Programme of Remaining Works considering new quantities due to re-grading and re-profiling of

Earthworks, Subbase and Base Course, Surface Course excluding the potential New Structures
REV. 03
Activity ID Activity Name Original Start Finish
Duration 2022 2023 2024 2025
J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F
407 30-Sep-22
TR4 PACKAGE C- REMAINING WORKS UPDATED PROGRAMME- (Excluding New Structure)-Rev3 10-Nov-23

CONSTRUCTION SCHEDULE ( AREA 1, 2, 3 , 4 & 5 ) 407 30-Sep-22 10-Nov-23


AREA-1 TIAONG BRIDGE TO DOLORES UNDERPASS ( STA. 86+833 TO 87+300 ) 60 04-Nov-22 02-Jan-23
MAJOR & MINOR STRUCTURES 60 04-Nov-22 02-Jan-23
BRIDGES, UNDERPASS AND RCBC 60 04-Nov-22 02-Jan-23
10.0 TIAONG BRIDGE, STA. 86+833.320 (Remaining Works) 27 04-Dec-22 30-Dec-22
11.0 TIAONG INTERCHANGE UNDERPASS, STA. 86+991.404 (Remaining Works) 60 04-Nov-22 02-Jan-23
AREA-2, STA. 86+039 to STA. 86+800 AND STA. 87+300 to STA. 87+450 252 30-Sep-22 08-Jun-23
MAJOR & MINOR STRUCTURES 252 30-Sep-22 08-Jun-23
BRIDGES, UNDERPASS AND RCBC 252 30-Sep-22 08-Jun-23
12.0 DOLORES UNDERPASS BRIDGE, STA. 87+323 52 02-Apr-23 23-May-23
7.0 BALAGO BRIDGE, STA. 86+087.300 246 30-Sep-22 02-Jun-23
SUPERSTRUCTURE 246 30-Sep-22 02-Jun-23
Launching of Girders 1 30-Oct-22 30-Oct-22
Concreting of Diaphragms & Shear Keys 40 30-Sep-22 08-Nov-22
Concreting of Deck Slab 53 13-Oct-22 04-Dec-22
Concreting of Back Wall, Wingwalls & Restrainer 22 05-Dec-22 26-Dec-22
Concreting of Parapet Wall 22 27-Dec-22 17-Jan-23
Installation of Expansion Joint and Concreting of Approach Slab 34 30-Apr-23 02-Jun-23
Construction of Vertical Ditch, Riprap & Flood Light 39 25-Apr-23 02-Jun-23
Construction of Bridge Drainage 26 08-May-23 02-Jun-23
8.0 PNR UNDERPASS, STA. 86+546.985 245 07-Oct-22 08-Jun-23
FABRICATION WORKS 37 07-Oct-22 12-Nov-22
SUPERSTRUCTURE 200 21-Nov-22 08-Jun-23
TR4A2SPS1000 Erection./Launching of Pre-stressed Girders 7 21-Nov-22 27-Nov-22
Concreting of Intermediate Diaphragms 23 28-Nov-22 20-Dec-22
Concreting of Abutment Backwall and Deck Slab 69 08-Dec-22 14-Feb-23
Concreting of Parapet Wall 18 15-Feb-23 04-Mar-23
Concreting of Approach Slab 15 30-Apr-23 14-May-23
Vertical Ditch, Riprap & Flood Light 71 30-Mar-23 08-Jun-23
Construction of Bridge Drainage 24 05-Mar-23 28-Mar-23
AREA-3, AVAILABLE AREA , ( STA. 83+100 TO 86+087 ) 154 29-Nov-22 01-May-23
MAJOR & MINOR STRUCTURES 154 29-Nov-22 01-May-23
ROAD UNDERPASS 154 29-Nov-22 01-May-23
ROAD UNDERPASS, STA. 85+985.303 87 29-Nov-22 23-Feb-23
CONCRETING OF BRIDGE PARAPET 15 29-Nov-22 13-Dec-22

The Adjusted Master Programme with projected completion on 25-August 2024, should be with respect to the conditions as detailed c) Workability Conditions:
below:
Laying of Cement Treated Base (CTB) and laying of Bituminous Concrete Surface Course and its requisite works will be carried out within the dry
a) Design and Approval Process of New Structures: months of January 2023 through May of years 2023 and 2024 as it is impossible to work with these materials if ground is saturated and precipitation is
frequent.
To Finalize and issue to the Contractor on or before 15-November 2022 the design Drawing and Shop Drawing of Road Underpass
intended for pedestrian Walkway at Main Alignment Sta. 83 250 and for the additional road underpass traversing over Alaminos bypass d) Schedule of Potential De-scoped items:
Road at Main Alignment Sta. 81 339.55.
Client de-scope the contractor with the laying of Bituminous Surface course and its other requisite works. However, the aforementioned items were
b) Potential Change in Design and Layout of Miscellaneous Structures: still included in this Programme so that whoever may work on this item will have a reference schedule to follow.

To Finalize on or before 15-November 2022 any potential changes in design and Layout for the Concrete Panel Fence except for the 762 e) Schedule of Toll Plaza & Roundabout Commencement:
LM fencing along Landco Property because of the reasons detailed in the Contractor's Letter (Ref. No. SCIC-SLEXTR4-SLTC-PMC-2022-
L546 dated 30-June 2022 ). The schedule of works in the Toll Plaza which are primarily of civil and MEFP works and Roundabouts is being on hold by Client due to
potential change in Design. Therefore, the contractor decided to include the schedule of work within this Programme. However, upon receipt of the
To Finalize on or before 30 November 2022 any potential changes in Design of New Jersey Barrier ( Reinforced Concrete Median barrier) final instruction for the said item, we will readily adjust the Programme accordingly.
Because of the reasons detailed in the Contractor's Letter (Ref. No. SCIC-SLEXTR4-SLTC-PMC-2022-L546 dated 30-June 2022 ).
Programme of Remaining Works considering new quantities due to re-grading and re-profiling of
Earthworks, Subbase and Base Course, Surface Course excluding the potential New Structures
REV. 03
Activity ID Activity Name Original Start Finish
Duration 2022 2023 2024 2025
J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F
WATERPROOFING FOR WALLS 26 14-Dec-22 08-Jan-23
CONCRETING OF RETAINING WALLS 47 06-Dec-22 21-Jan-23
AGGREGATE SUBBASE COURSE 12 22-Jan-23 02-Feb-23
PORTLAND CEMENT CONCRETE PAVEMENT 21 03-Feb-23 23-Feb-23
GROUTED RIPRAP 15 22-Jan-23 05-Feb-23
ROAD UNDERPASS, STA. 85+586.495 154 29-Nov-22 01-May-23
STRUCTURE EXCAVATION (AWL) 3 29-Nov-22 01-Dec-22
LEAN CONCRETE, t=100mm 3 02-Dec-22 04-Dec-22
CONCRETING OF BOTTOM SLAB & KICKER WALL 10 05-Dec-22 14-Dec-22
CONCRETING OF WALLS 21 15-Dec-22 04-Jan-23
CONCRETING OF TOP SLAB 28 05-Jan-23 01-Feb-23
CONCRETING OF WING-WALLS 18 02-Feb-23 19-Feb-23
CONCRETING OF BRIDGE PARAPET 16 20-Feb-23 07-Mar-23
WATERPROOFING FOR WALLS 25 19-Feb-23 15-Mar-23
CONCRETING OF RETAINING WALLS 33 28-Feb-23 01-Apr-23
AGGREGATE SUBBASE COURSE 12 02-Apr-23 13-Apr-23
PORTLAND CEMENT CONCRETE PAVEMENT 20 12-Apr-23 01-May-23
GROUTED RIPRAP 15 02-Apr-23 16-Apr-23
AREA-5, ( STA 79+950 to STA. 81+920) 300 15-Jan-23 10-Nov-23
DRAINAGE AND SLOPE PROTECTION 180 15-Jan-23 13-Jul-23
REINFORCED CONCRETE PIPE CULVERT 180 15-Jan-23 13-Jul-23
RCBC, STA. 81+032.40 180 15-Jan-23 13-Jul-23
MAJOR & MINOR STRUCTURES 300 15-Jan-23 10-Nov-23
BRIDGES, UNDERPASS AND RCBC 300 15-Jan-23 10-Nov-23
MUNICIPAL ROAD UNDERPASS, STA. 80+858.704 240 15-Jan-23 11-Sep-23
9.0 SPECIAL LARGE RCBC, STA. 80+035.80 180 15-Jan-23 13-Jul-23
ROAD UNDERPASS, STA. 81+665.125 240 16-Mar-23 10-Nov-23
ROAD UNDERPASS, STA. 81+369.876 240 16-Mar-23 10-Nov-23

The Adjusted Master Programme with projected completion on 25-August 2024, should be with respect to the conditions as detailed c) Workability Conditions:
below:
Laying of Cement Treated Base (CTB) and laying of Bituminous Concrete Surface Course and its requisite works will be carried out within the dry
a) Design and Approval Process of New Structures: months of January 2023 through May of years 2023 and 2024 as it is impossible to work with these materials if ground is saturated and precipitation is
frequent.
To Finalize and issue to the Contractor on or before 15-November 2022 the design Drawing and Shop Drawing of Road Underpass
intended for pedestrian Walkway at Main Alignment Sta. 83 250 and for the additional road underpass traversing over Alaminos bypass d) Schedule of Potential De-scoped items:
Road at Main Alignment Sta. 81 339.55.
Client de-scope the contractor with the laying of Bituminous Surface course and its other requisite works. However, the aforementioned items were
b) Potential Change in Design and Layout of Miscellaneous Structures: still included in this Programme so that whoever may work on this item will have a reference schedule to follow.

To Finalize on or before 15-November 2022 any potential changes in design and Layout for the Concrete Panel Fence except for the 762 e) Schedule of Toll Plaza & Roundabout Commencement:
LM fencing along Landco Property because of the reasons detailed in the Contractor's Letter (Ref. No. SCIC-SLEXTR4-SLTC-PMC-2022-
L546 dated 30-June 2022 ). The schedule of works in the Toll Plaza which are primarily of civil and MEFP works and Roundabouts is being on hold by Client due to
potential change in Design. Therefore, the contractor decided to include the schedule of work within this Programme. However, upon receipt of the
To Finalize on or before 30 November 2022 any potential changes in Design of New Jersey Barrier ( Reinforced Concrete Median barrier) final instruction for the said item, we will readily adjust the Programme accordingly.
Because of the reasons detailed in the Contractor's Letter (Ref. No. SCIC-SLEXTR4-SLTC-PMC-2022-L546 dated 30-June 2022 ).