Professional Documents
Culture Documents
Quantitative Techniques - Theories Part 2
Quantitative Techniques - Theories Part 2
4. A company is controlling a complex project by determining the activities that must take place and the relationship
among these activities. Attention then is focused on those activities that have the greatest influence on the project’s
estimated completion date. The quantitative technique most relevant to this is
a. Cost-volume-profit analysis c. Program evaluation review technique
b. Parametric programming d. Queuing analysis
6. PERT and the critical path method (CPM) are used for
a. Determining the optimal product mix c. Determining product costs
b. Project scheduling and control d. Determining the number of servers needed in a fast-food restaurant
7. A project is defined as a
a. Temporary endeavor c. Expensive endeavor
b. Continuous endeavor d. Endless endeavor
8. When using PERT, the expected time for an activity when given an optimistic time (A), a pessimistic time (B), and
most likely time (m) is calculated by which one of the following formulas?
a. (b – a) ÷ 2 c. (a + 4m + b) ÷ 6
b. (a + b) ÷ 2 d. (4abm) ÷ 6
9. Critical Path Method (CPM) is a technique for analyzing, planning, and scheduling large, complex projects by
determining the critical path from a single time estimated for each event in a project. The critical path
a. Is the maximum amount of time an activity may be delayed without delaying the total project beyond its target time
b. Is the earliest starting time that an activity for a project can begin
c. Is the pessimistic time estimate for an activity of a project
d. Is the longest time path form the first event to the last event for a project
11. When doing a cost-time trade-off in PERT analysis, the first activity that should be crashed is the activity
a. With the largest amount of slack
b. With lowest unit crash cost
c. On the critical path with the maximum possible time reduction
d. On the critical path with the lowest unit crash cost
12. A decision maker is operating in an environment wherein all the facts surrounding a decision are known exactly, &
each alternative is associated only with one possible outcome. The environment is known as
a. Certainty c. Uncertainty
b. Risk d. Conflict
16. The modeling technique used for situations involving a sequence of events with several possible outcomes associated
with each event is
a. Network analysis c. Queuing theory
b, Decision tree analysis d. Linear programming
17. Which of the following statements does not apply to decision tree analysis?
a. The sum of the probabilities of the events is less than one
b. All of the events are mutually exclusive
c. All of the events are included in the decision
d. The branches emanate from a node from left to right
19. If a cost function behaves that the average costs per unit of output decline systematically as cumulative production
doubles, the cost function is referred to as a:
a. Parabolic curve c. Linear cost curve
b. Learning curve d. Growth curve
20. The cost factor least likely to be affected by the learning curve is
a. Materials c. Indirect labor
b. Direct labor d. Variable overhead
22. A technique used for selecting the combination of resources that maximizes profits or minimizes costs.
a. Curvilinear analysis c. Dynamic programming
b. Queuing theory d. Linear programming
24. One limitation of the linear programming technique is that it is effective only for
a. Two-product situations c. Straight-line relationship situations
b. Manufacturing resource constraint situations d. Income maximization situations
26. The graphic method as a means for solving linear programming problems
a. Can be used when there are more than two restrictions (constraints)
b. Is limited to situations in which there are two restrictions (constraints)
c. Is limited to situations in which there is one restriction (constraint) only
d. Cannot be used if there are any restrictions (constraints)