Excavation
5 60cm*60cm*90 cm pit
Locating, clearing and preparing the site = 1 day * 2 labor * 400 birr/day each = 800
2 labor for two days = 2 days * 2 labor * 400 birr/day each = 1600
Concrete work
Transporting cement, sand, and aggregate = 2 days * 2 labor * 400 birr/day each = 1600
Installation/erection
Carpenter= 1500 birr/day * 2 days = 3000 birr
Labors for mixing concrete and helping carpenter during erection = 2 day * 3 labor * 400
birr/day each = 2400
Curing the concrete after finished for 15 days = 2000
My expense = 5000birr
My profit = 30,000 birr
Water
Meter
Jerry can
Level
Plumb bob
How long should concrete cure for a flagpole?
Allow at least 24 hours for the cement to harden before you can raise the flagpole at its
highest position.
A school flag pole ranges in height from 20 feet to 45 feet. Most flag poles intended for
public or institutional display generally fall within this range. The most common flagpole
heights are 25-35 feet.
a) Flagpoles must not exceed a height of 8 meters above natural ground level.
b) Distance between flagpoles placed close to each other should be a minimum of 1.8
meters.
c) The location of flagpoles shall be appropriate within the context of the surrounding
area and shall not interfere with trees, vegetation, overhead lines or cables,
maneuvering of vehicles, pedestrian access areas, easements or public thoroughfares.
d) Ropes, pulleys and stays must be secured so as not to cause noise nuisance.
Make sure the hole is at least 2 feet deep and four to six times the diameter of the pole to
accommodate the ground sleeve.
The dimensions of a flagpole foundation are directly related to the height of the pole. For
every 10' in pole height you must dig 1' in depth, width, and length, i.e. 1 cubic foot. For
example, the foundation for a 30' pole must be 3' deep, by 3' wide, and 3' long
Construction procedure
Dig a wide hole.
Add about 10-15 cm of gravel to the base of the hole to allow for better drainage.
Position the post in the hole.
Mix and pour concrete
Allow at least 24 hours for the cement to harden before you can raise the flagpole at its
highest position.
Option 1
Telescoping flag pole with stage
Telescoping flag pole without stage
Option 2
Concrete work
Transporting cement, sand, and aggregate = 2 days * 2 labor * 400 birr/day each = 1600
Installation/erection
Welder = 15000 birr
Carpenter = 1500 birr/day * 2 days = 3000 birr
Labors for mixing concrete and helping carpenter during erection = 2 day * 3 labor * 400
birr/day each = 2400
Curing the concrete after finished for 15 days = 2000
My expense = 5000birr
My profit = 30,000 birr
800
1600
1600
3000
2400
2000
5000
30000
15000
60 cm * 60 cm * 1 meter foundation
0.6*0.6*1 = 0.36 m3
0.36 * 1.55 = 0.558 m3
1:2:3 cement: sand: aggregate 1/6, 2/6, 3/6
Cement = 0.093 m3
50 kg = 0.035 m3
x = 0.093 m3
x = 50 *0.093/0.035
x = 133 Kg
x = 665 Kg