and utilization of spaces within and
and to coordinate the works of all allied design surrounding a specific building / structure in
professionals involved in the project including all relation with the existing natural and/or built
inter-disciplinary and specialized works. He environments have to be a well-coordinated
shall make certain that these inputs comply with effort so that both the building / structure and the
the requirements of the project and are host environment shall act as one.
compatible with the architectural design concept.
--------------the Architect is not merely
------------the Architect works on a development concerned with the building / structure he
concept. To realize this, the Architect develops creates but with the grounds and surrounding
the design by determining the size and space as well. He studies the existing
interrelationship of interior spaces, laying out the environment in relation to the building / structure
furniture, movables, equipment, built-ins and and consequently lays out the areas / grounds
fixtures to support the required activities, thus immediately surrounding the building / structure.
making both the exterior and interior spaces
contribute to the total concept. --------------conceptualizes the entire site
development plan (SDP) including the generic
----------prepares the drawings and specifications scope of civil works and the general scope of
for acoustic design and treatment, sound softscape and hardscape requirements.
control and reinforcement, sound absorption,
reflectance, insulation, etc. -------------conceptualizes the specifications for
the needed civil works and utility lines, assists
----------assists the Owner/ Client in bidding out the Owner/Client in bidding out the work or
the work or in negotiating with a specialty negotiating with landscape,
subcontractor, checks and approves samples of waterscape, rock formation contractors, etc., but
materials and equipment mainly when no SC is available.

----------assists Owner/ Client in evaluating the ------------refers to the orderly arrangement within
amount due the sub-contractor a piece of land or property on which
vertical structures such as buildings, monuments
----------involves the detailed planning and and the like, as well as horizontal
design of light transmission, timing and control developments such as rights-of-way (ROWs),
for compatibility with the architectural design open spaces and activity spaces are to be
concept. proposed.
----------The Architect undertakes the site ascertaining the value of structures or facilities
planning of a project that requires a composite which must be fully secured, kept safe,
arrangement of several buildings/ structures and protected, assured, guaranteed and provided
their requisite amenities, facilities, services and sufficient safeguards for the conduct of any work
utilities within a natural or built setting. or activity.

-----------are based on the concept of expanded ------------The Architect in this area of practice
physical planning services to include other engages in methods of producing building
activities necessary for the proper handling of components in a highly engineered, efficient and
the numerous components considered in the cost-effective manner, particularly for residential
formulation, implementation and realization of a and commercial applications
Master Development Plan (MDP).
-------------The Consulting Architect in this area of
------------covers the range of all services from practice provides the Owner/Client with means
primary data gathering through the formulation and measures to ensure the proper function and
of the MDP and the parallel preparation of the maintenance of the building / structure and site
environmental impact assessment / statement after final inspection.
(EIA/S).
--------------The Architect in this area of practice
-------------land use and the changes which occur recommends the systematic process of ensuring
within the physical environment (within the that a building / structure’s array of systems is
space where such activities take place), planned, designed, installed and tested to
represented mainly by the MDP. perform according to the design intent and the
building’s operational needs. If the building
------------the nation’s assets and its materials, equipment and systems are not
management. installed properly or are not operating as
intended, the effectiveness, efficiency,
------------the people, their living conditions and productivity and other benefits of high
the seeking of ways to ameliorate it. performance plans/designs will not be achieved.

------------road and transit networks, land-sea-air ----------------A building environment rating


linkages, the movement of people and goods system is needed to evaluate the environmental
from one place to another. performance of a building and to encourage
market migration towards sustainable design.
-----------the relationship of adopted development
proposals and policies to existing laws. --------------credit-based, allowing projects to earn
points for environment-friendly use of the
-----------calls for the detailed study of physical, building / structure and actions taken during
social, economic and administrative components planning, design, construction and occupancy.
and as such requires the expertise and
knowledge of Specialist Consultants (SCs). ---------------flexible, such that projects need not
meet identical requirements to qualify.
-----------identifies existing land use, resources,
social behavior and interaction ---------------consensus-based and market-driven
-----------undertakes environmental analysis, in order to accelerate the development and
demographic analysis and feasibility studies implementation of green building practices.
-----------examines existing laws, ordinances,
political/ social constraints ---------------The Consulting Architect in this area
-----------prepares the conceptual development of practice must have much more than the basic
plans, policies, implementing strategies to arrive knowledge of Green Architecture and
at the desired comprehensive and/or master Environmental and/or Sustainable Design and
planning solution/s sufficient knowledge of the governing
environmental laws and environmental
------------The Consulting Architect in this area of investigation processes and procedures under
practice arranges and formulates methods of international protocols such as the Philippine
rating and Solid Waste, Clean Air and
Clean Water Acts, DENR administrative ---------------The Consulting Architect in this area
issuances and the like. of practice must have much more than the basic
knowledge of Pre-Construction, Construction,
---------------The Architect in this area of practice Post-Construction and the other services under
undertakes a scientific study on the built SPP Documents 204, 206 and 207.
environment’s well-being, which allows the
Architect to focus on the ways in which the -------------Included under this specialized
building/structure can best maintain itself and practice is the preparation of the Fire Safety and
prolong its life in a cost-efficient manner, and Life Assessment Report (FALAR) required by
finally provide recommendations to the Owner/ R.A. No. 9514, the 2008 Fire Code of the
Client. Philippines and its 2009 IRR.

-------------determination as to the causes of --------------The Architect in this area of practice


building, building component and/or building must have much more than the basic knowledge
material deterioration of the various modes of Alternative Dispute
Resolution (ADR) prescribed under R.A. No.
--------------the causes of observed building 9285, the ADR Act of 2004 and its IRR i.e.
deficiencies e.g., non-compliance with planning Construction Arbitration, Mediation and
and building laws, deviations from original use or Conciliation, Negotiation and of Contract
function of spaces Administration, Quality Surveys, Appraisals and
Adjustments and Expert Testimony. An Architect
-------------research on possible faulty activities specializing in ADR must preferably be State-
and operations during the project accredited.
implementation phase, determination of faulty
plan/ design and/or construction methodology. --------------The Consulting Architect in this area
of practice must have much more than the basic
-------------is defined as an act or process of knowledge of Research Methods, Philippine
estimating value Architecture and its History, Architectural
Materials and Finishes, Building Types and
-----------The Consulting Architect in this Standards, Architectural Design Trends,
area of practice places value on the building / Architectural Writing and Architectural
structure condition and defects, and on its repair Photography.
and maintenance, including the required
improvements. --------------The Architect in this area of practice
must have much more than the basic knowledge
---------------The Architect in this area of practice of the Planning and Design Processes required
conceives, chooses and develops the type, for Housing Developments, Recreational and
disposition, arrangement and proportioning of Tourism Estates, Health Care and Hospitality
the structural elements of an architectural work, Facilities, Transportation and
giving due considerations to safety, cost- Telecommunications Facilities, Production and
effectiveness, functionality and aesthetics. Extractive Facilities, Utility-related
Developments, Secure Facilities, Business and
---------------The Consulting Architect in this area Industrial Parks, Economic Zones and
of practice must have much more than the basic Community Architecture and the like.
knowledge of Site Analysis, Space Planning and
Management, Architectural Programming, and ----------------The Consulting Architect in this area
the other services under SPP Document 201. of practice must have much more than the basic
knowledge of Building Materials and Finishes,
---------------The Architect in this area of practice Construction Methodologies, Building Envelopes
must have much more than the basic knowledge including cladding and roofing systems,
of Specification Writing, Estimation and Quantity Architectural Fenestrations and Architectural
Survey, Architectural Production, Architectural Hardware, Fixtures and Fittings.
Software, Architectural Support Services and
Contract Document Review. ----------The Architect in this area of practice
must have much more than the basic knowledge
of the Types of Architectural Office Operations,
Architectural Office Management, Accounting /
Finance / Taxation / Audit, Labor Code,
Architectural Marketing and Project
Development, Proposals / Negotiations /
Contracts, Contract Administration, File
Management and Limitations of Business
Process Outsourcing (BPO) and Knowledge
Process Outsourcing (KPO) Operations.

---------------Compensation for the foregoing


specialized architectural services, all of which
may be classified as additional or extra services,
shall be through man-months i.e. 22 man-days
multiplied by 8 man-hours, and multiplied by a
factor to cover other direct and indirect costs
e.g. overhead, etc. or any other applicable mode
of determination of the Architect’s fee as stated
in Doc. 201, Doc. 202 and the Architect’s
Guidelines.

SPP 204A

Four principal members were involved in the


design and building construction process:

1-4

SCOPE OF SERVICES

1-4

-------------The Construction Supervision Group


(CSG), which may be a qualified architectural
firm, or which the Architect is only part of, shall
not assume the responsibility of the Contractor’s
project superintendent.

--------------The CSG shall not make decisions on


matters that are the sole responsibility of the
Architect-of record (Aor).