SAUDI ARCHIRODON LTD.

Early and General Civil Works for Riyadh


Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 2 of 25

Table of Contents
1.0 Purpose and Scope .............................................................................................. 3
2.0 Document Control ............................................................................................... 3
3.0 Reference Documents ......................................................................................... 4
4.0 Definitions, Terms and Abbreviations .............................................................. 10
5.0 Responsibility ................................................................................................... 10
6.0 Materials and Equipment .................................................................................. 11
7.0 Resources .......................................................................................................... 12
8.0 Methodology / Procedure .................................................................................. 13
9.0 Quality Control ................................................................................................. 18
10.0 Health, Safety and Environment ....................................................................... 19

Appendices

Appendix A Inspection and Test Plan for Civil Works.


Appendix B Job Safety Analysis (JSA).

2
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 3 of 25

1.0 Purpose and Scope

1.1 This method statement describes the techniques and methods to be implemented and the
resources to be utilized for all the concrete operations required in the construction of the
‘‘Early and General Civil Works at Power Plant PP14 in Riyadh, Saudi Arabia’’.
1.2 The work covered includes the transportation and placement of concrete for typical concrete
structures in the works.
1.3 When required and particularly at the large pours (over 400m3) an amendment will be prepared
in which will be described in detail :
a) The pouring gangs and the sequence of pouring.
b) The vibration pattern.
c) No and position of concrete pumps.
d) Back up plant requirements
e) Pouring time schedule.
f) Location of thermocouples
g) Identification and fix number of proposals for corrosion items (anchor bolts,
cast-in plates, earth conduits, ducts and pipe works).

2.0 Document Control

2.1 This method statement is a controlled document as required by the system procedure Quality
Planning and it is issued in accordance to the system procedure Control of Documents and
Data. Furthermore, it will be distributed as such to those detailed on the Internal Distribution
of Documents Matrix maintained by the Document Controller.
2.2 Internal distribution of this document will be by the Document Controller, while external
distribution will be via the Secretary.
2.3 The documents govern the preparation, registration, approval, distribution and
amendment/revision of this method statement will be detailed in below paragraphs if necessary.
2.4 This method statement is subject to amendments during the execution of all operations
described above in Paragraph 1.2, as a result either of periodic reviews or whenever
circumstances demand such an action.
2.5 Revisions will be issued in accordance to the system procedure Control of Documents and Data
both whenever the body of the method statement changes and when an appendix is being added
or removed. Revised appendices for substitution will be issued separately and, where
appropriate, will include a separate schedule of contents. Revisions to the text of this document
will be indicated by a black line in the right hand side. Revisions to forms and the like will be
indicated by ‘’clouding’’ the changed information.
2.6 Details of previous revisions will be removed. This document’s revision and appendix issue
status is shown in the Project Register of Management System Documents, a copy of which
may be obtained from the Project Office upon request.

3
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 4 of 25

2.7 This document includes all revised versions, will be included in 11061-PMG-PSP-10-F01,
“Deliverables Plan” prepared by the Project Controls Manager and maintained by the
Document Controller.

3.0 Reference Documents

3.1 The following documents define the requirements to be employed to demonstrate compliance
of the works defined in this method Statement:
 Specifications / Codes / Standards
Ref. Title
GEMSS - C - 15 ,
Cast in Place concrete & Precast concrete Elements
Rev - 02
PP1314 - 00 - Y - CI
Concrete Technical Specification
- WP - 301 - Rev - 01
NOTE: The design, all materials, constructions and installations, tests and investigations
also on site, shall be as a minimum conform to the latest edition or replacement of the
Codes and Standards listed in alphabetical order in the project Tender Documents, as far
as these standards, codes and regulations are available in English language edition

 Drawings
Ref. Title
PP1314-00-Y-CD-WP-001 “STRUCTURAL GENERAL STEEL NOTES’’ – Rev.0
“STRUCTURAL GENERAL CONCRETE NOTES
PP1314-00-Y-CD-WP-002
SHEET 1’’ – Rev.0
“STRUCTURAL GENERAL CONCRETE NOTES
PP1314-00-Y-CD-WP-003
SHEET 2’’ – Rev.0
“GENERAL ABBREVATIONS,LEGENDS &
PP1314-00-Y-CD-WP-004
TERMINOLOGY LIST”– Rev.0
“STRUCTURAL GENERAL STEEL DETAILS
PP1314-00-Y-CD-WP-005
GUARDRAIL”– Rev.0
“ANCHOR BOLTS DETAILS & NOTES FOR STEEL
PP1314-00-Y-CD-WP-014
STRUCTURES”– Rev.0
“STRUCTURAL STANDARD CONCRETE DETAILS
PP1314-00-Y-CD-WP-015
SHEET 1”– Rev.0
“STRUCTURAL STANDARD CONCRETE DETAILS
PP1314-00-Y-CD-WP-016
SHEET 2”– Rev.0

4
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 5 of 25

“STRUCTURAL STANDARD REINFORCEMENT


PP1314-00-Y-CD-WP-017
DEVELOPMENT AND SPILCE TABLES”– Rev.0

“POWER GENERATION BUILDING


PP14-50-UMC-CDQ-WP-001 FOUNDATIONS OVERALL LAYOUT PLANS”–
Rev.0
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-002
FOUNDATIONS LAYOUT PLANS”– Rev.1
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-003
FOUNDATIONS SECTIONS”– Rev.1
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-004 FOUNDATIONS PLANS & DETAILS DETAIL
SHEET 1”– Rev.1
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-005 FOUNDATIONS PLANS & DETAILS DETAIL
SHEET 2”– Rev.1
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-006 FOUNDATIONS PLANS & DETAILS DETAIL
SHEET 3”– Rev.0
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-007 FOUNDATIONS PLANS & DETAILS DETAIL
SHEET 4”– Rev.0
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-008
FOUNDATIONS LAYOUT PLANS”– Rev.1
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-009
FOUNDATIONS SECTIONS”– Rev.1
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-010 FOUNDATIONS PLANS & DETAILS DETAIL
SHEET 1”– Rev.0
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-011 FOUNDATIONS PLANS & DETAILS DETAIL
SHEET 2”– Rev.0
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-012 FOUNDATIONS PLANS & DETAILS DETAIL
SHEET 3”– Rev.0
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-013
FOUNDATIONS LAYOUT PLANS”– Rev.1
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-014
FOUNDATIONS SECTIONS”– Rev.1

5
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 6 of 25

“POWER GENERATION BUILDING


PP14-50-UMC-CDQ-WP-015 FOUNDATIONS PLANS & DETAILS DETAIL
SHEET 1”– Rev.0
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-016 FOUNDATIONS PLANS & DETAILS DETAIL
SHEET 2”– Rev.0
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-017 FOUNDATIONS PLANS & DETAILS DETAIL
SHEET 3”– Rev.0
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-018
FOUNDATIONS LAYOUT PLANS”– Rev.1
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-019
FOUNDATIONS SECTIONS”– Rev.1
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-020 FOUNDATIONS PLANS & DETAILS DETAIL
SHEET 1”– Rev.0
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-021 FOUNDATIONS PLANS & DETAILS DETAIL
SHEET 2”– Rev.0
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-022 FOUNDATIONS PLANS & DETAILS DETAIL
SHEET 3”– Rev.0
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-023
FOUNDATIONS LAYOUT PLANS”– Rev.1
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-024
FOUNDATIONS SECTIONS”– Rev.1
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-025 FOUNDATIONS PLANS & DETAILS DETAIL
SHEET 1”– Rev.1
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-026 FOUNDATIONS PLANS & DETAILS DETAIL
SHEET 2”– Rev.1
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-027 FOUNDATIONS PLANS & DETAILS DETAIL
SHEET 3”– Rev.0
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-028 FOUNDATIONS PLANS & DETAILS DETAIL
SHEET 4”– Rev.0

6
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 7 of 25

“POWER GENERATION BUILDING


PP14-50-UMC-CDQ-WP-029
FOUNDATIONS – GRADE WALL DETAILS”– Rev.0
“POWER GENERATION BUILDING
PP14-50-UMC-CDQ-WP-035 FOUNDATIONS PLANS & DETAILS DETAIL
SHEET 4”– Rev.0
“GAS TURBINE GENERATOR FOUNDATION
PP14-11-UMB-CDQ-WP-001
PLANS”– Rev.0
“GAS TURBINE GENERATOR FOUNDATION
PP14-11-UMB-CDQ-WP-004
SECTIONS & DETAILS”– Rev.0
“ACCESSARY LF & AA MODULE FOUNDATION
PP14-11-UMB-CDQ-WP-001
PLAN, SECTIONS & DETAILS”– Rev.0
“GAS TURBINE GENERATOR FOUNDATION
PP14-12-UMB-CDQ-WP-001
PLANS”– Rev.0
“GAS TURBINE GENERATOR FOUNDATION
PP14-12-UMB-CDQ-WP-004
SECTIONS & DETAILS”– Rev.0
“ACCESSARY LF & AA MODULE FOUNDATION
PP14-12-UMB-CDQ-WP-001
PLAN, SECTIONS & DETAILS”– Rev.0
“GAS TURBINE GENERATOR FOUNDATION
PP14-13-UMB-CDQ-WP-001
PLANS”– Rev.0
“GAS TURBINE GENERATOR FOUNDATION
PP14-13-UMB-CDQ-WP-004
SECTIONS & DETAILS”– Rev.0
“ACCESSARY LF & AA MODULE FOUNDATION
PP14-13-UMB-CDQ-WP-001
PLAN, SECTIONS & DETAILS”– Rev.0
“GAS TURBINE GENERATOR FOUNDATION
PP14-21-UMB-CDQ-WP-001
PLANS”– Rev.0
“GAS TURBINE GENERATOR FOUNDATION
PP14-21-UMB-CDQ-WP-004
SECTIONS & DETAILS”– Rev.0
“ACCESSARY LF & AA MODULE FOUNDATION
PP14-21-UMB-CDQ-WP-001
PLAN, SECTIONS & DETAILS”– Rev.0
“GAS TURBINE GENERATOR FOUNDATION
PP14-22-UMB-CDQ-WP-001
PLANS”– Rev.0
“GAS TURBINE GENERATOR FOUNDATION
PP14-22-UMB-CDQ-WP-004
SECTIONS & DETAILS”– Rev.0
“ACCESSARY LF & AA MODULE FOUNDATION
PP14-22-UMB-CDQ-WP-001
PLAN, SECTIONS & DETAILS”– Rev.0
“GAS TURBINE GENERATOR FOUNDATION
PP14-23-UMB-CDQ-WP-001
PLANS”– Rev.0

7
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 8 of 25

“GAS TURBINE GENERATOR FOUNDATION


PP14-23-UMB-CDQ-WP-004
SECTIONS & DETAILS”– Rev.0
“ACCESSARY LF & AA MODULE FOUNDATION
PP14-23-UMB-CDQ-WP-001
PLAN, SECTIONS & DETAILS”– Rev.0
PP14-00-UHY-CDA-WP-001 “ACC 28 UTILITY BRIDGE LAYOUT”– Rev.0
PP14-00-UHY-CDA-WP-002 “ACC 18 UTILITY BRIDGE LAYOUT”– Rev.0
“ACC 18 UTILITY BRIDGE FOUNDATION TYPES
PP14-00-UHY-CDQ-WP-001
SECTIONS & DETAILS”– Rev.0
“ACC 28 UTILITY BRIDGE FOUNDATION TYPES
PP14-00-UHY-CDQ-WP-002
SECTIONS & DETAILS”– Rev.0
PP14-28-URC-CDA-WP-001 “ACC BLOCK 20 FOUNDATION PLAN”– Rev.0
PP14-00-URC-CDQ-WP-001 “ACC BLOCK 20 FOUNDATION DETAILS”– Rev.0
“ACC STEAM DUCT BLOCK 20 FOUNDATION
PP14-00-URC-CDQ-WP-002
DETAILS”– Rev.0
“ACC STAIRCASE STRUCTURE BLOCK 20
PP14-00-URC-CDQ-WP-003
FOUNDATION DETAILS AND PLAN”– Rev.0
“CONDENSATE TANK STRUCTURE
PP14-00-URC-CDQ-WP-004
FOUNDATION DETAILS BLOCK 20”– Rev.0
“BYPASS STACK FOUNDATION
PP14-23-UHA-CDQ-WP-005
PLAN,SECTIONS,DETAILS”– Rev.0
“ELECTRICAL MANHOLES - PLAN,
PP14-00-UBR-CDQ-WP-001 REINFORCEMENT SECTIONS & SCHEDULE”–
Rev.0
“MAIN UTILITY FOUNDATION LAYOUT PLAN -
PP14-00-UMY-CDA-WP-001
SHEET 1” – Rev.0
“MAIN UTILITY FOUNDATION LAYOUT PLAN -
PP14-00-UMY-CDA-WP-002
SHEET 2” – Rev.0
“MAIN UTILITY FOUNDATION TYPES
PP14-00-UMY-CDQ-WP-001
SCHEDULE AND DETAILS” – Rev.0
“HRSG FOUNDATION PLANS & SECTIONS” –
PP14-23-UHA-CDQ-WP-001
Rev.0
“HRSG FOUNDATION ANCHOR BOLT / SHEAR
PP14-23-UHA-CDQ-WP-002 POCKET ENLARGED PLANS & SECTIONS” –
Rev.0

8
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 9 of 25

“HRSG FOUNDATION ANCHOR BOLT / SHEAR


PP14-23-UHA-CDQ-WP-003 POCKET ENLARGED PLANS & SECTIONS” –
Rev.0
“HRSG FOUNDATION ANCHOR BOLT
PP14-23-UHA-CDQ-WP-004
ASSEMBLES SCHEDULE & DETAILS” – Rev.0
“UNDERGROUND CONDUIT LAYOUT POWER
PP14-10-BYB-EDA-WP-018
GENERATION BUILDING BLOCK – 10” – Rev.0
“DUCT BANK MANHOLE DETAIL POWER
PP14-10-BYB-EDA-WP-030
GENERATION BLOCK – 10” – Rev.0
“DUCT BANK MANHOLE DETAIL POWER
PP14-10-BYB-EDA-WP-031
GENERATION BLOCK – 10” – Rev.0
“DUCT BANK SECTION & CONDUIT DETAIL
PP14-10-BYB-EDA-WP-032
POWER GENERATION BLOCK – 10” – Rev.0
“ENLARGE VIEW 1 POWER GENERATION
PP14-10-BYB-EDA-WP-034
BUILDING GAS TURBINE – 11 ” – Rev.0
“ENLARGE VIEW 1 POWER GENERATION
PP14-10-BYB-EDA-WP-035
BUILDING GAS TURBINE – 12 ” – Rev.0
“ENLARGE VIEW 1 POWER GENERATION
PP14-10-BYB-EDA-WP-036
BUILDING GAS TURBINE – 13 ” – Rev.0
“DUCT BANK MANHOLE DETAIL POWER
PP14-10-BYB-EDA-WP-038
GENERATION BLOCK – 10” – Rev.0
“UNDERGROUND CONDUIT LAYOUT POWER
PP14-20-BYB-EDA-WP-019
GENERATION BUILDING BLOCK – 20” – Rev.0
“DUCT BANK MANHOLE DETAIL POWER
PP14-20-BYB-EDA-WP-038
GENERATION BLOCK – 20” – Rev.0
“DUCT BANK MANHOLE DETAIL POWER
PP14-20-BYB-EDA-WP-039
GENERATION BLOCK – 20” – Rev.0
“DUCT BANK SECTION & CONDUIT DETAIL
PP14-20-BYB-EDA-WP-041
POWER GENERATION BLOCK – 20” – Rev.0
“ENLARGE VIEW 1 POWER GENERATION
PP14-20-BYB-EDA-WP-043
BUILDING GAS TURBINE – 21 ” – Rev.0
“ENLARGE VIEW 1 POWER GENERATION
PP14-20-BYB-EDA-WP-044
BUILDING GAS TURBINE – 22 ” – Rev.0
“ENLARGE VIEW 1 POWER GENERATION
PP14-20-BYB-EDA-WP-045
BUILDING GAS TURBINE – 23 ” – Rev.0
And all approved Drawings related to concrete works.

9
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 10 of 25

 Documents
Ref. Title
PMG-PRO-10 Development and Control of Project IMS Documents and
Records
PMG-WI-001 Guidelines to Develop a Method Statement
QLT-WI-002 Codification of IMS Document
QLT-PRO-04 Control of Inspection and Testing of permanent works
JSP-QM-43-10-001 Inspection Procedure for Civil Works (with ITP)
HSE-PRO-10 HSE Risk Assessment for Activities
11061-PMG-PRO-10-D01 Project Quality Plan
11061-PMG-PRO-10-D02 Project HS Plan
11061-PMG-PRO-10-D03 Construction Environmental Management Plan
SCS-Q-003 SCECO Construction Standards Cast In Place Concrete
PP14-00-Y-UFG-SAR-001 Method Statement for General Excavation & Backfilling
Inspection and Test Plan for Concrete Civil Works Cast
11061-QLT-PRO-04-F03
in Place and Precast Elements

4.0 Definitions, Terms and Abbreviations

4.1 Definition and Terms


No definitions or terms require further explanation or analysis, than that stated in the present
document.
4.2 Abbreviations
 P.E.L : Plant Elevation Level
 P.G.B : Power Generation Building
 T.O.C.: Top of Concrete
 B.O.C.: Bottom of Concrete
 W.: Wall
 C.J.: Construction Joint

5.0 Responsibility

5.1 The Project Manager is responsible to appoint site supervisory personnel to organize,
coordinate, and oversee the execution of the work detailed in this method statement.
5.2 The Construction Manager is responsible for the organization and coordination of the entire
work detailed in this method statement.
5.3 The responsible Section Engineer is responsible for the execution of the works detailed in this
method statement. He will be responsible for instructing the Foremen/Superintendent about the
requirements of the contract, including all restrictions, safety regulations, scope of work and
time schedule. In addition, he will be responsible for related logistic matters and all matters
related to HSE and the quality of the works.
10
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 11 of 25

5.4 The Site Civil Engineers are responsible to assist the Section Engineer and to ensure that the
construction teams will be provided with the necessary information to execute their work
accurately and effectively.
5.5 The Superintendent/Foreman is responsible for the day-to-day implementation and supervision
of the works detailed in this method statement.
5.6 Assigned HSE staff is responsible to assist the construction team to develop safe methods of
working and to monitor implementation of the controls as required.
5.7 Assigned QA/QC staff is responsible to assist the construction team to ensure all works comply
with specified requirement and to monitor implementation of the controls as required.

6.0 Materials and Equipment

6.1 Materials
 All materials to be used in the permanent works will comply with the latest project
specifications and appropriate Material Approvals will be submitted and approved prior to the
incorporation of the materials into the works.
 Quality Control tests will be performed as required by the project specifications to ensure
compliance prior to any materials being incorporated in the works.

 The main items of permanent materials are as follows:

- Concrete Grade 15/200 KG/m3 Class A (Lean concrete & Conduit duct bank outside
traffic area).
- Concrete Grade 35/400 KG/m3 Class B (Walls, Paving & slab all above grade).
- Concrete Grade 35/400KG/m3 Class C (All RC Foundation below grade).
- Retarding Admixtures.
- Air-entrainment admixture.
- Curing Compound.
- Concrete Repair Mortar (Minor/Major Defects).
- Bonding Agent.
- Potable water.
- Reinforcing Steel (According to the Technical Specifications).
- PVC Water Stop.
- Mould Release Agent.
- Bituminous paint.
- Plasticized sheet vapor barrier.
- Non-shrink Grout.
- Anchor Bolts.
- Embedded plates.
- Expansion joint filler board.
- Joint sealant.
- Embedded pipes / duct works.
- Earthing details.

11
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 12 of 25

6.2 Equipment
 All equipment to be used in the permanent works will comply with the latest project
specifications and appropriate Material Approvals will be submitted and approved prior to
the incorporation of the equipment into the works.

 Quality Control tests will be performed as required by the project specifications to ensure
compliance prior to any equipment being incorporated in the works.

7.0 Resources
7.1 Land Based Equipment
Description No.

Concrete Pumps As Required

Concrete Transit Mixers As Required

Vibrators/Mass Vibrators As Required

Mobile Cranes As Required

7.2 Personnel / Workforce:

Description No.
Foremen One
Carpenters
Steel Fixers
Masons
Scaffolders
Labor
Riggers/Flagmen As Required
Concrete Pump Operators
Transit Mixer Drivers
Electricians
Tower Crane Operators
Mobile Crane Operators

12
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 13 of 25

8.0 Methodology / Procedure

8.1 General
This Section includes all operations for casting typical concrete foundations and
slabs including blinding concrete, formwork, reinforcement, embedded items, water
stops, construction joints, transportation & placement and curing of concrete.

8.2 Transportation and Delivery of Concrete


The concrete will be delivered from the batching plant to the place of pouring in
agitating transit mixers. Before departure of the loaded transit mixer from the batching
plant, the delivery ticket will be handed over to the driver.

In order for the concrete to maintain a homogeneous mass, transit mixers shall have
drums rotating continually both during transportation and while waiting to discharge.
The mixers prior to discharge will stop at the site laboratory, or at a suitable testing
station within the construction site, where tests will be performed on the fresh concrete
and cylinders will be taken for strength tests for the casting of test cubes. The
frequency of testing shall be in accordance with the ‘’Inspection and Test Plan for
Concreting Works’’.
No addition of water shall be permitted at any point after the transit mixer has left the
batching plant.

Should we require to increase the concrete slump to maintain or achieve better


workability, but without exceeding the maximum dosage which is permitted, one
addition of plasticizer will be allowed after consultation with the batching plant
manager.

If water additives are added to the fresh concrete after leaving the batching plant, then
the company representative is to be advised.

The concrete will be transferred to the point of placement in one of the following
ways:
a) By metal chutes.
b) By concrete pump.
c) By concrete bucket with bottom opening. The bucket will be carried to
the place of pouring by crane.

8.3 Lean concrete of 100mm thickness:


A Lean concrete layer Class A grade 15 / 200 Kg/m3, will be poured on the compacted
soil. The Lean concrete layer shall be minimum 100mm thick will cover an area
exceeding the foundation footprint by 100mm on each side. The Lean concrete surface
will be toweled to achieve a smooth surface.

13
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 14 of 25

8.4 Bitumen Coating:


Two coats of Nito Proof 10 bitumen coating, or similar approved, will be applied to
the blinding concrete layer top surface. A two hour period will be afforded between
coats in accordance with the manufacturer’s instructions. Prior to the application, it
will be ensured that the concrete surface will be dry and free from dirt, dust, oil and
grease.

8.5 Vapor Barrier


Vapor barrier of 250 microns will be provided on top of lean concrete prior to install
rebar & formwork. In the case of the grade slab a vapor barrier will be provided in the
form of a 250 micron thick plasticized sheet laid on the ground surface prior to pouring
the grade slab concrete to prevent bleeding of the blinding concrete that will
subsequently be poured. A 300 mm minimum lap shall be maintained where the
plasticized sheet is jointed as per the approved drawings.

8.6 Formwork
Formwork will be comprised of steel or timber frame panels or proprietary formwork
material and will be supported by props anchored on surrounding shores and on the
protective concrete layer or any other supporting surfaces or members.
Formwork will be of adequate strength and rigidness, and will be installed sufficiently
tight to prevent loss of mortar from the poured concrete, as well as to ensure the
accurate dimensions of all reinforced concrete elements.
Upward or lateral displacement of any part of the formwork system will be prevented
during all time of works. When forms for continuous surfaces are placed in successive
units, the forms will be fitted over the completed surface to obtain a continuous
alignment and to avoid leakage of mortar.
Surveyors will mark the location of all formwork system. Checking of location,
verticality and cleanness will be carried out prior to any further actions.
Void formers will be prevented from moving horizontally or vertically. Form ties
where used shall be sleeved by PVC pipe to allow subsequent withdrawal. Before any
use of the formworks, all members will have to be clean, with all loose elements, loose
bindings and any other extraneous matter removed.
A Chemical Mould Release Agent, FOSAM Company Limited or similar approved,
will be smeared on the inner surface of all formwork panels before installation, to
ensure their smooth subsequent removal.
The criteria for striking vertical formwork, not supporting the self-weight of concrete,
shall be solely based on a minimum compressive strength requirement. In accordance

14
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 15 of 25

with CIRIA Report 136; Formwork Striking Times, a minimum value of in situ cube
strength of 2 M Pa is required to prevent mechanical damage.
Once removed, formwork will be prepared for being reused where and when required
based on schedule of works.
8.7 Reinforcement
Steel reinforcement bars, cut and bend in accordance with approved drawings, will
be supplied by approved supplier. Cutting and bending of all reinforcement bars will
be done in accordance to the project specifications.
Non-structural connections for the positioning of reinforcement will be made with
1.5mm black tie wire from Al-Faizal Steel Products Company, or other approved
supplier. Care will be taken to ensure that projecting ends of ties do not encroach
into the concrete cover.
Concrete spacers will be used for the proper placing, spacing and supporting of all
reinforcement bars. The concrete spacers will be manufactured from the same
concrete grade as that of the concrete element under construction. Additionally,
spacers will ensure the required concrete cover based on relevant design drawings is
achieved.
Reinforcement bars will be protected from rough handling, shock loading (prior to
embedment) and the dropping from a height. Reinforcement will be secured against
displacement outside the specified limits.
Reinforcement will not be surrounded by concrete unless it is free from mud, oil,
paint, retarders, grease or any other substance which can be shown to adversely
affect the steel or concrete chemically, or reduce the bond.
The positioning of reinforcement shall be checked before and during concreting.
Particular attention will be directed to ensuring that the required cover in maintained
within the limits given.
8.8 Construction Joints
Construction joint locations will be as per the drawings issued for construction. The
number of additional construction joints will be kept to the minimum necessary for
the adequate execution of the works. Generally they will be located at right angles to
the main direction of the reinforced concrete members. Vertical joints will be formed
against a stop end.
The top surface of a layer of concrete will be level and reasonably flat. When a kicker
is used, it will be at least 70mm high and cast with the previous concrete.
The surface of the first pour will be roughened to increase the bond strength and to
provide aggregate interlock. Both at horizontal and vertical construction joints, a
retarder on the stop end will be applied, to enable the joints surfaces to be treated after
the stop end has been removed. Rugasol ® -2 Liquid PDS, a Water based Concrete
Surface Retarder, or similar approved will be applied to the shutters face forming the
construction joints, and at the concrete top where the construction joints are

15
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 16 of 25

horizontal. The retarder will be removed by water jetting shortly after the stripping of
the formwork, leaving exposed aggregate concrete finish at the construction joint
surface.
Care will be taken to ensure that the joints’ surfaces are clean immediately before the
fresh concrete is placed against it. Joint surfaces will be soaked with water and
bonding agent Nitobond 10 or similar approved will be applied. Prior to the new
concrete being placed, to prevent excessive loss of mix water into the previous cast
by absorption and enhance the bonding between the existing concrete surface and the
newly laid concrete. Particular care will be taken in the placing of new concrete close
to the joints to ensure it is fully compacted and dense.
8.8.1 Concrete Pouring
Concrete of approved mix design will be supplied by Saudi Archirodon Ltd own
site based batching plant or other approved supplier. During concreting operations a
stand-by batching plant will be made available. This second/stand-by batching plant
will be Saudi Ready-mix Concrete Co or other approved supplier.
The temperature of the mixed concrete shall not exceed below criteria referred in
table - 1 at discharge into the works. Measures to assist keeping the concrete within
the required temperature levels, will include keeping the aggregates in a shaded area
prior to batching, adding ice to the mixing water during batching, and spraying with
water the formwork and reinforcement before placement.
Massive concrete (over 2400 mm thk.) Max. 21° C & Min. 10° C
Massive concrete (less than 2400 mm but more than
Max. 27° C & Min. 10° C
1200 mm thk.)
Concrete (less than 1200 mm but more than 300 mm
Max. 35° C & Min. 10° C
thk.)
Concrete (less than 300 mm thk.) Max. 35° C & Min. 12.8° C

Table - 1
Discharge of concrete will be done within a maximum of ninety (90) minutes from
the time of batching. Placement into the works will be carried out via truck mounted
concrete pumps. A stand-by concrete pump will be available at all times in case of a
breakdown.
Pouring of the concrete in each element shall be done in a continuous operation and
in horizontal layers of 450 mm maximum thickness. The concrete mix must have
sufficient workability at the time of compaction to ensure that reinforcement is
thoroughly embedded into the concrete mass.
Concrete will be well compacted with the use of concrete vibrators during the process
of pouring. Concrete vibrators shall penetrate by 150mm, the layer below in cases of
a multilayer concrete casting. Concrete will have to be thoroughly worked around the
reinforcement, the water stops and into the formwork system inner corners, in order
to prevent honey combing or planes of weakness. Vibration will continue until the

16
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 17 of 25

expulsion of air has practically ceased and in a manner that does not promote
segregation. Over-vibration will be avoided to prevent the risk of harming a weak
surface layer. The concrete shall be placed in a manner to avoid segregation. Tremie
pipes will be used where necessary to avoid the concrete being dropped into place
from a height exceeding 1.5 meters. No concrete transportation within the formwork
system is allowed by the use of mass concrete vibrators.
The Concrete top surface shall be screeded and floated to achieve the required finish.
Once the concrete is of adequate stiffness and the film of moisture has been removed,
a fine finish will be achieved by refloating or by mechanical means.
All concreting operations will be supervised by a competent person at all times.
8.8.2 Concrete Curing
As soon as the concrete has been placed, compacted and finished, the curing process
will begin to prevent moisture loss whilst maintaining a satisfactory temperature
regime.
The process will involve application of a hessian mat over the whole of the exposed
surface of the poured concrete. This hessian layer will be kept moist throughout the
curing duration. A layer of polyethylene sheet will be laid on top of the wet mat to
prevent water evaporation.
On top of the polyethylene sheets, a combination of insulating open cell polyurethane
foam (foam mats) and quilts will be used to prevent heat loss from the surface and to
contain the differential temperature between the concrete core and surface within the
20oC prescribed limit.
The insulation wherever installed will be covered with tarpaulin sheets, which will
increase the insulating value and ensure that the concrete element will be wind proof
to prevent the drying of the concrete surface and propagation of plastic shrinkage
cracking.
2
For Slabs (including Grade slabs), Pavings & horizontal elements, curing
compounds will be used like Masterkure 106 J or similar approved. The compound
will form wax emulsion like blockade and the resultant film retains sufficient moisture
in the concrete to ensure full hydration of the cement and it will help to produce
optimum strength development.
It is suitable for spray application to freshly poured concrete, as soon as the initial
surface sheen has disappeared from concrete surface, as evenly as possible at ratio of
5 - 6 m2 per litre. The compound will removed completely by grinding the surface
prior to the application of any surface finish or treatments, as per the manufacturer
recommendation.
When placing concrete in elements where the smallest dimension is greater than 1000
mm , the temperature differential between the core and surface of the concrete element
will be measured by embedding electronic sensors (thermocouples) in the cast (see
figure - 1).

17
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 18 of 25

The number of thermocouples to be used depends on the dimensions of the structure.


In principal we place one row of thermocouples at mid height, with the first
thermocouple 100 mm from the form, the next one about 250 mm from the form and
the rest spaced about 700 mm apart until we reach the middle of the section. We repeat
the spacing as we approach the opposite side of the section, and repeat this array in a
line perpendicular to the first set and at the center of the cross section. We finally add
a thermocouple near the base and one near the top surface where heat loss may be the
most rapid.
After all works have been completed and prior to pouring the concrete, thermocouple
installation will be carried out. The thermocouple wires will be attached to the
reinforcement with nylon cable zip ties. Immediately after fixing, the thermocouples
shall be checked by comparing readings to the relative ambient temperature. Any
damaged thermocouple wires will be replaced. Doubling the wires will minimize the
risk of them being damaged during the concrete pouring works.

Figure - 1
After placing the concrete, temperature readings shall be taken at regular intervals of
every two hours for first two days after the concrete pouring and every four hours
from third day and logged. This monitoring frequency will continue until the
minimum concrete temperature is 20oC or less than the daily minimum ambient
temperature. Once this is achieved, the curing will cease and all insulation,
polyethylene sheets and other curing material will be removed.

9.0 Quality Control


9.1 All works will be undertaken in compliance with the quality requirements of the Contract,
and PP14-00-Y-CNQ-SAR-001 Rev A, “Project Quality Plan”.

18
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 19 of 25

9.2 All works requiring inspection and testing to demonstrate conformity with requirements
will be undertaken in accordance with PP14-00-Y-CPT-SAR-002 – Rev.0 “Inspection and
Test Plan for Civil Works attached in Appendix A.
9.3 Where non-conformities are found/identified, they will be addressed in accordance with
QLT-PRO-05 – Rev.0 “Control of Non-conformities”.

9.4 The quality control activities associated with the works will be conveyed to all personnel
involved in the execution of the works by the Project QA/QC Manager prior to the
commencement of the work.

9.5 All concrete testing will be monitored and tested by RGF or any approved third party
independent Lab technician.

9.6 Concrete Pouring plan and drawing will be submitted including numbers of equipment to
be used prior to pouring of concrete, if the concrete pour is more than 250 cubic meter.

9.7 Prior to concrete production of Contractor’s Batching Plant and Laboratory, all equipment
will be calibrated and will be submitted for Company Representative approval. And also
concrete trial mix for Contractor’s Batch Plant will be submitted for approval accordingly.

10.0 Health, Safety and Environment


10.1 HSE Program Overview
The HSE Program will be utilizing steps based on “Plan, Do, Check, and Act”
Principles, as shown below:

19
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 20 of 25

10.2 Managing Hazards & Risks


Ref. PP1314-00-Y-UP-WP-018 15. Hazard Identification Program
Ref. PP1314-00-Y-UP-WP-029 6. Managing Hazards & Risk

10.2.1 Planning & Objectives

The fundamental HSE objective for the Project is to achieve a mutually agreed
target of zero harm to People, assets and the environment, and to maintain the
welfare of all Project personnel by removing or reducing to As Low as Reasonably
Practicable (ALARP) all Occupational Safety, Health and Environmental risks
during all field activities. Specific objectives are:

 To define the methods to be applied for the prevention of incidents and the
improvement of HSE standards.
 To foster the maximum involvement by management and employees in
the prevention of accidents through training, orientation and mutual
consultation, and their actions.
 To record and monitor the effectiveness of the Corporate and Project HSE
Management System by utilizing best-practice methodology and
recognized continuous improvement processes.
 Provide a risk-based HSE management system framework, consistent with
ISO QMS 9001:2008, BS OHSAS 18001:2007, AS/NZS 4801, ISO EMS
14001:4004 and other internationally recognized standards that support
the implementation of Project HSE Policies.

20
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 21 of 25

10.2.2 Hazard Identification, Assessment and Control

The Project HSE Management Strategy is to identify hazards and their potential
consequences within the construction environment. This will be achieved by
encouraging the active participation of all personnel in the identification and
continual assessment of hazards to avoid or minimize the risk of the hazard to a
level that is As Low as Reasonably Practicable (ALARP) and/or controlling the
events that could lead to a potentially hazardous situation.
Hazard and risk management techniques, such as HAZIDs, HAZOPs, JSAs, and
START Cards will be used throughout the Project.

 Technical Risks (Safety in Design)


The Technical risks are or may be associated with the construction, engineering
process, facility, operability, and maintainability of the plant.

 Technical Risks (Safety in Design)


The diagram below outlines the five-step process that will be utilized throughout
the construction phase.

 Project HSE Keys


Project personnel working within the operating facility areas will be required to
use a specifically designed “START Card”. This form of hazard identification
card will be undertaken as a team. A card will be done for each new task and
on each new day. It will be revisited if anything changes. The HSE team will
monitor compliance and quality.

21
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 22 of 25

 Job Safety Analysis (JSA)


From a safety perspective, JSA is the most commonly used term and the most
misunderstood within the industry today.
To ensure clarity with regard to this item, this procedure describes JSA in the
context of:
 Tasks that have a history of, or high potential for, injury, near miss or loss-
related Incidents.
 Critical tasks outlines in Company’ Safe Work Procedures or Practices.
 Tasks carried out in new or unusual environments.
 Tasks that have high potential for changing conditions during execution.
 Tasks that are rarely performed in a petrochemical environment.
 Tasks where multiple contractors / subcontractors are required to
sequentially execute an activity.
 Tasks where high ongoing interaction with process operations is required.
 Tasks that have a high potential for impact on the integrity of processing
systems.
 Tasks that need to be performed when a state of zero energy cannot be
achieved.

10.3 Mandatory Safety Rules


Adherence to critical safety rules is mandatory. Failure to follow these rules
allows the potential for serious injury to people or damage to equipment. As such,
the consequence, after investigation, may result in dismissal from site for the
subcontractor’s employee(s) in violation of the rule. In addition, the employee’s
immediate supervisor will be appropriately disciplined and / or dismissed from
the work site. The following are the contractor.
Mandatory Safety Rules:
1. Always protect against falling where you can fall more than 1.8m (6 ft).
2. Never throw or drop any object or tool from one level to another.
3. Never initiate or participate in any physical altercation (fight).
4. Always adhere to work permit procedure.
5. Never engage in any horseplay.
6. Never tamper, alter or remove any safety device.
7. Always verify and tag and lock all energy isolations.
8. Never wilfully give an unsafe instructions nor allow another person / s to
work in an unsafe manner.
9. Always smoke in designated smoking areas.
10. Never begin a skilled task or operate equipment or machinery unless
qualified.
Instructing or allowing an employee to operate any type of equipment without the
required competencies and / or licenses is not allowed.

22
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 23 of 25

10.4 Site Transportation Rules


 Drivers of motor vehicles shall be instructed to exercise judgment as well as
observe posted speed limits. Maximum speed limit is 30 Km/h in all site
premises. Vehicles shall only be operated by employees having a valid driver’s
license and insurance recognized by the Government permitting them to drive
in Saudi Arabia.
 All Contractors’ means of ingress and egress routes will be adequately marked
as such, since their employees are to travel these routes only.
 Pedestrians have right of way over motorized traffic.
 Established signals or turn signals are to be used.
 Ignition key is to be left in cars at all times when within the jobsite. Contractor’s
employees’ cars may be locked within the designated Contractor’s perimeter
parking area.
 Reckless driving or other non- observance of these instructions will be cause
for withdrawal of driving privileges on the project.
 No bicycle or 2 wheeled motorized vehicles are allowed on the project.
 Full caution is to be exercised in the movement of heavy equipment on
EGCW’s roadways.
 Flagmen or grounds-men shall be provided by Contractor ahead of and behind
heavy moving loads to ensure safe movement of this equipment, the Health &
Safety of other plant traffic, protection of pipe

23
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 24 of 25

Appendix A
Inspection and Test Plan for Civil Works

24
SAUDI ARCHIRODON LTD.
Quality (QLT)
Integrated Management System Rev.
Issued for General Use
Employer Ref. PP14-00-Y-CPT-SAR-002 1
Reference No. 11063-QLT-PRO-04-F03 0
Serial No. ITP - 0002
Inspection and Test Plan for Civil Works Page 1 of 12

Verification Activity Acceptance Criteria Verification Point


H , W, S, R (see below)
Document /
Sequence

Frequency Verification Verification


Specification / Drawing (Time, quantity, or
Requirement
No.

Description Personnel Document

SAR
otherwise)

SEC
Ref.

WP
(Specify precise criteria for acceptance)

I
(incl. Cl. No / No’s where
applic.)

1.0 PRELIMINARY
PP1314-00-Y-CI-WP-
005-R1 Section 3.3 Laboratory
Approved Independent

N/A

N/A
1.1 and 3.4 and PP1314- Visual and Document Check Qualification R R

H
Laboratory
00-Y-CI-WP-004-R1 Documents
Sec. 1.6E
1.2 Survey
Surveyor/
QC
Bench Mark Benchmark Validation and

N/A

N/A
1.2.1 IFC Drawing Inspector/ • Survey W S

H
Verification/Approval Document Check
Site Report
Engineer

Surveyor/
Survey Validation and

N/A

N/A

S/R
1.2.2 Survey/Layout IFC Drawings QC • Survey S

W
Document Check
Inspector Report

2.0 EARTHWORKS

Surveyor/
Approved for QC
Survey Validation and

N/A

N/A

S/R
2.1 Setting out Construction Inspector/  Survey S

W
Document check
Drawings Site Report
Engineer
SAUDI ARCHIRODON LTD.
Quality (QLT)
Integrated Management System Rev.
Issued for General Use
Employer Ref. PP14-00-Y-CPT-SAR-002 1
Reference No. 11063-QLT-PRO-04-F03 0
Serial No. ITP - 0002
Inspection and Test Plan for Civil Works Page 2 of 12

Site
As per PP1314-00-Y- • Visual Check Engineer/  Form(11061

N/A

N/A

S/R
2.2 Excavation By Area S

W
CI-WP-004-R1 • Document Check QC -QLT-000-
Inspector 00-F07)

Site
As per PP1314-00-Y-  test result
• Document Check Prior to start of Engineer/

N/A

N/A
2.3 Material Approval CI-WP-004-R1  Material R R

H
• Laboratory Evaluation Check Earthworks activities QC
Section 2.2 Approval
Inspector
Site  RFI
Engineer/  Form(11061
As per PP1314-00-Y- Proof rolling inspection for large
QC -QLT-000-

N/A

S/R
2.4 Subgrade Preparation CI-WP-004-R1 areas and field density testing By Area W H S
Inspector/ 00-F07)
Section 3.1 (FDT)
Lab.  Lab. Test
Technician report
Site  RFI
Engineer/  Form(11061
As per PP1314-00-Y-
FDT Test for subgrade level QC -QLT-000-

N/A
2.5 Subgrade Compaction CI-WP-004-R1 By Area H H W S
(10% Inspection Required) Inspector/ 00-F07)
Section 3.4
Lab.  Lab. Test
Technician report
3.0 BLINDING CONCRETE

Approved
As per PP1314-00-Y-
• Document Review Prior to start of Lean Trial Mix

N/A

N/A
3.1 Concrete Mix Design Approval CI-WP-301-R1, Sec. R R

H
• Trial Mix of Design Concrete Pouring design
1.5
documents
As per PP1314-00-Y-
CI-WP-301-R1 Sec.
Site
3.2B/ PP1314-00-Y-  RFI
Visual and dimensional Once for Every Engineer/

N/A

N/A

S/R
3.2 Pre-placement Inspection CI-WP-004-R1 Sec.  11061-QLT- S

W
Inspection location or Area QC
3.4; PP1314-00-Y-CI- 000-00-F12
Inspector
WP-005-R1, Sec. 3.1
Table 1 & 2
SAUDI ARCHIRODON LTD.
Quality (QLT)
Integrated Management System Rev.
Issued for General Use
Employer Ref. PP14-00-Y-CPT-SAR-002 1
Reference No. 11063-QLT-PRO-04-F03 0
Serial No. ITP - 0002
Inspection and Test Plan for Civil Works Page 3 of 12

 RFI
 11061-QLT-
As per PP1314-00-Y- Site
000-00-F11
CI-WP-301-R1 Sec. Engineer/

N/A

N/A

S/R
3.3 Lean Concrete Placement Visual Inspection  11061-QLT- S

W
2.6.C. 1 ̴ 7 & Sec. 2.E QC
000-00-F09
1 ̴ 10 Inspector
 Batch plant
tickets
● 4 cylinders samples
 RFI
for Compressive Site
 11061-QLT-
Strength every 80 m3 Engineer/
Concrete Sampling & Concrete As per PP1314-00-Y- 000-00-F11
Visual Inspection and Document ● Slump, Temperature QC

N/A
3.4 Testing (Slump, Temperature, CI-WP-301-R1, Sec.  11061-QLT- H S

S
Check Every Truck Mixer Inspector/
Air Content, etc.) 3.4.C.2.a ̴ 1 000-00-F09
Delivered; Independent
Laboratory  Batch Plant
tickets

Site
As per PP1314-00-Y-  RFI
Visual Inspection and Document Once for Every Engineer/

N/A

N/A

S/R
3.5 Post Pour Inspection CI-WP-301-R1, Sec.  11061-QLT- S

W
Check location or Area QC
3.5.A ̴ C 000-00-F10
Inspector
QC  RFI
Inspector /  11061-QLT-
As per PP1314-00-Y-
Concrete compressive Strength Compressive Strength Testing Site 000-00-F11

N/A

S/R
3.6 CI-WP-301-R1Sec. Every 7 & 28 Days H S

W
Testing for 7 & 28 days cylinder sample Engineer/  11061-QLT-
3.4.C.2.i
Independent 000-00-F09
Lab. Tech.  Test Report
4.0 STRUCTURAL CONCRETE

4.1 CONCRETE
Approved
As per PP1314-00-Y-
Trial Mix

N/A

N/A
4.1.1 Concrete Mix Design CI-WP-301-R1 Sec. Trial Mix Design R

R
Design
1.5.D
documents
SAUDI ARCHIRODON LTD.
Quality (QLT)
Integrated Management System Rev.
Issued for General Use
Employer Ref. PP14-00-Y-CPT-SAR-002 1
Reference No. 11063-QLT-PRO-04-F03 0
Serial No. ITP - 0002
Inspection and Test Plan for Civil Works Page 4 of 12

As per PP1314-00-Y- QC Approved


Material Approval (Cement,

N/A

N/A
4.1.2 CI-WP-301-R1 Sec. Document Check/Review Inspector/ Material R

R
etc.)
1.4.B.2.A ̴ S Storekeeper Submittal
4.2 STEEL REINFORCEMENT

As per PP1314-00-Y-
Approve
Material Approval CI-WP-301-R1 Sec. QC

N/A

N/A
4.2.1 Visual Inspection Material R R

R
(Reinforcement, etc.) 1.4.B.2.D & Sec. 2.6 Inspector
Submittal
A̴B

As per PP1314-00-Y-
Storekeeper
CI-WP-301-R1 Sec.

N/A

N/A
4.2.2 Material Storage Visual Inspection QC S S

W
1.4.B.2.d & Sec 2.6 A ̴
Inspector
B

4.3 PRE-PLACEMENT INSPECTION AND PLACEMENT RELEASE

Verification of concrete Surveyor/


structure location and elevation Site  RFI
Survey Validation and Once for Every

N/A

N/A
4.3.1 and setting out of Embedded IFC Drawing Engineer/  Survey W S

W
Document Check location or Area
Items (anchor bolts/embedded QC Report
plate) location and elevation Inspector
Site
As per PP1314-00-Y-  RFI
Pre-pour Inspection and Pour Visual Inspection & Document Engineer/

N/A

N/A
4.3.2 CI-WP-301-R1, Sec.  11061-QLT- W S

H
Release Check QC
3.2 A ̴ D 000-00-F12
Inspector
As per PP1314-00-Y- Site
 RFI
Rebar Fabrication and CI-WP-301-R1 Sec. Visual Inspection & Document Engineer/

N/A

N/A
4.3.2.1  11061-QLT- W S

H
Installation 1.5.B.1 ̴ 9 & Sec. Check QC
3.2.B 1 ̴ 9 Inspector 000-00-F12

 RFI
As per PP1314-00-Y- Site
 11061-QLT-
CI-WP-301-R1, Sec. Visual Inspection & Document Engineer/

N/A

N/A
4.3.2.2 Formwork/Support, Joints, etc. 000-00-F12 W S

H
3.2.A.1 ̴ 11 & Sec. Check QC
3.2.D.1 ̴ 6 Inspector  11061-QLT-
000-00-F08
SAUDI ARCHIRODON LTD.
Quality (QLT)
Integrated Management System Rev.
Issued for General Use
Employer Ref. PP14-00-Y-CPT-SAR-002 1
Reference No. 11063-QLT-PRO-04-F03 0
Serial No. ITP - 0002
Inspection and Test Plan for Civil Works Page 5 of 12

 RFI
As per PP1314-00-Y- Site
 11061-QLT-
Anchor Bolts and other CI-WP-301-R1, Sec Visual Inspection & Document Engineer/

N/A

N/A
4.3.2.3 000-00-F12 W S

H
Embedded Items 3.2.C.1 ̴ 8 & Sec. Check QC
3.4.B.1 ̴ 2 Inspector  11061-QLT-
000-00-F08
4.4 PLACEMENT OF STRUCTURAL CONCRETE
● 4 cylinders samples
for Compressive
Strength every 80 m3
● 1 cylinder Samples
for Water Permeability
 RFI
once per month Site
 11061-QLT-
●1 cylinder Sample Engineer/
Concrete Sampling & Concrete As per PP1314-00-Y- 000-00-F11
for Chloride QC

N/A
4.4.1 Testing (Slump, Temperature, CI-WP-301-R1, Sec. Concrete Sampling Inspection  11061-QLT- W S

W
H
Permeability once per Inspector/
Air Content, etc.) 3.4.C.2.a ̴ 1 000-00-F09
month Independent
● Slump, Temperature Lab. Tech.  Batch Plant
Every Truck Mixer tickets
Delivered;
●Air Content every
80 m3

 RFI
Site
 11061-QLT-
As per PP1314-00-Y- Engineer/
000-00-F11
CI-WP-301-R1, Sec. QC

N/A

N/A
4.4.2 Concrete Placement Visual Inspection  11061-QLT- W S

W
2.6.C.1 ̴ 7, Sec. 3.2.F ̴ Inspector/
000-00-F09
H & Sec. 3.2.E.1 ̴ 10 Independent
Lab. Tech  Batch Plant
tickets
Site
As per PP1314-00-Y-
Engineer/

N/A

N/A
4.4.3 Concrete Curing Process CI-WP-301-R1, Sec Visual Inspection  RFI S S

W
QC
3.5.A ̴ C
Inspector
SAUDI ARCHIRODON LTD.
Quality (QLT)
Integrated Management System Rev.
Issued for General Use
Employer Ref. PP14-00-Y-CPT-SAR-002 1
Reference No. 11063-QLT-PRO-04-F03 0
Serial No. ITP - 0002
Inspection and Test Plan for Civil Works Page 6 of 12

● Formworks not
supporting concrete
weight will be
removed 12 hrs after
the casting;  RFI
Site
As per PP1314-00-Y- ● Slabs and Beams  11063-QLT-
Engineer/

N/A

N/A
4.4.4 Removal of Formworks CI-WP-301-R1, Sec. Visual Inspection will be removed at 15 000-00-F10 S S

S
QC
3.2.J.1 ̴ 3 Mpa concrete
Inspector  11063-QLT-
strength; 000-00-F08
● Walls and Columns
will be removed at 2
Mpa Concrete
Strength.
 RFI
As per PP1314-00-Y- QC  11063-QLT-
Compressive Strength Test (7 & CI-WP-301-R1; Sec. Compressive Concrete Crushing Inspector/ 000-00-F11

N/A

S/R
4.4.5 Every 7 & 28 Days S

W
H
28 days test) 1.5.D.11 & Sec Inspection Independent  11063-QLT-
3.4.C.2.i Lab. Tech. 000-00-F09
 Test Report

4.5 CONCRETE REPAIR WORKS

As per PP14-00-Y-CI- Approved


Visual Inspection & Document

N/A

N/A
4.5.1 Material Approval WP-301-R1, Sec. K 1 Material R R

H
Check
&2 Document

As per PP1314-00-Y-
 RFI
CI-WP-301-R1, Sec. Site
 11061-QLT-
3.2-J-3.e & Sec. K 1 & Engineer/

N/A

N/A
4.5.2 Concrete Repair Procedure Visual/Dimensional Inspection 000-00-F10 W S

H
2 and Approved QC
Concrete Method Inspector  11061-QLT-
Statement 000-00-F08
SAUDI ARCHIRODON LTD.
Quality (QLT)
Integrated Management System Rev.
Issued for General Use
Employer Ref. PP14-00-Y-CPT-SAR-002 1
Reference No. 11063-QLT-PRO-04-F03 0
Serial No. ITP - 0002
Inspection and Test Plan for Civil Works Page 7 of 12

 RFI
Site
 11061-QLT-
Approved Method Engineer/

N/A

N/A
4.5.3 Conduct Repair Works Visual Inspection 000-00-F10 W S

H
Statement/Procedure QC
Inspector  11061-QLT-
000-00-F08
 RFI
QC  11063-QLT-
As per PP1314-00-Y-
Compressive Strength Test (7 & Inspector/ 000-00-F11

N/A

S/R
4.5.4 CI-WP-301-R1, Sec. Compressive Strength Inspection S

W
H
28 days test), if needed Independent  11063-QLT-
C-2
Lab. Tech. 000-00-F09
 Test Report
5.0 GROUTING WORKS (Non-shrink Cementitious grout/Epoxy grout)

Approved
PP1314-00-Y-CI-WP-

N/A

N/A
5.1 Material Approval Document Review/Approval Material R R

H
302-R1 Sec. 3.1
Document
 RFI
Site
 11063-QLT-
Inspection and Surface PP1314-00-Y-CI-WP- Visual Inspection/Dimensional Engineer/

N/A

N/A
5.2 000-00-F15 W S

H
Preparation 302-R1, Sec. 3.2 Inspection QC
Inspector  11063-QLT-
000-00-F16
 RFI
Site
 11063-QLT-
PP1314-00-Y-CI-WP- Engineer/

N/A

N/A
5.3 Pre-Grouting Inspection Visual Inspection of Formworks 000-00-F15 W S

W
302-R1, Sec. 3.2 QC
Inspector  11063-QLT-
000-00-F16
 RFI
PP14-00-Y-CI-WP- Site
 11063-QLT-
302-R1, Sec. 3.2.B & Engineer/

N/A

N/A
5.4 Grout Placement Procedure Visual Inspection 000-00-F15 S S

W
Manufacturer’s QC
Recommendation Inspector  11063-QLT-
000-00-F16
SAUDI ARCHIRODON LTD.
Quality (QLT)
Integrated Management System Rev.
Issued for General Use
Employer Ref. PP14-00-Y-CPT-SAR-002 1
Reference No. 11063-QLT-PRO-04-F03 0
Serial No. ITP - 0002
Inspection and Test Plan for Civil Works Page 8 of 12

 RFI
PP1314-00-Y-CI-WP- Site
 11063-QLT-
302-R1 Sec. 3.2.C & Engineer/

N/A

N/A
5.5 Grout Finishing and Curing Visual Inspection 000-00-F15 S S

W
Manufacturer’s QC
Recommendation Inspector  11063-QLT-
000-00-F16
 RFI
Site
 11063-QLT-
Engineer/
000-00-F15
PP1314-00-Y-CI-WP- QC

N/A

N/A
5.6 Grout Sampling and Testing Grout Sampling Inspection  11063-QLT- S S

W
302-R1 Sec. 3.3-3.4 Inspector/
000-00-F16
Independent
Lab. Tech.  11063-QLT-
000-00-F11
 RFI
QC
As per PP1314-00-Y-  11063-QLT-
Inspector/

N/A

N/A

S/R
5.7 Compressive Strength Test CI-WP-302-R1, Sec. Inspection of Test Results 000-00-F09 S

W
Independent
3.4-C/D
Lab. Tech  11063-QLT-
000-00-F11
6.0 CONCRETE PROTECTIVE COATINGS

6.1 BITUMINOUS FELT MEMBRANE

 Approved
As per PP1314-00-Y-
Material

N/A

N/A
6.1.1 Material Approval CI-WP-301-R1, Sec. Document Review/Approval R R

H
Submittal
3.8

 RFI
Site
 11063-QLT-
As per Manufacturer’s Surface properly cleaned and Engineer/

N/A

N/A
6.1.2 Concrete Surface Preparation 000-00-F17 S S

W
Recommendation defects corrected. QC
Inspector  11063-QLT-
000-00-F18
SAUDI ARCHIRODON LTD.
Quality (QLT)
Integrated Management System Rev.
Issued for General Use
Employer Ref. PP14-00-Y-CPT-SAR-002 1
Reference No. 11063-QLT-PRO-04-F03 0
Serial No. ITP - 0002
Inspection and Test Plan for Civil Works Page 9 of 12

 RFI
As per PP14-00-Y-CI- Site
 11063-QLT-
Installation of Bituminous felt WP-301-R1, Sec. 3.8 Visual Inspection. Surface Engineer/

N/A

N/A

S/R
6.1.3 000-00-F17 S

W
membrane & Manufacturer’s should be dry QC
Recommendation Inspector  11063-QLT-
000-00-F18
 RFI
As per PP1314-00-Y- Site
 11063-QLT-
Elastomeric Polyurethane CI-WP-301-R1, Sec. Visual inspection and Document Engineer/

N/A

N/A

S/R
6.1.4 000-00-F17 S

W
Coating 3.8 & Manufacturer’s Checking QC
Recommendation Inspector  11063-QLT-
000-00-F18
6.2 BITUMINOUS PAINT

As per PP1314-00-Y-  Approved

N/A

N/A
6.2.1 Material Approval CI-WP-301-R1, Sec. Document Review/Approval Material R R

H
3.7 & 3.8 Submittal

 RFI
Site
 11063-QLT-
As per Manufacturer’s Surface properly cleaned and Engineer/

N/A

N/A
6.2.2 Concrete Surface Preparation 000-00-F17 S S

W
Recommendation defects corrected QC
Inspector  11063-QLT-
000-00-F18
As per PP1314-00-Y-
CI-WP-301-R1,
 RFI
Section 3.7 & 3.8 & Site
 11063-QLT-
Application of Bituminous Paint PP1314-00-Y-CI-WP- Engineer/

N/A

N/A

S/R
6.2.3 Visual Inspection 000-00-F17 S

W
1st/2nd coat 901 Section 3.5-D-a.1 QC
or as per Inspector  11063-QLT-
Manufacturer’s 000-00-F18
Recommendation
SAUDI ARCHIRODON LTD.
Quality (QLT)
Integrated Management System Rev.
Issued for General Use
Employer Ref. PP14-00-Y-CPT-SAR-002 1
Reference No. 11063-QLT-PRO-04-F03 0
Serial No. ITP - 0002
Inspection and Test Plan for Civil Works Page 10 of 12

As per PP1314-00-Y-
CI-WP-301-R1,
 RFI
Section 3.7 & 3.8 & Site
 11063-QLT-
Application of Bituminous Paint PP1314-00-Y-CI-WP- Visual Inspection and Document Engineer/

N/A

N/A
6.2.4 000-00-F17 S S

W
Final coat 901 Section 3.5-D-a.1 Checking QC
or as per Inspector  11063-QLT-
Manufacturer’s 000-00-F18
Recommendation
Site
As per PP1314-00-Y-
Inspection Of Polyethylene Visual Inspection and Document Engineer/

N/A

N/A
6.2.5 CI-WP-301-R1,  RFI S S

W
Sheets Checking QC
Section 3.8
Inspector

Site
As per PP1314-00-Y- Visual Inspection and Document Engineer/

N/A

N/A
6.2.6 Protection Board  RFI S S

W
CI-WP-301-R1 Checking QC
Inspector
As per PP1314-00-Y-
CI-WP-301-R1,  RFI
Site
Section 3.8 & PP14-  11063-QLT-
Elastomeric Polyurethane Visual Inspection and Document Engineer/

N/A

N/A

S/R
6.2.7 00-Y-CI-WP-901 Sec. 000-00-F17 S

W
Coating Checking QC
3.5.D-a.2 , As per
Inspector  11063-QLT-
Manufacturer’s 000-00-F18
Recommendation
7.0 STRUCTURAL BACKFILL
Site
PP1314-00-Y-CI-WP- Review of Laboratory Test Engineer/

N/A

N/A
7.1 Evaluation of Backfill Materials  Test Results R R

H
004-R1, Sec. 2.2.A-C Results QC
Inspector
SAUDI ARCHIRODON LTD.
Quality (QLT)
Integrated Management System Rev.
Issued for General Use
Employer Ref. PP14-00-Y-CPT-SAR-002 1
Reference No. 11063-QLT-PRO-04-F03 0
Serial No. ITP - 0002
Inspection and Test Plan for Civil Works Page 11 of 12

 RFI
PP14-00-Y-CI-WP- Site  11063-QLT-
Subgrade Preparation/Release 004-R1, Sec. 3.2.E.1-6 Visual Inspection/Document Engineer/ 000-00-F07

N/A

N/A

S/R
7.2 S

W
note for Backfilling GEMSS-C-08 review QC  11063-QLT-
CLAUSE 9.1.8.2 Inspector 000-00-F08

Every 300mm layer


 For Random Fill:
One test for each 5000
ft2 (465 m2) of
fill material placed or
one test per lift,
Checking and Measurement of whichever is more
PP14-00-Y-CI-WP- layer thickness and each lift shall frequent. Site  RFI
Backfilling and Compaction 004-R1 be brought to the required  Select and Engineer/  11063-QLT-

N/A

N/A
7.3 W S

H
every 200mm layer GEMSS-C-08, density and checked by Structural Fill: QC 000-00-F07
CLAUSE 9.1.8.2 appropriate field test before One test for each Inspector  Test report
proceeding with next lift 2500 ft2 (232 m2) of
fill material placed or
one test per lift,
whichever is more
frequent,

8.0 COMPLETED DOCUMENTATION

 Punchlist

N/A

N/A
8.1 Walkdown/Punchlist Visual Inspection of defects  11063-QLT- W S

H
000-00-F08
SAUDI ARCHIRODON LTD. Early and General Civil Works for Riyadh
Integrated Management System PP14 - Combined Cycle Power Plant
Employer Ref. No. PP14-00-Y-CNL-SAR-002 Rev 2
Reference No. 11061-PMG-PSP-03-F01 Rev 0
Method Statement for Serial No. 0005
Concrete Operations
Page Page 25 of 25

Appendix B
Job Safety Analysis (JSA)

25