Exercise 1
Comparison of strengths and weaknesses of activity on node diagrams and activity on arrow diagrams.
If we use activity on arrow diagrams we can show only finish to start relationships. But when we use activity on nodes diagrams we can show more details on the activities Such as Earliest start date, Earliest finish date, Latest start date, Latest finish date, Activity span, Float.
And also when we use activity on arrow diagrams sometimes we will have to use dummy nodes to represent complex relationships and dependencies between activities. Activity on nodes diagrams show relationships by arrows. Because of that it doesn t require dummy nodes.
Activities on nodes diagrams are more flexible than activity on arrow diagrams and they can show all of major types of relationships.
In activity on nodes diagrams, since the activity is on the node more data can be placed on the activity. Activity on the arrow diagrams on the other hand presents only the most important elements and provides a summarized idea of the total picture in an easy to understand format.
2|P a ge
ICT2009 ITPM
Assignment 01
Exercise:2
A 2 11 B 3 E
C 4 F 6
D 5
Answer
A 2 11 B 3 E
C 4 F 6
G D 5
Add new activity G to make one ending Node.
3|P a ge
ICT2009 ITPM
Assignment 01
Exercise:3
ghg
C 4
B 3 D E 5
Answer
A 1
F 6
B 3 D 4.a E 5 G
To avoid logical error add dummy node 4.a and to make one ending node add new activity G.
4|P a ge
ICT2009 ITPM
Assignment 01
Exercise:4
C A 22 4
1 B 3 D 5
E 6 F
Answer
C A 1 B 3 D 5 F 2 4
G
E 6
ICT2009 ITPM
Assignment 01
Exercise:5
A 1 C B 3
2 G E 4 F 5
Answer
A 2 1 C B 3 D 4 F 5 E G
In this diagram there is no logical error in representation. But in activity of E s direction cannot be reversed. Because it represents the duration (time) of that activity.
6|P a ge
ICT2009 ITPM
Assignment 01
Exercise:6
A 1 C B 3
2 G E 5 F
Answer
A 1 C E B 3 D 4
2 G 5 F 6 H
There is a loop in this diagram (G, F, E ). Loops are cannot be there in activity on arrow diagrams. So we added node 6 and activity G to avoid that loop.
7|P a ge
ICT2009 ITPM
Assignment 01
8|Page
ICT2009 ITPM
Assignment 01
START
5 Days
4 Days
7 Days
2 Days
1 Day
0 0
Requirements Gathering
5 5
5 5 4
Hardware Specifications 0
9 9
9 9 7
Comparing information 0
16 16
16 18 4
18 20
20 20 1
Purchasing
21 21 0
4 Days
16 16 4
Preparing money 0
20 20
FINISH
9|Page
ICT2009 ITPM
Assignment 01
Exercise:8 Organizing and carrying out a survey of users opinions of an information system
Activity Description Duration (Days) 14 Precedents
A B C D E F G H I
Understanding about the current information system and it s procedure Decide the type of information collecting method Preparing the questioner for survey Selecting a target set of users of the Information System Fixing dates and select a crew to carry out the survey Distribute the survey materials among crew members Supervise to carryout and to collect survey materials Analyze the survey information Making decisions according to the survey information and present it to the relevant people
A B B B E,C F G H
3 3 1 1 5 2
10 | P a g e
ICT2009 ITPM
Assignment 01
D=3
11 | P a g e