Professional Documents
Culture Documents
Energy Audit For The Electrical System I
Energy Audit For The Electrical System I
ABSTRACT
ENERGY AUDIT FOR THE ELECTRICAL SYSTEM IN THE COMMERCIAL BUOLDING . This
papers presents some results of the energy audit that was conducted in the commercial building i.e
a hotel to recommended measures to decrease energy costs every month by identifying of energy
loss. This audit focused on the electrical system. The performance of this system was examined to
identify opportunities for improving energy efficiency. It is concluded that approximately 65 % of
electricity use in the object study is for its central air conditioning system. Therefore, automatic
energy saving adjustments towards the air conditioning system will provide a significant amount of
savings.
Keywords: Energy audit, electrical system
ABSTRAK
AUDIT ENERGI UNTUK SISTEM ELEKTRIKAL PADA GEDUNG KOMERSIAL. Tulisan ini
menampilkan beberapa hasil dari audit energi yang telah dilakukan untuk gedung komersial dalam
hal ini hotel untuk menurunkan biaya energi setiap bulan dengan cara mengidentifikasi kehilangan
energi. Audit ini difokuskan pada system elektrikal. Kinerja system ini telah dievaluasi untuk
mengidentifikasi oportunitas memperbaiki efisiensi energy. Disimpulkan bahwa sekitar 65 % dari
penggunaan energi pada objek studi adalah untuk system pengkondisian udara sentral. Oleh
karena itu, pengaturan penghematan energi otomatis pada system pengkondisian udara akan
memberikan jumlah yang cukup siknifikan.
Kata Kunci : Audit energi, sistem elektrikal
219
Urania Vol. 14 No. 4, Oktober 2008 : 161 - 233 ISSN 0852-4777
mass flow and energy content of these flow West Jakarta. There are two sources of
streams directly benefit unit performance. electrical power for the hotel and the
Other losses occur from surface heat transfer apartment buildings. The first source is from
to the atmosphere and incomplete PLN (the State Electric Company) with the
combustion of the fuel. The number of pieces voltage of 20 kV, 3 (three) phases, frequency
of equipment that required to be run during of 50 Hz, and a total power capacity of 1800
shutdown is optimized to reduce station kVA. The second source is from two
energy consumption. Continuous trend generator units each with a capacity of 1500
monitoring of heavy water and light water kVA with parallel connections to the PLN line.
collection during reactor operation will help The two electrical generators function as
stations in taking appropriate remedial backup power supply and are only operated
measures. when power supply from PLN fails.
A hotel is a typical commercial building The electrical energy from PLN travels
that behaves quite differently in comparison to through the middle voltage main panel (Panel
other commercial buildings. The energy Utama Tegangan Menengah, PUTM) and is
consumption of a hotel depends on the rate of then distributed through the low voltage main
occupancy and the hotel type. Due to the distribution panel (LVMDP) through 2 units of
economic crisis which directly affected the voltage reducing transformers to the capacity
tourism sector in Indonesia, the hotel of 2000 KVA, then the electrical energy goes
business experienced significant deflation. to the loads through bus bars.
The number of hotels decreased to 20% from
To compensate the excess kVARh (Kilo
the year 1997 to the year 2000. To sustain
Volt Ampere Reactive hours), two sets of
the hotel business from falling into economic
capacitor banks have been installed and are
crisis, due to rapidly increasing energy prices,
arranged in parallel connections with the
it is highly recommended that the hotels
transformers. The banks capacity for the
participate in energy saving projects and
apartment is 10 x 2 x 50 KVAR, and for
energy efficiency campaigns including energy
utilities is 6 x 50 KVAR.
audits as well. The energy saving project
requires an energy audit to be conducted on The electrical energy load distribution is
all systems within the hotel building. It is divided into three loads, i.e.: the load for
hoped that the energy audit activity will utilities and supporting facilities of the hotel
improve the awareness of energy saving and apartment; the total load for the hotel;
activities especially for star and non-star and the total load for the apartment. The
hotels in Jakarta. energy audit activity was focused only on the
total load of the hotel.
The objective of the energy audit is to
find ways to decrease energy costs (electrical
and thermal) per month by identifying sources METHODOLOGY
of energy loss within the hotel. It is important
to boost the efficiency of every utility ● Study approach
component to optimize electric usage.
An energy audit is one of the first steps
in any comprehensive energy management
THEORY program. Without conducting an energy audit
it would be difficult to quantify the energy
● Electrical system description consumption, energy distribution, perfor-
Figure 1 shows the electric supply of the mance levels and energy saving potential for
object study of Twin Hotel that located in all energy intensive systems within a hotel. By
220
ISSN 0852-4777 Energy Audit For The Electrical System
in The Commercial Building
(Amiral Aziz dan Rizka Elyza Sari)
[2]
Figure 1. Electrical Power Supply for the object study
221
Urania Vol. 14 No. 4, Oktober 2008 : 161 - 233 ISSN 0852-4777
222
ISSN 0852-4777 Energy Audit For The Electrical System
in The Commercial Building
(Amiral Aziz dan Rizka Elyza Sari)
Appartement 68,400
15%
Hotel 389,600
85%
0.23%
18.18%
lift
AC(AHU& FCU)
11.92% Boiler
exhause fan
Lighting
etc
0.73%
3.50% 65.44%
[2]
Figure 3. Electrical load balance in the hotel
223
Urania Vol. 14 No. 4, Oktober 2008 : 161 - 233 ISSN 0852-4777
power factor of the hotel’s electricity system Due to the high power factor in the hotel, it is
varies slightly from 0.965 to 0.995, as provided free from the penalty charged by PLN to
in Figure 5 The power factor reading implies customers with a power factor value below
that the hotel has applied a good practice for 0.85. A penalty from PLN is also usually
load distribution. This is a result of installing charged to customers with ratio of kVARh to
capacitor banks to increase the existing kWh below 0.62.
capacity, to reduce cable and distribution
losses and to improve the total system voltage.
35
Un balance Power (ph R, Ph S, Ph T) max = 1.46 %
it is < 3 %, good
34.5
Prosentase difference Power (%)
34
33.5
33
32.5
32
31.5
31
11:55
14:00
16:05
18:10
20:15
22:20
0:25
2:30
6:35
8:40
10:45
12:50
14:55
17:00
19:05
21:10
23:15
1:20
5:25
7:30
9:35
11:40
13:45
15:50
17:55
20:00
22:05
10:55
13:00
15:05
17:10
19:15
14:50
Fr St Su Mn Tu We
Time
Phase R Phase S Phase T
Figure 4. Power balance between the phases in the input panel of hotel loads
0.99
0.98
Power Factor
0.97
0.96
0.95
0.94
16:55
19:10
12:20
14:35
16:50
19:05
21:20
23:35
1:50
6:05
8:20
10:35
12:50
15:05
17:20
19:35
21:50
0:05
2:20
6:35
8:50
11:05
13:20
15:35
17:50
20:05
22:20
11:20
13:35
15:50
18:05
20:20
16:05
Fr St Su Mn Tu We
Time
Power Factor phase R Power Factor phase S Power Factor phase T
224
ISSN 0852-4777 Energy Audit For The Electrical System
in The Commercial Building
(Amiral Aziz dan Rizka Elyza Sari)
225
Urania Vol. 14 No. 4, Oktober 2008 : 161 - 233 ISSN 0852-4777
14
THD Current < 15 %, Good quality of electric current
12
10
THD Current (%)
0
1
29
237
265
293
321
349
377
405
433
461
489
517
545
573
601
629
657
685
713
741
769
797
825
853
881
909
937
1096
1124
1152
1180
1415
time
226
ISSN 0852-4777 Energy Audit For The Electrical System
in The Commercial Building
(Amiral Aziz dan Rizka Elyza Sari)
1.6
1.4
1.2
THD Voltage (%)
0.8
0.6
0.4
0.2
0
1
25
231
255
279
303
327
351
375
399
423
447
471
495
519
543
567
591
615
639
663
687
711
735
759
783
807
831
855
879
903
927
1083
1107
1131
1155
1179
1203
TIME
From the histogram above it can be Usually in addition to the electrical energy
observed that the average energy costs (kWh) and contract capacity costs that
consumption in the hotel tends to be constant are paid monthly, an electrical consumer in a
at 333 MWH per month. The tariff for electricity commercial building must also pay penalty
per kWh from the PLN electricity bill was costs. The penalty cost is an expense that is
constant. This was approximately 0.0502, - paid due to inactive electrical energy produced
US$/kWh/month (at off peak hour time). by electrical appliances.
600 Rp 300
Billing of PLN electric at power contract = 1800 KVA,
Transformator 2 X 2000 kVA
Average PLN energy per month = 333 kWh/mh
WBP/LWBP average = 20.98 %
500 Rp 250
Electricity cost (million Rp)
PLN Electric cost (million Rp/ mh)
400 Rp 200
ENERGY (kWh)
300 Rp 150
200 Rp 100
100 Rp 50
- Rp -
JANUARY
FEBRUARY
MARCH
APRIL
MAY
JUNE
JULY
AUGUST
SEPTEMBER
OCTOBER
NOVEMBER
DECEMBER
month( at 2003)
227
Urania Vol. 14 No. 4, Oktober 2008 : 161 - 233 ISSN 0852-4777
The penalty cost should be paid if the Main Distribution Panel -- LVMDP) and in the
comparison of kVARh to kWh is not more than sub-distribution panels (Low Voltage Sub-
0.62. However, the hotel is not required to pay distribution Panel).
this additional cost, as it has installed capacitor
The electrical power balance can be
banks to compensate for excessive KVARh
presented in types of grouped load distribution,
use. The hotel should pay special attention to
which can reveal the power that is not utilized
the quality of its Total Harmonics Distortion
or not clearly utilized within the system.
(THD) based on the current load to ensure
peak performance from its capacitor banks. Figure 9 depicts the average monthly
electrical energy balance in the hotel. The
electricity supply from PLN (1821 MWh/month)
● Electrical power balance is utilized mainly by the central air condition
system (approximately 1191.7 MWh/ month or
Electrical power balance is studied to
65.44% of the total consumption). The hotel
observe the hotel’s energy consumption and
utilizes 217 MWh/month for lighting purpose
distribution data for a specific period of time.
(11.92% of the total consumption) and 412.3
This can be obtained by measuring the
MWh/month (22.64%) for other purposes.
electrical load in the center panel (Low Voltage
[2]
Figure 9. Electrical power balance based on the electrical load type
The electrical load consumption for the kW, and the average is approximately 355.5
hotel is depicted in figure 10. From the curve it kW. From the figures above, it is clear that the
can be observed that the maximum load hotel consumes more electrical power than the
appears during the evening. The maximum apartment. The total maximum power
load actually depends on the occupancy rate consumption for both the hotel and apartment
of the hotel at that point in time. The is 570.2 kW. With the installed contract
magnitude of the maximum load differs from capacity from PLN of 1800 kVA and the power
day to day. The maximum electrical power factor of 0.97, the total maximum active power
consumption in the hotel could reach 441.9 is 1746 kW. Thus, the percentage of maximum
228
ISSN 0852-4777 Energy Audit For The Electrical System
in The Commercial Building
(Amiral Aziz dan Rizka Elyza Sari)
From the audit process, it was - Reducing chiller operation time from
recommended that the following actions to be 22 hours per day to 18 hours per day
implemented to improve efficiency in electricity - Cleaning of the AHU’s and FCU’s heat
usage : exchanger, and the chillers evapora-
■ Optimization of chiller operation tors and condensers. This needs to be
followed with a regular preventive
Based on the electrical power maintenance program, to avoid a
consumption curve, the energy saving oppor- return to the system’s previous ineffi-
tunities within the Central Air Conditioning cient condition.
(AC). System can be realized through the - Adding automatic control system
optimization of chiller operation. The electrical equipment in the chiller system inclu-
energy consumption of the central AC system ding regulating valves, motorized
can be reduced by decreasing the chiller valves, and variable speed drives,
operation time without lowering the thermal among others will increase the overall
229
Urania Vol. 14 No. 4, Oktober 2008 : 161 - 233 ISSN 0852-4777
performance of the chiller system by consumption for both the hotel and apartment
1.5%. is only 570.2 kW, equivalent to 600 kVA. If it is
- At the moment the level of hotel room assumed that given the safety factor for
thermal comfort is lower than the contracted power that is 2.5 times the maxi-
standard thermal comfort. The level of mum load consumption which is 600 kVA, then
hotel room thermal comfort can be there’ is a possibility to decrease 300 kVa of
increased by adjusting the air volume contracted power from PLN. This implies
rate and air change rate in every room. reducing the capacity to 1,500 kVA. By doing
This can be done by conducting air so, there will be a reduction in electrical energy
balancing within the central air condi- payments by approximately 945 US$/month (1
tioning system. It is recommend-ded to kVA/month= Rp. 28,500 = $ 3.15). Reducing
conduct the air balancing process after the contracted power only requires Rp.
chiller maintenance. 150,000 (equivalent to $ 16.67) as
administration fee.
■ Housekeeping Management
■ Maintain capacitor bank performance
By maximizing the utility of electrical
■ Proper maintenance of electrical
appliances, the kW factor value will reach
the maximum level ( 1 ). This means that equipment
power consumed by the appliances to do
Proper maintenance and operation of
the work will be the same as its design.
electrical equipment can help energy saving
efforts in addition to lengthening electrical
■ Modifying the key tag system equipment lifetimes.
Currently the key tag system is widely
used in star hotels. The use of the key tag REFFERENCE
system in the hotel increases the efficiency 1. ANONIMUS, “ Guidelines on Energy
of electricity use. However, there is an Audit, Electrical & Mechanical Services
opportunity of improved energy savings if Department, The Government of the
the system is modified. For example, Hongkong Special Administration Region,
usually when guests use a key card upon April 2004.
entry, it will automatically activate the 2. RIZKA ELYZA SARI,” Energy Mana-
room’s main lamps, bathroom lamp and the gement Assignment”, Magister of Energy
A/C system. This setting can be modified to Conversion, Mechanical Engineering
ensure that when they use the key card the Department , The Trisakti University,
bathroom lamp does not turn on instantly. Jakarta, 2006.
Instead, guests can turn the bathroom lamp 3. SMITH, “ Energy Management Principle –
on when required. Applications – Benefits - Savings “
■ Reducing the contracted power from PLN Pengamon Prwess.
4. WAYNE, C, Turner “ Energy Manage-
from 1800 kVA to 1500 kVa
ment Handbook ”, The Fairmont Press,
From the load consumption curve, it 2 nd edition.
can be observed that the maximum
230