Road Asphalt Works-Epc10-Ra-74-R0
Road Asphalt Works-Epc10-Ra-74-R0
Risk Rating
Risk Rating
Probability
Probability
Categories
Categories
Severity
Severity
No
Vehicles PTW work system shall be effectively implemented as per EPC-10 and
movement/ company requirement Constructio
hit by Use Approved and identified tracks (Not short cuts) all operators to hold valid
Mobilization 4 D P High n manager,
vehicles/ driving licenses.
and site Lo site
crushed by All equipments and operator shall have valid third party certificate. 1 A A engineer,
preparation vehicles w
Equipment shall be check after mobilization operator
/Vehicle Reverse alarm, seatbelt, all safety features shall be functional at all time.
overturn
Operator cabin shall be free of any visual obstruction
All operators shall wear mandatory PPE at site.
2 High Traffic management shall be in accordance with project requirement through 1 A A Lo Constructio
Eequipmen w n manager,
interface
Improper traffic t Hit to site
existing 4 C P Trained flagman shall be provided at both ends to guide the traffic movement engineer
management,
structure/ when construction works in progress near to perimeter road.
Uncontrolled moving Road works area shall be demarcated, barricaded /cordon off, and
vehicles.
workers appropriate signage posted to warn / communicate road users.
movement. Appropriate road signage shall be posted to communicate / warn drivers of
Physical construction activity as per road safety standard requirement.
injury.
Property Plastic barriers and sand bag shall be provided to segregate workers and
damage. traffic movements
Access to be controlled by soft as well as hard abreaction.
The swing area of the equipment shall be cordon off and stand by person
shall monitor worker movement around the equipment.
Operatives shall maintain safe distance from the operating construction
equipment and moving traffic.
Reflective road signage to be provided where required.
ABU DHABI GAS DEVELOPMENT COMPANY LIMITED
SHAH GAS DEVELOPMENT (SGD) PROGRAM
RISK ASSESSMENT and WORK INSTRUCTIONS
Task/Activity Description: ASPHALT PAVING WORKS Reference Number: EPC10-RA-74-R0
Note : Risk Assessment Matrix adopted from ADNOC-CoPV5-06 Date of Issue: 06/10/2015
Page 2 of 5
Ri Hazard Risk/Impact Risk Assessment Control Measures Risk Assessment Responsible
sk (Pre Controls) (Post Controls) Personal
No
Risk Rating
Risk Rating
Probability
Probability
Categories
Categories
Severity
Severity
Close supervision of the activity.
Ensure the even ground.
Vehicle Ensure vehicle is in good condition.
/Equipment Daily checklist of equipment shall be maintained.
overturn, Dedicated Banks man shall be provided & ensure reverse alarm for trucks. Constructio
Loading/Unload Physical Ensure preventive maintenance schedule shall be implemented & Lo n manager,
3 ing Aggregate injury 4 C P High 1 A P
maintained. w site
Base Course; Property engineer
Ensure authorised operators shall operate the moving plant and equipment.
damage All vehicles movement shall be controlled by dedicated Banks man & ensure
the working of reverse alarm for trucks, beacon light and other safety devices
Close supervision shall be provided
Equipment Hit Provide adequate sloping, shoring or benching to prevent collapse of
by /hit to Physical Lo
4 C P High excavation due to impact of traffic movement 2 A P Constructi
existing INJURY. W on
structure/ Lateral movement due to traffic movement shall be considered when sloping manager,
4 moving site
vehicles during Property and benching excavation. Lo
4 4 A High 2 A A engineer
construction damage w
Provide goal post to prevent equipment hitting overhead structure
Vehicle
/Equipment Follow site speed limit and road signs. Constructi
Transportation overturn, on
Follow Safe Defensive Driving techniques. Lo
of aggregate & Physical 4 C P High 1 A P manager,
5 Provide speed humps to control the speed of vehicles. w
Base course INJURY site
material; Ensure Traffic Marshall available and monitored the road condition.
Property engineer
While transporting material shall be covered with net to prevent fall.
damage
Clean the Housekeeping of the area will be done prior to the activity, and on daily Supervisor
Lo /
6. paved area Physical 4 C P High basis. 1 A P
w
prior to Injury, Ensure all equipments are inspected by competent person prior to start work. operator
ABU DHABI GAS DEVELOPMENT COMPANY LIMITED
SHAH GAS DEVELOPMENT (SGD) PROGRAM
RISK ASSESSMENT and WORK INSTRUCTIONS
Task/Activity Description: ASPHALT PAVING WORKS Reference Number: EPC10-RA-74-R0
Note : Risk Assessment Matrix adopted from ADNOC-CoPV5-06 Date of Issue: 06/10/2015
Page 3 of 5
Ri Hazard Risk/Impact Risk Assessment Control Measures Risk Assessment Responsible
sk (Pre Controls) (Post Controls) Personal
No
Risk Rating
Risk Rating
Probability
Probability
Categories
Categories
Severity
Severity
Adequate Job specified Personal Protective Equipments .i.e. Face shield.
Long leather hand gloves, Gauntlets, Suitable Safety boots.
Dust, slips Identified (orange colour jacket) Banks man at safe position.
asphalting; trips and Ensure reverse beepers are functioning always. And maintain safe distance
falls may between man & machine.
occur.
Highly reflective jacket shall be provided to operatives working in poor
visibility and road side.
Provide work equipment which is ergonomically design to prevent frequent
stooping, bending.
Deployed sufficient banks man to controlled the traffic and Equipment
Man and movement
machine / Constructi
Work area shall be kept cleared of unwanted material, debris shall not be
vehicle on
Physical Medi allowed to filth the adjacent road. Lo
7. interface 3 C p 1 A P manager,
injury um Slip, trip risks to be minimised by proper housekeeping w
site
Dedicated worker boarding and drop off point to be provided. engineer
Land safety procedure to be implemented.
Risk Rating
Risk Rating
Probability
Probability
Categories
Categories
Severity
Severity
Suitable and inspected Fire Extinguisher should be in place.
burn &
Regular TBT by foreman Constructi
Physical Availability of first aid kit along with first aider at site. on
Hot bitumen Medi Lo
9 injury 3 C P 1 A P manager,
(75 degree C) um Adequate hand protection to be provided to prevent burn injury. w
site
Property Appropriate respiratory protection to be provided to operatives exposed to engineer
damage contaminated air.
Work Instructions:
1. All hazard control measures prescribed in this Risk Assessment is issued as a work instruction to be implemented by site supervisors.
2. All persons and vehicles must comply with Site HSE Rules and PPE Requirements.
3. Under no circumstance shall any person will work under suspended load / bucket while manually handling/ loading / offloading from equipment.
ABU DHABI GAS DEVELOPMENT COMPANY LIMITED
SHAH GAS DEVELOPMENT (SGD) PROGRAM
RISK ASSESSMENT and WORK INSTRUCTIONS
Task/Activity Description: ASPHALT PAVING WORKS Reference Number: EPC10-RA-74-R0
Note : Risk Assessment Matrix adopted from ADNOC-CoPV5-06 Date of Issue: 06/10/2015
Page 5 of 5
Ri Hazard Risk/Impact Risk Assessment Control Measures Risk Assessment Responsible
sk (Pre Controls) (Post Controls) Personal
No
Risk Rating
Risk Rating
Probability
Probability
Categories
Categories
Severity
Severity
4. Hand brake to be applied when workers are working near equipment for lifting/ transferring load to and from the equipment
5. Do a tool box talk with all site supervisors, operators and operatives. Explain these control measures to all relevant operatives.
6. Housekeeping to be done and workplace to be made safe prior to leaving the workplace.
7. All persons shall sign their understanding and confirmation in the Tool Box Talk attendance sheet.
8. All construction waste will be removed daily from the work area.
9. All Near Misses and Accidents will be reported immediately to the on-duty Medic and site safety officers
10. Copy of this RA will be discussed in pre- start TBT. Copy will be available on site.
Prepared by Name Date and Signature Approved by Name Date and Signature
Construction HSE Manager Izhar Baig
Manager
Project Engineer Issued by Name Date and Signature
Sr. HSE Officer Dieudonne Chrameh Project manager Joseph. P