Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 12

1.

________are entities whose value is determined from the solution of LPP


A. objective function
B. decision variable
C. constraints
D. opportunity cost
A.objective function

2. The region of feasible solution in LPP graphical method is called ____


A. infeasible region
B. unbounded region
C. infinite region
D. feasible region
D.feasible region

3. The outgoing variable row in the simplex table is called ____


A. outgoing row
B. key row
C. basic row
D. interchanging row
C.basic row

4. When the solution is degenerate in transportation problem, we add a _


A. dummy
B. epsilon
C. penalty
D. regret
B.epsilon

5. ______method is used in Assignment Problem


A. ncwr
B. lcm
C. vam
D. hungarian
D.hungarian

6. The longest path in the network diagram is called ____


A. head path
B. sub path
C. critical path
D. sub critical path
C.critical path

7. IF the Minimax are ( 10,18,16) and Maximin are (8,10,7). The saddle point is ___
A. 7
B. 10
C. 18
D. 8
B.10

8. Pick the wrong relationship:


A. interfering float = total float – free float
B. total float =free float + independent float
C. total float ≥ free float ≥ independent float
D. free float = total float – head event slack
B.total float =free float + independent float

9. The shortest time in the PERT is called ______time


A. expected
B. pessimitic
C. optimistic
D. most likely
C.optimistic
10. The total time required to complete all the jobs in a job sequence problem is known as
______
A. processing order
B. idle time
C. processing time
D. elapsed time
D.elapsed time

11. Operations Research Models in which values of all variables and all possible outcomes
are known with certainty are called models.
A. physical
B. symbolic
C. deterministic
D. probabilistic
C.deterministic

12. Operations Research Models in which some or all variables are random in nature are
called models.
A. physical
B. symbolic
C. deterministic
D. probabilistic
D.probabilistic

13.                   and are techniques applied in project management.


A. cpm and pert
B. assignment & transportation
C. game theory
D. decision theory& inventory models
A.cpm and pert

14.                are the entities whose values are to be determined from the solution of the LPP.
A. objective function
B. decision variables
C. constraints
D. opportunity cost
B.decision variables
15.                specifies the objective or goal of solving the LPP.
A. objective function
B. decision variables
C. constraints
D. opportunity cost
A.objective function

16.                   _are the restrictions or limitations imposed on the LPP.


A. objective function
B. variables
C. constraints
D. profit
C.constraints

17. When it is not possible to find solution in LPP, it is called as                         solution
A. infeasible
B. unbounded
C. improper
D. unknown
A.infeasible

18. In case of a ‘ ’ constraint, the feasible region is a straight line.


A. less than or equal to
B. greater than or equal to
C. mixed
D. equal to
D.equal to

19. In linear programming, unbounded solution means solution.


A. infeasible
B. infinite
C. unique
D. degenerate
B.infinite

20. The incoming variable column in the simplex algorithm is called .


A. key column
B. incoming column
C. important column
D. variable column
A.key column
21. The intersection value of key column and key row is called                
A. vital element
B. important element
C. basic element
D. key element
D.key element

22. The variable added to the LHS of a less than or equal to constraint to convert it into
equality is called variable.
A. surplus
B. artificial
C. slack
D. additional
C.slack

23. A resource which is completely utilized is called in simplex


A. null resource
B. scarce resource
C. abundant resource
D. zero resource
B.scarce resource

24. In simplex, a minimization problem is optimal when all Delta J, i.e. Cj – Zj values are .
A. either zero or positive
B. either zero or negative
C. only positive
D. only negative
A.either zero or positive

25. To find initial feasible solution of a transportation problem the method which starts
allocation from the lowest cost is called method
A. vogel’s approximat ion method
B. nwcr
C. lcm
D. Modi
C.lcm

26. When the total of allocations of a transportation problem match with supply and demand
values, the solution is called solution.
A. infeasible solution
B. feasible solution
C. optimum solution
D. degenerate solution
B.feasible solution

27. When the allocations of a transportation problem satisfy the rim condition (m + n – 1) the
solution is called                  
A. infeasible solution
B. feasible solution
C. non degenerate solution
D. degenerate solution
C.non degenerate solution

28. Which of the following considers difference between two least costs for each row and
column while finding initial basic feasible solution in transportation?
A. vam
B. nwcr
C. modi
D. lcm
discuss
A.vam

29. If the number of rows and columns in an assignment problem are not equal than it is
called problem.
A. balanced
B. unbalanced
C. infeasible
D. unbounded
B.unbalanced

30. The method used for solving an assignment problem is called                 method.
A. vam
B. nwcr
C. modi
D. hungarian
D.hungarian

31. When a maximization assignment problem is converted in minimization problem, the


resulting matrix is called matrix.
A. cost
B. regret
C. profit
D. dummy
B.regret

32. The longest path in the network diagram is called path


A. critical
B. sub-critical
C. best
D. worst
A.critical

33. Backward pass calculations are done to find occurrence times of events.
A. tentative
B. definite
C. latest
D. earliest
C.latest

34. The order in which machines are required for completing the jobs is called
A. machines order
B. job order
C. processing order
D. working order
C.processing order

35. The time during which a machine remains waiting or vacant in sequencing problem is
called time.
A. processing
B. waiting
C. free
D. idle
D.idle

36. In linear programming represents mathematical equation of the limitations imposed by


the problem.
A. objective function
B. decision variables
C. constraints
D. opportunity cost
C.constraints

37. The type of constraint which specifies maximum capacity of a resource is                     
‘or equal to’ constraint.
A. less than
B. greater than
C. not greater than
D. not less than
A.less than

38. The region of feasible solution in LPP graphical method is called                    region


A. infeasible
B. infinite
C. unbounded
D. feasible
D.feasible

39. When the constraints are a mix of ‘less than’ and ‘greater than’ it is a problem having .
A. multiple constraints
B. infinite constraints
C. infeasible constraints
D. mixed constraints
D.mixed constraints

40. The outgoing variable row in the simplex algorithm is called.


A. outgoing row
B. key row
C. interchanging row
D. basic row
B.key row

41. A resource which is partially utilized is called in simplex.


A. null resource
B. scarce resource
C. abundant resource
D. zero resource
C.abundant resource
42. The value of one extra unit of resource is called in simplex.
A. unit price
B. extra price
C. retail price
D. shadow price
D.shadow price

43. In simplex, a maximization problem is optimal when all Delta J, i.e. Cj – Zj values are .
A. either zero or positive
B. either zero or negative
C. only positive
D. only negative
B.either zero or negative

44. In a transportation problem, the method of penalties is called                     method.


A. vogel’s approximat ion method
B. nwcr
C. lcm
D. modi
A.vogel’s approximat ion method

45. When there is a degeneracy in the transportation problem, we add an imaginary allocation
called in the solution.
A. dummy
B. penalty
C. regret
D. epsilon
D.epsilon

46. If M + N – 1 = Number of allocations in transportation, it means . (Where ‘M’ is number


of rows and ‘N’ is number of columns)
A. there is no degeneracy
B. degeneracy exists
C. solution is optimum
D. problem is balanced
A.there is no degeneracy

47. An activity whose start or end cannot be delayed without affecting total project
completion time is called activity.
A. dummy
B. non-critical
C. important
D. critical
D.critical

48. Floats for critical activities will be always be .


A. one
B. zero
C. highest
D. equal to duration
B.zero

49. The shortest possible completion time of an activity in PERT is called time.
A. optimistic
B. pessimistic
C. expected
D. most likely
A.optimistic

50. The total time required to complete all the jobs in a job sequencing problem is known as .
A. processing time
B. waiting time
C. elapsed time
D. idle time
C.elapsed time

51. The participants in a game are called .


A. invitees
B. players
C. contestants
D. clients
B.players

52. The outcome of the interaction of selected strategies of opponents in a game is called .
A. income
B. profit
C. payoff
D. gains
C.payoff

53. In a game, the alternatives or courses of action available to each player are called .
A. choices
B. strategies
C. options
D. actions
B.strategies

54. A situation in a game where, in the payoff matrix, maximin of row is equal to minimax of
column is called .
A. centre point
B. saddle point
C. main point
D. equal point
B.saddle point

55. If there are or more decision variables in a LPP, SIMPLEX method is used.
A. 2
B. 3
C. 1
D. 4
B.3

56. If 5y = 30, then the line is                    


A. parallel to x axis
B. parallel to y axis
C. passes through the origin
D. intersects both the axis
A.parallel to x axis

57. Operations Research techniques are in nature.


A. qualitative
B. quantitative
C. judgmental
D. subjective
B.quantitative

58. Forward pass calculations are done to find occurrence times of events.
A. exact
B. earliest
C. latest
D. approximate
B.earliest

59. The second longest path in the network diagram is called Path.
A. alternate
B. feasible solution
C. critical
D. sub-critical
D.sub-critical

60. When a particular assignment in the given problem is not possible or restricted as a
condition, it is called a problem.
A. degenerate
B. prohibited
C. infeasible
D. unbalanced
B.prohibited

61. Operations Research (OR) , which is a very powerful tool for ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
A. Research
B. Decision – Making
C. Operations
D. None of the above
B.Decision – Making

62. Who coined the term Operations Research?


A. J.F. McCloskey
B. F.N. Trefethen
C. P.F. Adams
D. Both A and B
D.Both A and B

63. The term Operations Research was coined in the year ‐‐‐‐‐‐‐‐‐‐‐‐‐‐
A. 1950
B. 1940
C. 1978
D. 1960
B.1940

64. This innovative science of Operations Research was discovered during ‐‐‐‐‐‐‐‐‐‐‐‐‐
A. Civil War
B. World War I
C. World War II
D. Industrial Revolution
C.World War II

65. Operations Research was known as an ability to win a war without really going in to a
‐‐‐‐‐‐‐‐‐‐‐‐‐
A. Battle field
B. Fighting
C. War
D. Both A and B
D.Both A and B

66. Who defined Operations Research as scientific method of providing executive


departments witha quantitative basis for decisions regarding the operations under their
control?
A. Morse and Kimball (1946)
B. P.M.S. Blackett (1948)
C. E.L. Arnoff and M.J. Netzorg
D. None of the above
A.Morse and Kimball (1946)

67. Who defined Operations Research as scientific approach to problem solving for
executivemanagement ?
A. E.L. Arnoff
B. P.M.S. Blackett
C. H.M. Wagner
D. None of the above
C.H.M. Wagner

68. Who defined Operations Research as an aid for the executive in marketing his decisions
byproviding him with the quantitative information based on the scientific method of
analysis ?
A. C. Kitte
B. H.M. Wagner
C. E.L. Arnoff
D. None of the above
A.C. Kitte
69. Operations Research has the characteristics the it is done by a team of ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
A. Scientists
B. Mathematicians
C. Academics
D. All of the above
A.Scientists

70. There is a great scope for ‐‐‐‐‐‐‐‐‐‐‐‐ working as a team to solve problems of defence by
using theOperations Research approach
A. Economists
B. Administrators
C. Statisticians and Technicians
D. All of the above
D.All of the above

71. Operations Research emphasizes on the overall approach to the system. This
charecteristics of Operations Research is often referred as
A. System Orientation
B. System Approach
C. Interdisciplinary Team Approach
D. none
D.none

72. Operations Research cannot give perfect ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ to problems


A. Answers
B. Solutions
C. Both A and B
D. Decisions
C.Both A and B

73. Operations Research simply helps in improving the ‐‐‐‐‐‐‐‐‐‐‐‐‐‐ of the solution but does
not resultin a perfect solution.
A. Quality
B. Clarity
C. Look
D. None of the above
A.Quality

74. Operations Research involves ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ attack of complex problems to arrive at


theoptimum solution
A. Scientific
B. Systematic
C. Both A and B
D. Statistical
C.Both A and B

75. Operations Research uses models built by quantitative measurement of the variables c a
given problem and also derives a solution from the model using ‐‐‐‐‐‐‐‐‐‐‐‐‐ of the diversified
solution techniques oncerning
A. Two or more
B. One or more
C. Three or more
D. Only One
B.One or more

You might also like